Opening an EXISTING Project View - OnePager Express Add-in for Version 6.0

From OnePager Documentation
Jump to: navigation, search

Overview

Once project views are created, they can be re-opened from the OnePager Express Start form. The purpose of this scenario is to retrieve a project view for inclusion in another presentation or to further edit the project view.

Using this methodology may or may not import new or old data from Microsoft Excel. However, Microsoft Excel needs to be launched so that you can access the OnePager Express button.

With OnePager Express (OPX) you have the option to install both the Add-in and desktop applications. As an alternative you may double-click on the desired project view’s .TAM file to open an existing project view as described in the article at Opening an EXISTING Project View - OnePager Express Desktop.

The steps to open an EXISTING project view from within Microsoft Excel are shown in the steps below:

X60-7 6 1-53-(1)-09162016.png

Procedures

1) Launch Microsoft Excel.

2) With Microsoft Excel running, launch OnePager and click the OPEN button on the OnePager Excel Start' form. OnePager will display a list of recently-used project views and a BROWSE FILES… option. If you click BROWSE FILES…, you will get a Windows Open form where you may select a project view to open.

X60-7 6 1-53-(2)-09162016.png

3) Selecting a project view to open will tell OnePager to retrieve and display it. Source plan data may or may not be imported from the selected Microsoft Excel source plan.

4) Once the project view is displayed and available, you may edit, save, and copy the project view to a Microsoft PowerPoint slide or elsewhere as described previously.

5) Once a project view with multiple snapshots is opened, you may want to switch between snapshots. There are two methods to do this.

a) The first is to use the forward/back arrows on the View tab to move between snapshot dates.
b) The second method is to click the List All button View tab which will display a list of all available snapshot dates for the project view as shown below:
X60-7 6 1-60-(3)-01302017.png

6) In addition to editing the opened project view and switching between snapshots you can also use the Data tab on the ribbon to replace snapshots, add snapshots, and perform custom updates. The Data tab on the ribbon appears as shown below:

X53-7 6 1-53-(4)-11272015.png

Related Links

Creating a NEW Project View via Pull Operation - OnePager Pro

Creating a NEW Project View via Pull Operation - OnePager Express

REPLACING a Snapshot via Pull Operation - OnePager Pro

REPLACING a Snapshot via Pull Operation - OnePager Express

ADDING a Snapshot via Pull Operation - OnePager Pro

ADDING a Snapshot via Pull Operation - OnePager Express

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express

Using the OnePager "Data" Tab's "Selected file(s)" Button

(7.6.1-60)