Creating a NEW Project View from Microsoft Project Server/Online for OnePager Live

From OnePager Documentation
Jump to: navigation, search

Overview

7.13.1-OPL Not Edited beyond this point.

The purpose of these articles is to acquaint you with the new pull features of OnePager Pro (OPP) and Express (OPX). There are eight (8) articles in this series, four (4) providing examples of the pull feature for OPP and four (4) for OPX. Please see the links at the end of this article to access the rest of the series.

Creating a NEW project view via pull is not the main reason why OnePager has pull operations. This workflow is most useful only when you want to fill an empty Project View Editor (PVE) by making a new project view. The real power of the pull operation is to let you do repeated snapshot REPLACE and snapshot add operations on an open project view. In other words, the pull operation’s main purpose is to let you update the on-screen project view as you edit its source file(s). The pull update operation is discussed in other articles in this series.

What is a Pull Operation?

A pull operation starts in the PVE. That is, you already have OnePager running and decide to update the open project view or (rarely) create a new project view. In contrast, a push operation begins in the OnePager Pro Start from which you make a new project view or update an existing project view.

We added the pull operation because we found that our users were often creating a project view, finding something in the source file that they needed to change, going back to the source file, making the change, and then re-launching OnePager to update the project view.

The pull update lets you open a project view and update it repeatedly as you edit its source file(s). After each set of changes to the source file(s), you can quickly see the effect on the screen by using OnePager’s new Data tab to pull the source file changes into the project view.

You’ll see this more when you read the articles REPLACING a Snapshot via Pull Operation - OnePager Pro and ADDING a Snapshot via Pull Operation - OnePager Pro.

The example below illustrates creating a new project view.

Example

1) Let’s suppose you have a Microsoft Project plan that you want to present to two different audiences – Your Project Management Office (PMO) and your customer. However, before the presentation you want to quickly examine the two project views made by OnePager side-by-side.

2) In preparation, you flag the rows to be shown to the PMO using Microsoft Project’s Flag20 column and put a Yes in the appropriate rows. You also decide to use Flag10 to show those rows that you want to show in your presentation to the customer. You insert both the Flag20 and Flag10 columns into the plan as shown below:

P53-7 13 1-53-(1)-12022015.png

Prepare First Project View

3) For the sake of this example, let's first use the OnePager Pro desktop application to access the Microsoft Project plan using the Flag20 flag column shown above.

4) After the steps covered in the article above are completed, OnePager will generate a project view with the title shown below, using the Flag20 column, and designating the snapshot with the date shown. The resulting project view will look like the following:

P53-7 13 1-53-(5)-12022015.png

5) Since we are using the desktop application of OPP, it was not necessary to launch Microsoft Project first. As long as you’ve properly prepared your Microsoft Project plan source file just launching OPP from the desktop icon is basically all that is necessary to utilize the new pull feature.

6) At this point it is recommended that you save this first project view for access later.

Prepare a Second Project View

7) There are two ways of creating the second project view from the same Microsoft Project source file:

(1) After saving the first project view, close the OPP desktop application and repeat the above process by opening the second project view and then using Flag10 to select the tasks.
(2) Remain in the current OPP PVE window and create a second new project view from there.

8) Here we will demonstrate the second (2) method as it is more efficient.

9) With the above project view saved and visible in the PVE window, click on the File tab and then click the New… tab on the page that appears:

P53-7 13 1-53-(6)-12022015.png

10) When you click the New… button as shown above, OnePager will display the OnePager choices (OPC) form. You may now use the form to create the project view for the customer by giving the new project view a new name, specifying that the flag column to be used is Flag10, and specifying the appropriate snapshot date as shown in the sequence below:

P53-7 13 1-53-(7)-12022015.png

11) When the file is selected, the OPC form will expand and provide you with the ability to uniquely name the new project view, specify the flag field to use, and specify the snapshot date as we have done in the illustration below:

P53-7 13 1-53-(8)-12022015.png

12) With the new settings confirmed in the OPC form, click the Create new project view and OnePager will use your new settings to create the second project view and display it as shown below:

P53-7 13 1-53-(9)-12022015.png

13) In this example, we used the OPP desktop application to create two project views from the same Microsoft Project source file but using different flag columns. Now that the second project view is created, we recommend that it too be saved for future access.

Compare Results, Edit, Copy to PowerPoint

14) Once you are satisfied with your project views you may save them, copy them into PowerPoint presentations, or share time in other ways.

15) The pull feature is an easy, fast, and convenient way to create multiple project views which will make you more efficient.

Related Links

Creating a NEW Project View - OnePager Live 7.1.1-OPL

Creating a NEW Project View from Microsoft Project Server/Online 7.13.1-OP

Creating Another New Project View - OnePager LIve 7.3.1-OPL

Opening an EXISTING Project View - OnePager LIve 7.5.1-OPL

ADDING a Snapshot - OnePager Live 7.7.1-OPL

ADDING a Snapshot from Microsoft Project Server/Online 7.15.1-OP

REPLACING a Snapshot - OnePager Live 7.9.1-OPL

REPLACING a Snapshot with Microsoft Project Server/Online 7.14.1-OPL

Custom Update (Replacing) of a Snapshot with Microsoft Project Server/Online 7.1.16.1-OP

Using the OnePager Live Data Tab's Selected file(s) Button 7.17.1-OPL

Merging the Wrong Tasks into a Project View from Microsoft Project 7.11.1-OPL

Merging the Wrong Tasks into a Project View from Microsoft Excel 7.12.1-OPL


(7.13.1-OPL)