There are four '''endpoints''' definable in OnePager for each task.  Although '''deadlines''' can be applied to both tasks and milestones, the four '''endpoints''' apply only to tasks.
 
There are four '''endpoints''' definable in OnePager for each task.  Although '''deadlines''' can be applied to both tasks and milestones, the four '''endpoints''' apply only to tasks.
  
Accordingly, and for all practical purposes, the four possible '''endpoints''' ('''Endpoint1, Endpoint2, Endpoint3, and Endpoint4''') can be thought of as additional '''deadlines''' for tasks. As you will see, the control and the behavior of all four '''endpoints''' are identical to that discussed for '''deadlines'''.  (See:  [[Deadlines for Version 6.0 (OnePager Pro) | Deadlines for OnePager Pro]] 10.9.1-60). As an additional thought, you may consider the four '''endpoints''' as task-oriented milestones as they occupy the same row as their parent task.
+
Accordingly, and for all practical purposes, the four possible '''endpoints''' ('''Endpoint1, Endpoint2, Endpoint3, and Endpoint4''') can be thought of as additional '''deadlines''' for tasks. As you will see, the control and the behavior of all four '''endpoints''' are identical to that discussed for '''deadlines'''.  (See:  [[Deadlines for Version 6.0 (OnePager Pro) | Deadlines for OnePager Pro]]<!--10.9.1-60-->). As an additional thought, you may consider the four '''endpoints''' as task-oriented milestones as they occupy the same row as their parent task.
  
 
By convention and as a default, the initial association of '''Endpoints 1 through 4''' to Microsoft Project '''source plan''' fields is as follows:
 
By convention and as a default, the initial association of '''Endpoints 1 through 4''' to Microsoft Project '''source plan''' fields is as follows:
Line 25: Line 25:
  
 
<center>[[File:P60-10_11_1-60-(2)-02102017.png]]</center>
 
<center>[[File:P60-10_11_1-60-(2)-02102017.png]]</center>
<center>P60-10_11_1-60-(2)-02102017.png</center>
+
<!--<center>P60-10_11_1-60-(2)-02102017.png</center>-->
  
 
2) Clicking the '''Next&gt;''' button with the '''Show field mappings''' checkbox checked brings you to the second page of the '''OPC''' form shown below:
 
2) Clicking the '''Next&gt;''' button with the '''Show field mappings''' checkbox checked brings you to the second page of the '''OPC''' form shown below:
  
 
<center>[[File:P60-10_11_1-60-(3AA)-03072017.png]]</center>
 
<center>[[File:P60-10_11_1-60-(3AA)-03072017.png]]</center>
<center>P60-10_11_1-60-(3AA)-03072017.png</center>
+
<!--<center>P60-10_11_1-60-(3AA)-03072017.png</center>-->
  
 
3) Clicking the '''Edit current template…''' button takes you to the '''Template Properties''' form where you should navigate to the '''Task Bars''' tab and the '''Endpoints''' checkbox in the '''Gantt Bar Decorations''' group of the form which is shown below:
 
3) Clicking the '''Edit current template…''' button takes you to the '''Template Properties''' form where you should navigate to the '''Task Bars''' tab and the '''Endpoints''' checkbox in the '''Gantt Bar Decorations''' group of the form which is shown below:
  
 
<center>[[File:P60-10_11_1-60-(4A)-02102017.png]]</center>
 
<center>[[File:P60-10_11_1-60-(4A)-02102017.png]]</center>
<center>P60-10_11_1-60-(4A)-02102017.png</center>
+
<!--<center>P60-10_11_1-60-(4A)-02102017.png</center>-->
  
 
4) Now, clicking the '''Endpoint Properties''' button will show the '''Set endpoint properties''' form shown below:
 
4) Now, clicking the '''Endpoint Properties''' button will show the '''Set endpoint properties''' form shown below:
  
 
<center>[[File:P60-10_11_1-60-(5)-02102017.png]]</center>
 
<center>[[File:P60-10_11_1-60-(5)-02102017.png]]</center>
<center>P60-10_11_1-60-(5)-02102017.png</center>
+
<!--<center>P60-10_11_1-60-(5)-02102017.png</center>-->
  
 
5) The above form is almost identical to the '''Set deadline properties''' form. The difference is the '''Show this endpoint''' checkbox which refers to the dropdown menu shown above whereby you may select which '''endpoint''' to control. In effect, this form is four (4) forms in one and allows you to turn on or off each individual '''endpoint''' and configure the properties for each separately.
 
5) The above form is almost identical to the '''Set deadline properties''' form. The difference is the '''Show this endpoint''' checkbox which refers to the dropdown menu shown above whereby you may select which '''endpoint''' to control. In effect, this form is four (4) forms in one and allows you to turn on or off each individual '''endpoint''' and configure the properties for each separately.
Line 47: Line 47:
  
 
<center>[[File:P60-10_11_1-60-(6)-02102017.png]]</center>
 
<center>[[File:P60-10_11_1-60-(6)-02102017.png]]</center>
<center>P60-10_11_1-60-(6)-02102017.png</center>
+
<!--<center>P60-10_11_1-60-(6)-02102017.png</center>-->
  
 
7) Now that we have defined '''endpoints''' with distinct properties for all tasks in our example, we go back to the '''Template Properties''' form, click the '''Save and use''' button to get back to the second page of the '''OPC''' form, and clicked the '''Create new project view''' button. OnePager will produce the following project view:  
 
7) Now that we have defined '''endpoints''' with distinct properties for all tasks in our example, we go back to the '''Template Properties''' form, click the '''Save and use''' button to get back to the second page of the '''OPC''' form, and clicked the '''Create new project view''' button. OnePager will produce the following project view:  

Latest revision as of 20:14, 10 April 2017

About Modify Endpoints

There are four endpoints definable in OnePager for each task. Although deadlines can be applied to both tasks and milestones, the four endpoints apply only to tasks.

Accordingly, and for all practical purposes, the four possible endpoints (Endpoint1, Endpoint2, Endpoint3, and Endpoint4) can be thought of as additional deadlines for tasks. As you will see, the control and the behavior of all four endpoints are identical to that discussed for deadlines. (See: Deadlines for OnePager Pro). As an additional thought, you may consider the four endpoints as task-oriented milestones as they occupy the same row as their parent task.

By convention and as a default, the initial association of Endpoints 1 through 4 to Microsoft Project source plan fields is as follows:

  • Endpoint 1: Start Date.
  • Endpoint 2: Finish Date.
  • Endpoint 3: Baseline Start Date.
  • Endpoint 4: Baseline Finish Date.

Controls are provided as described below whereby you can change the endpoint association with Microsoft Project source plan fields.

Displaying Endpoints

For OnePager to properly display your endpoints, you must first define the endpoint field in Microsoft Project and map them to OnePager through the OnePager choices (OPC) form. A sample, Microsoft Project source plan is shown below with both deadline and endpoint definitions:

P52-10 11-(1)-06012015.png

In the sample above, we see the typical task information with Flag20 used to signal OnePager which rows to import, the Microsoft Project Deadline field and four Date fields (Date1, Date2, Date3, and Date4) which will be used to import information to OnePager representing Endpoints 1 through 4 respectively.

1) When the OnePager button is clicked on the Microsoft Project tool bar and you click the NEW button on the OnePager Pro Start form, OnePager will display the first page of the OPC form as shown below:

P60-10 11 1-60-(2)-02102017.png

2) Clicking the Next> button with the Show field mappings checkbox checked brings you to the second page of the OPC form shown below:

P60-10 11 1-60-(3AA)-03072017.png

3) Clicking the Edit current template… button takes you to the Template Properties form where you should navigate to the Task Bars tab and the Endpoints checkbox in the Gantt Bar Decorations group of the form which is shown below:

P60-10 11 1-60-(4A)-02102017.png

4) Now, clicking the Endpoint Properties button will show the Set endpoint properties form shown below:

P60-10 11 1-60-(5)-02102017.png

5) The above form is almost identical to the Set deadline properties form. The difference is the Show this endpoint checkbox which refers to the dropdown menu shown above whereby you may select which endpoint to control. In effect, this form is four (4) forms in one and allows you to turn on or off each individual endpoint and configure the properties for each separately.

6) The form above covers up two important controls that need to be addressed: The Show this endpoint checkbox and the Field dropdown menu by which you tell OnePager which Microsoft Project source plan field will be used for each particular endpoint. These controls are shown here:

P60-10 11 1-60-(6)-02102017.png

7) Now that we have defined endpoints with distinct properties for all tasks in our example, we go back to the Template Properties form, click the Save and use button to get back to the second page of the OPC form, and clicked the Create new project view button. OnePager will produce the following project view:

P52-10 11-(7)-06012015.png

Modifying Endpoint Properties

8) Configuring Other Endpoint Properties. The above discussion covered the set up and initial display of endpoints. Recall that endpoint controls are exactly identical to the controls for deadlines. The exception is only for the necessity to turn on the individual endpoints through their respective Show this endpoint checkbox and to enter the Microsoft Project source plan field that will be used for the respective endpoints in the Field dropdown menu of the Set endpoint properties form.

9) Setting Endpoint Properties for Individual Tasks. Endpoint properties may be set or changed for individual tasks. A prerequisite for modifying individual endpoint properties is the necessity for endpoint data to be imported from the Microsoft Project source plan. Some individual task endpoint properties may be changed by selecting the desired task or tasks with a left-click operation and then right-clicking one of the selected task to show the context menu below:

P52-10 11-(8)-06012015.png
a) Select the Format… command which brings up the Change Marker Properties form. NExt, navigate to the Endpoints tab, which will display the endpoint control options shown below:
P52-10 11-(9)-06012015.png
b) From the Endpoints tab of the form above, you are able to turn the selected endpoint off or on, show the endpoint connector to the task and display or turn off the endpoint date label.
c) For example, using the Deadlines-Endpoints Example previously illustrated above, suppose we want to make the following changes:
  • Turn off the display of Endpoint 1 for Task B
  • Show the Endpoint connector for Endpoint 1 to Task C
  • Show the Date Label for Endpoint 4 for Task C under the task
d) For each task we select the task with a left-click, then right-click to get to the context menu, select the Format… command to get to the Change Marker Properties form and finally go to the Endpoints tab.
e) We do these steps for each of the tasks involved starting with Task C where we’ll make one change to Endpoint 1 and then to Task C where we’ll make a change to Endpoints 1 and 4. After making these changes the project view will look like this:
P52-10 11-(10)-06012015.png

(10.11.1-60)