Creating a NEW Chart - OnePager Pro Desktop for Version 7.0

From OnePager Documentation
Jump to: navigation, search

Overview Flow Chart

P70-7 1 2-70-(1)-08052019.png

Procedure

Preparing The Microsoft Project Source Plan

After launching Microsoft Project with your desired source plan, set Flags/Numbers field into the Microsoft Project source plan. This is the Flag that OnePager uses to determine which tasks and milestones to import. Determine which of the tasks and milestones are to be included and set the Flags/Numbers field cell to Yes for these while leaving the remainder of the task's and milestone's Flag field set to No, 0, or blank. At this point your Microsoft Project source plan can be saved and closed. The Desk top version of OnePager Pro does not require that the Microsoft Project source plan be launched first. The part of the procedure described above are in preparation for using the Desk top version of OnePager Pro.

Launching OnePager Pro Desktop

Launch OnePager from the Desktop Icon. The OnePager splash page appears briefly followed by the OnePager Chart Editor form displaying the OnePager Pro Start form as shown below:

P70-7 1 2-70-(2)-08052019.png

At the completion of paragraph 6) when you click the “NEW” button, OnePager displays an abbreviated OnePager choices (OPC) form.

P70-7 1 2-70-(3)-08052019.png

When you click the Select button shown above, OnePager then provides a dropdown menu for you to either choose to use the BROWSE FILES... to select a source plan or click the RECENT MS Project Files... option to access Microsoft Project Server source files as shown above. Clicking the BROWSE FILES… option as shown above accesses a Windows Open form where you can select a Microsoft Project source plan to load as shown here:

P70-7 1 2-70-(4)-08052019.png

When you click the Open button on the Windows Open form above, OnePager loads the selected Microsoft Project source plan and provide you with the expanded OPC form so that you can confirm or edit the settings before OnePager creates the new chart.

P70-7 1 1-70-(4)-08052019.png

As shown above, OnePager displays the loaded Microsoft Project source plan in the Selected File(s) group of the OPC form. You can use the Add/Remove feature (described elsewhere) to edit the choice of Microsoft Project source plan, add additional files to the source packet, and remove files. Clicking the Add/Modify button accesses the Data source selection form as shown below:

P70-7 1 1-70-(5)-08052019.png

It is recommended that the chart name selected refer to both the project and, perhaps, be familiar to the audience that is likely to view the completed OnePager chart. Additionally, notice that the Select Tasks with ‘YES’ in field: is showing Flag20 as a default. Most users select Flag20 to tell OnePager which tasks and milestones to import but any of the 20 Flag fields or any of the 20 Number fields can be used. It is important that the Flag field number represented in this window correspond to the Flag field containing the Yes and No data placed in the Microsoft Project source plan.

The Snapshot date represents the time now or as-of date for the chart you are about to create. If the date created by OnePager does not reflect the status date required, change the date by using the calendar dropdown window. As the source plan changes later on, you can create additional snapshots to show changes consistently.

Finally, note that the Show file mappings checkbox is checked ON as shown above. Checking this checkbox ON and pressing the Next> button takes you to the second page of the OPC form shown below:

P70-7 1 2-70-(5)-08052019.png

This form allows you to edit which Microsoft Project source plan fields are used for various purposes such as the Start field and the Color by field. The Edit current template button also gives you a second opportunity to edit many more initial properties of the chart by accessing the current Template Properties form. Once these choices are confirmed or edited, click the Create new chart button and OnePager imports the flagged data and creates the chart.

Once the chart is created, you can edit by right-clicking task bars and milestone symbols and using the context menus commands. You can also left-click on task bars and milestone symbols and use the editing Icons on the OnePager ribbon tool bar tabs. You can also left-click on a task bar or milestone symbol and use the mouse to drag the selected task bar or milestone symbol up or down from row to row in the chart. When the desired editing is complete, click the Copy to Clipboard button on the OnePager Home ribbon tool bar tab and then paste the chart into a Microsoft PowerPoint presentation, email message, or Microsoft Word document. If the chart contains more than one page, you can choose to copy the entire document, the last page (current page), or a selected numerical page to the clipboard. OnePager can save all charts and snapshots after editing.

Related Links

Creating a NEW Chart via Pull Operation - OnePager Pro

Creating a NEW Chart via Pull Operation - OnePager Express

REPLACING a Snapshot via Pull Operation - OnePager Pro

REPLACING a Snapshot via Pull Operation - OnePager Express

ADDING a Snapshot via Pull Operation - OnePager Pro

ADDING a Snapshot via Pull Operation - OnePager Express

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express

Using the OnePager "Data" Tab's "Selected file(s)" Button

(7.1.2-70)