===Overview===
+
==Overview==
  
As with the previous version of OnePager Pro, version 6.1 of '''OPP''' can be launched from a '''desktop''' icon as well as from within Microsoft Project ('''Add-in''').
+
1) As with the previous version of OnePager Pro, version 6.1 of '''OPP''' can be launched from a '''Desktop''' icon as well as from within Microsoft Project ('''Add-in''').
  
1) Please note that after selecting the '''Add-in''' launch option that you will not be able to launch the OnePager '''Desktop''' application.   
+
2) Please note that after selecting the '''Add-in''' launch option that you are not be able to launch the OnePager '''Desktop''' application.   
  
2) Only one of these applications ('''Add-in''' or '''Desktop''') may be active at a time.   
+
3) Only one of these applications ('''Add-in''' or '''Desktop''') can be active at a time.   
  
3) If you attempt to launch both, a warning message will appear as shown below.
+
4) If you attempt to launch both, a warning message appears as shown below.
  
 
<center>[[File:P53-3_0_1-53-(01)-11062015.png]]</center>
 
<center>[[File:P53-3_0_1-53-(01)-11062015.png]]</center>
  
4) Further note that as mentioned in [[What's New with OnePager Release 6.1?]] 0.4-61, this new version has enhanced features such as '''Task Link Upgrades''' and  '''Time Axis Upgrades''' to name a few.   
+
5) Further note that as mentioned in [[What's New with OnePager Release 6.1?]] <!--0.4-61-->, this new version has enhanced features such as '''Task Link Upgrades''' and  '''Time Axis Upgrades''' to name a few.   
  
5) This article covers the '''Getting Started''' process when you launch '''OPP''' from Microsoft Project.   
+
6) This article covers the '''Getting Started''' process when you launch '''OPP''' from Microsoft Project.   
  
6) The article which provides '''Getting Started''' guidance when launching from the '''Desktop''' icon is at [[Getting Started with OnePager Pro Version 6.1 Desktop | Getting Started with OnePager Pro Desktop]] 3.0.1.2-61.
+
7) The article which provides '''Getting Started''' guidance when launching from the '''Desktop''' icon is at [[Getting Started with OnePager Pro Version 6.1 Desktop | Getting Started with OnePager Pro Desktop]]. <!--3.0.1.2-61.-->
  
===Launching OnePager Pro for the First Time===
+
==Launching OnePager Pro for the First Time==
  
 
1)  The '''OPP Add-in''' automatically displays the '''OnePager''' icon on the Microsoft Project ribbon once OnePager is installed. That tool bar looks like this:
 
1)  The '''OPP Add-in''' automatically displays the '''OnePager''' icon on the Microsoft Project ribbon once OnePager is installed. That tool bar looks like this:
Line 23: Line 23:
 
<center>[[File:P53-3_0_1-53-(1)-11062015.png]]</center>
 
<center>[[File:P53-3_0_1-53-(1)-11062015.png]]</center>
  
2) Clicking the '''OnePager Pro''' button will take you to the Project View Editor ('''PVE'''). Clicking the '''Templates…''' button will let you edit the templates provided with the product. For now, it is simplest to use the default '''Template'''.  You can learn how '''Templates''' let you customize and standardize graph features later in this document.
+
2) Clicking the '''OnePager Pro''' button takes you to the Project View Editor ('''PVE'''). Clicking the '''Templates…''' button lets you '''edit'''' the '''Templates''' provided with the product. For now, it is simplest to use the default '''Template'''.  You can learn how '''Templates''' let you customize and standardize graph features later in this document.
  
3) Before you launch '''OPP''', it is a good idea to unhide the Microsoft Project '''flag''' field you intend to use. (Note that when you unhide a field in Microsoft Project, that field may now appear in some of Microsoft Project’s standard reports. Do not forget to hide the field again before generating such reports if you do not want the field to appear in those reports.)  The selected '''flag''' field allows you to control which tasks get graphed and to store those choices in Microsoft Project for future use. For example, the '''flag''' field (e.g., Flag20) is shown below:
+
3) Before you launch '''OPP''', it is a good idea to unhide the Microsoft Project '''flag''' field you intend to use. (Note that when you unhide a field in Microsoft Project, that field can now appear in some of Microsoft Project’s standard reports. Do not forget to hide the field again before generating such reports if you do not want the field to appear in those reports.)  The selected '''flag''' field allows you to control which tasks get graphed and to store those choices in Microsoft Project for future use. For example, the '''flag''' field (e.g., Flag20) is shown below:
  
 
<center>[[File:P61-3_0_1-61-(2)-10232017.png]]</center>
 
<center>[[File:P61-3_0_1-61-(2)-10232017.png]]</center>
<center>P61-3_0_1-61-(2)-10232017.png</center>
+
<!--center>P61-3_0_1-61-(2)-10232017.png</center-->
  
4) To control which tasks get graphed, specify the Microsoft Project '''flag''' field (e.g. Flag1, Flag2 … Flag20) that you wish to use. '''Number''' fields may also be used the same as the '''flag''' fields where a '''1''' in a '''Number''' field indicates '''Yes'''and a '''0''' in a '''Number''' field indicates '''No'''.  Unhide that field in Microsoft Project by right-clicking in the field header area and selecting '''Insert Column''':
+
4) To control which tasks get graphed, specify the Microsoft Project '''flag''' field (e.g. Flag1, Flag2 … Flag20) that you wish to use. '''Number''' fields can also be used the same as the '''flag''' fields where a '''1''' in a '''Number''' field indicates '''Yes'''and a '''0''' in a '''Number''' field indicates '''No'''.  Unhide that field in Microsoft Project by right-clicking in the field header area and selecting '''Insert Column''':
  
 
<center>[[File:P61-3_0_1-61-(3)-10232017.png]]</center>
 
<center>[[File:P61-3_0_1-61-(3)-10232017.png]]</center>
<center>P61-3_0_1-61-(3)-10232017.png</center>
+
<!--center>P61-3_0_1-61-(3)-10232017.png</center-->
  
 
5) Now put a '''Yes''' in this '''flag''' field for any task that you want to graph:
 
5) Now put a '''Yes''' in this '''flag''' field for any task that you want to graph:
  
 
<center>[[File:P61-3_0_1-61-(4)-10232017.png]]</center>
 
<center>[[File:P61-3_0_1-61-(4)-10232017.png]]</center>
<center>P61-3_0_1-61-(4)-10232017.png</center>
+
<!--center>P61-3_0_1-61-(4)-10232017.png</center-->
  
 
:a) When making your first project view, we strongly recommend that you mark 50 or fewer tasks with '''Yes'''.
 
:a) When making your first project view, we strongly recommend that you mark 50 or fewer tasks with '''Yes'''.
Line 48: Line 48:
 
:d) There are two solutions to this issue: :
 
:d) There are two solutions to this issue: :
  
::(1) Define the dates for your tasks and milestones in Microsoft Project. This will overwrite any default dates that Microsoft Project is assigning, and will make your project schedule more consistent with your '''OPP''' timeline. :
+
::(1) Define the dates for your tasks and milestones in Microsoft Project. This overwrites any default dates that Microsoft Project is assigning, and makes your project schedule more consistent with your '''OPP''' timeline. :
 
+
 
::(2) Remove the '''dateless tasks''' from your '''OPP''' graph. You can leave them in project, but by removing them from the '''OPP''' graph, you won't have to explain why certain tasks/milestones are appearing in weird places when they really should not.  As a rule of thumb, we recommend defining dates for all tasks and milestones, especially when it comes to graph generation.
 
::(2) Remove the '''dateless tasks''' from your '''OPP''' graph. You can leave them in project, but by removing them from the '''OPP''' graph, you won't have to explain why certain tasks/milestones are appearing in weird places when they really should not.  As a rule of thumb, we recommend defining dates for all tasks and milestones, especially when it comes to graph generation.
  
Line 55: Line 54:
  
 
<center>[[File:P61-1_6-(2)-61-10232017.png]]</center>
 
<center>[[File:P61-1_6-(2)-61-10232017.png]]</center>
<center>P61-1_6-(2)-61-10232017.png</center>
+
<!--center>P61-1_6-(2)-61-10232017.png</center-->
  
 
7) The '''OnePager Pro Start''' form provides you with three options:
 
7) The '''OnePager Pro Start''' form provides you with three options:
  
:a) '''NEW'''  Clicking the '''NEW''' button will bring up the '''OnePager Pro choices''' ('''OPC''') form.
+
:a) '''NEW'''  Clicking the '''NEW''' button brings up the '''OnePager Pro choices''' ('''OPC''') form.
  
:b) '''UPDATE'''  Clicking the '''UPDATE''' button will allow you to '''BROWSE FILES''' for an existing project view or select a recently-opened project view.
+
:b) '''UPDATE'''  Clicking the '''UPDATE''' button allows you to '''BROWSE FILES''' for an existing project view or select a recently-opened project view.
  
:c) '''OPEN'''  Clicking the '''OPEN''' button will allow you to '''BROWSE FILES''' for an existing project view or select a recently-opened project view.  Once selected and opened, the project view is available for editing.
+
:c) '''OPEN'''  Clicking the '''OPEN''' button allows you to '''BROWSE FILES''' for an existing project view or select a recently-opened project view.  Once selected and opened, the project view is available for '''editing'''.
  
===Creating a New Project View===
+
==Creating a New Project View==
  
8) Clicking the '''NEW''' button brings up the '''OPC''' form as shown below:
+
1) Clicking the '''NEW''' button brings up the '''OPC''' form as shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(6)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(6)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(6)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(6)-04302018.png</center-->
  
 
===Options on the New OnePager Choices form===
 
===Options on the New OnePager Choices form===
  
9) We’ve enhanced the '''OPC''' form to give you more options for selecting '''source plans'''.  The illustration above shows that '''OPP''' was initiated from Microsoft Project with the '''source plan''' shown in the '''Selected File(s)''' group shown above.  The '''Add/Remove''' button gives you the capability to '''add''' more '''source plans''' to the '''source packet''' or, for multiple file packets, to '''remove''' files.
+
2) We’ve enhanced the '''OPC''' form to give you more options for selecting '''source plans'''.  The illustration above shows that '''OPP''' is initiated from Microsoft Project with the '''source plan''' shown in the '''Selected File(s)''' group shown above.  The '''Add/Remove''' button gives you the capability to '''add''' more '''source plans''' to the '''source packet''' or, for multiple file packets, to '''remove''' files.
  
 
:a) Clicking the '''Add/Remove''' button brings up the '''Data source selection''' form as shown below:
 
:a) Clicking the '''Add/Remove''' button brings up the '''Data source selection''' form as shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(7)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(7)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(7)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(7)-04302018.png</center-->
  
:b) The '''Data source selection''' form displays the current '''source plan''' that was loaded with Microsoft Project when you clicked the '''OnePager Pro'''.  This form lets you '''Add''' more Microsoft Project '''source plan''' to create a multi-project project view or '''Remove''' a '''source plan''' from a multi-file '''source packet'''.  These options are detailed below.
+
:b) The '''Data source selection''' form displays the current '''source plan''' that was loaded with Microsoft Project when you clicked the '''OnePager Pro''' button.  This form lets you '''Add''' more Microsoft Project '''source plan''' to create a multi-project project view or '''Remove''' a '''source plan''' from a multi-file '''source packet'''.  These options are detailed below.
  
 
===Adding a New Source Plan===
 
===Adding a New Source Plan===
Line 88: Line 87:
  
 
<center>[[File:P61-3_0_1_1-61-(8)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(8)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(8)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(8)-04302018.png</center-->
  
::i) Clicking the '''BROWSE FILES…''' option displays a Window’s '''Open''' form from which you may select a Microsoft Project '''source plan''' to add to the '''source packet'''.  A sample '''Open''' form is shown below:
+
::i) Clicking the '''BROWSE FILES…''' option displays a Window’s '''Open''' form from which you can select a Microsoft Project '''source plan''' to add to the '''source packet'''.  A sample '''Open''' form is shown below:
  
<center>[[File:P61-3_0_1-61-(9)-10232017.png]]</center>
+
<center>[[File:P61-3_0_1_1-61-(9)-05012018.png]]</center>
<center>P61-3_0_1-61-(9)-10232017.png</center>
+
<!--center>P61-3_0_1_1-61-(9)-05012018.png</center-->
  
 
::ii) When you select a desired Microsoft Project '''source plan''' and click the '''Open''' button as shown above, '''OPP''' adds the '''source plan''' to the '''source packet''' and displays it in the '''Data source selection''' window as shown below:
 
::ii) When you select a desired Microsoft Project '''source plan''' and click the '''Open''' button as shown above, '''OPP''' adds the '''source plan''' to the '''source packet''' and displays it in the '''Data source selection''' window as shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(10)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(10)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(10)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(10)-04302018.png</center-->
  
::iii) The selected '''source plan''' is added to the '''source packet''' as shown above.  '''OPP''' shows the path name of the '''source plan''' in the window if you hover the mouse over the '''source plan''' name.
+
::iii) The selected '''source plan''' is added to the '''source packet''' as shown above.  '''OPP''' shows the '''path name''' of the '''source plan''' in the window if you hover the mouse over the '''source plan''' name.
  
::iv) If you select a recently used '''source plan''' from the dropdown menu displayed when the '''Add''' button is clicked ('''Data source selection''' form), '''OPP''' will add that '''source plan''' to the '''source packet'''.
+
::iv) If you select a recently used '''source plan''' from the dropdown menu displayed when the '''Add''' button is clicked ('''Data source selection''' form), '''OPP''' adds that '''source plan''' to the '''source packet'''.
  
 
===Removing a Source Plan===
 
===Removing a Source Plan===
Line 109: Line 108:
  
 
<center>[[File:P61-3_0_1_1-61-(11)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(11)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(11)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(11)-04302018.png</center-->
  
  
 
<center>[[File:P61-3_0_1_1-61-(12)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(12)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(12)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(12)-04302018.png</center-->
  
 
===Other Choices to Make===
 
===Other Choices to Make===
  
10) Moving on to the other groups of the '''OPC''' form, you are asked to confirm a few things before you build the project view. '''OPP''' makes good guesses for each of these choices, but you can change any of them:
+
3) Moving on to the other groups of the '''OPC''' form, you are asked to confirm a few things before you build the project view. '''OPP''' makes good guesses for each of these choices, but you can change any of them:
  
 
<center>[[File:P61-3_0_1_1-61-(15)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(15)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(15)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(15)-04302018.png</center-->
  
 
:a) '''Starting Template''': The current '''Template''' determines which fields get imported from Microsoft Project and how the initial project view looks.  '''OPP''' ships with many sample '''Templates''', but you can also customize your own '''Templates'''.  
 
:a) '''Starting Template''': The current '''Template''' determines which fields get imported from Microsoft Project and how the initial project view looks.  '''OPP''' ships with many sample '''Templates''', but you can also customize your own '''Templates'''.  
Line 136: Line 135:
  
 
:::i) Either click the '''Select all tasks''' radio button to graph everything or choose a '''flag''' field. You can make several project views from a single Microsoft Project '''source plan''', each using a different '''flag''' or '''number''' field.  In '''OPP''' if no '''flags''' are set to '''Yes''', '''OPP''' provides you with a warning message.
 
:::i) Either click the '''Select all tasks''' radio button to graph everything or choose a '''flag''' field. You can make several project views from a single Microsoft Project '''source plan''', each using a different '''flag''' or '''number''' field.  In '''OPP''' if no '''flags''' are set to '''Yes''', '''OPP''' provides you with a warning message.
:::ii) Clicking the '''Select tasks by custom filter''' button activates the '''Edit filters...''' button.  Clicking the '''Edit filters...''' button takes you to a form that controls the new '''Conditional Import Filters''' feature.  Please see the article titled [[Conditional Import for Version 6.1 (Portal) | Conditional Import Filters (Portal)]] 7.18.1-61 for more detailed on the use of this feature.
+
:::ii) Clicking the '''Select tasks by custom filter''' button activates the '''Edit filters...''' button.  Clicking the '''Edit filters...''' button takes you to a form that controls the new '''Conditional Import Filters''' feature.  Please see the article titled [[Conditional Import for Version 6.1 (Portal) | Conditional Import Filters (Portal)]] <!--7.18.1-61--> for more detailed on the use of this feature.
  
 
:d) '''Snapshot Date''': This is the date of the report and lets you keep track of how schedules change over time. Each project view can have many snapshots.  
 
:d) '''Snapshot Date''': This is the date of the report and lets you keep track of how schedules change over time. Each project view can have many snapshots.  
  
11) The '''Show field mappings''' checkbox near the bottom of the form can be checked.  When this box is checked you have a chance to review and change the Microsoft Project '''field mappings''' to '''OPP''' before you make your first project view.  To do this, check the box and click the '''Next&gt;''' button.    You now see the following form:
+
4) The '''Show field mappings''' checkbox near the bottom of the form can be checked.  When this box is checked you have a chance to review and change the Microsoft Project '''field mappings''' to '''OPP''' before you make your first project view.  To do this, check the box and click the '''Next&gt;''' button.    You now see the following form:
  
 
<center>[[File:P61-3_0_1_1-61-(16)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(16)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(16)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(16)-04302018.png</center-->
  
12) Notice in the form above that '''OPP''' has relied on the current '''Template''' to make some guesses on which Microsoft Project fields should be used in making the graph.    You can easily change any of these '''field mappings''' by making selections from the dropdown menus.  For example, we show below how to change the '''Finish Date''' :
+
5) Notice in the form above that '''OPP''' has relied on the current '''Template''' to make some guesses on which Microsoft Project fields should be used in making the graph.    You can easily change any of these '''field mappings''' by making selections from the dropdown menus.  For example, we show below how to change the '''Finish Date''' :
  
 
<center>[[File:P61-3_0_1_1-61-(17)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(17)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(17)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(17)-04302018.png</center-->
  
 
===Making the Graph===
 
===Making the Graph===
  
13) Once you are satisfied with the '''field mappings''', click the '''Create new project view''' button to import your selected data and create a project view.  After a second or two you see a screen that looks like this:
+
6) Once you are satisfied with the '''field mappings''', click the '''Create new project view''' button to import your selected data and create a project view.  After a second or two you see a screen that looks like this:
  
 
<center>[[File:P61-3_0_1_1-61-(18)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(18)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(18)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(18)-04302018.png</center-->
  
14) Note that each task or milestone was '''color''' coded based on the value in the '''Resource Names''' field.   
+
7) Note that each task or milestone was '''color''' coded based on the value in the '''Resource Names''' field.   
  
 
:a) The '''Legend''' contains an optional diagram near the bottom explaining that the bars inside the Gantt bars represent '''percent complete''' extracted from Microsoft Project.
 
:a) The '''Legend''' contains an optional diagram near the bottom explaining that the bars inside the Gantt bars represent '''percent complete''' extracted from Microsoft Project.
Line 166: Line 165:
  
 
<center>[[File:P61-3_0_1_1-61-(19)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(19)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(19)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(19)-04302018.png</center-->
  
 
===Opening a Project View===
 
===Opening a Project View===
  
15) The right-most button on the '''OPC''' form is the '''OPEN''' button.  Clicking the '''OPEN''' button displays a dropdown menu which happens to be the same for the '''UPDATE''' button.  The options in the dropdown are discussed below:
+
8) The right-most button on the '''OPC''' form is the '''OPEN''' button.  Clicking the '''OPEN''' button displays a dropdown menu which happens to be the same for the '''UPDATE''' button.  The options in the dropdown are discussed below:
  
 
<center>[[File:P61-3_0_1_1-61-(19A)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(19A)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(19A)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(19A)-04302018.png</center-->
  
:a) Clicking the '''BROWSE FILES...''' option brings up a Windows '''Open''' form from which you can select a '''.TAM''' that you want to open.  Selecting the desired '''.TAM''' causes '''OPP''' to display the selected project view.  From this position, you may edit the project view, save it, or share it with others.
+
:a) Clicking the '''BROWSE FILES...''' option brings up a Windows '''Open''' form from which you can select a '''.TAM''' that you want to open.  Selecting the desired '''.TAM''' causes '''OPP''' to display the selected project view.  From this position, you can '''edit''' the project view, save it, or share it with others.
  
:b) Clicking any of the '''RECENT project views''' items in the dropdown menu above causes '''OPP''' to load the associated '''.TAM''' into the Project View Editor ('''PVE''') where you may also edit the project view, save it, or share it with others.
+
:b) Clicking any of the '''RECENT project views''' items in the dropdown menu above causes '''OPP''' to load the associated '''.TAM''' into the Project View Editor ('''PVE''') where you can also '''edit''' the project view, save it, or share it with others.
  
 
===Updating a Project View with Changes Made to the Microsoft Project Source Plan Data===
 
===Updating a Project View with Changes Made to the Microsoft Project Source Plan Data===
  
16) Suppose after examining the project view you created before, you realize that it would be best to show more task bars.  This, you think, would greatly improve the schedule discussion you are about to conduct.  Updating the project view at this point is a simple matter.  Recall that '''OPP''' is active and the '''PVE''' is displaying the current project view you want to update.  Additionally, the Microsoft Project '''source plan''' and the application are active.  The original project view looked like this:
+
9) Suppose after examining the project view you created before, you realize that it might be best to show more task bars.  This, you think, would greatly improve your schedule presentation.  Updating the project view at this point is a simple matter.  Recall that '''OPP''' is active and the '''PVE''' is displaying the current project view you want to update.  Additionally, the Microsoft Project '''source plan''' and the application are active.  The original project view looked like this:
  
 
<center>[[File:P61-3_0_1_1-61-(18)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(18)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(18)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(18)-04302018.png</center-->
  
 
:a) Since Microsoft Project is still an active program and the Microsoft Project '''source plan''' you are using is still being displayed, go back to the Microsoft Project application and change the '''Flag20''' field setting for the rows you want to now display from '''No''' to '''Yes'''.  A section of the Microsoft Project '''source plan''' where this is done is shown below:
 
:a) Since Microsoft Project is still an active program and the Microsoft Project '''source plan''' you are using is still being displayed, go back to the Microsoft Project application and change the '''Flag20''' field setting for the rows you want to now display from '''No''' to '''Yes'''.  A section of the Microsoft Project '''source plan''' where this is done is shown below:
  
 
<center>[[File:P61-3_0_1-61-(19A)-10232017.png]]</center>
 
<center>[[File:P61-3_0_1-61-(19A)-10232017.png]]</center>
<center>P61-3_0_1-61-(19A)-10232017.png</center>
+
<!--center>P61-3_0_1-61-(19A)-10232017.png</center-->
  
:b) Once you’ve made the '''Flag20''' changes lines 8 through 15 in the Microsoft Project the '''source plan''' will look like this:
+
:b) Once you’ve made the '''Flag20''' changes lines 8 through 15 in the Microsoft Project the '''source plan''' looks like this:
  
 
<center>[[File:P61-3_0_1-61-(19B)-10232017.png]]</center>
 
<center>[[File:P61-3_0_1-61-(19B)-10232017.png]]</center>
<center>P61-3_0_1-61-(19B)-10232017.png</center>
+
<!--center>P61-3_0_1-61-(19B)-10232017.png</center-->
  
 
:c) With the Microsoft Project '''source plan''' updated, go back to '''OPP''' and navigate to the '''Data''' tab on the ribbon where you see several buttons.  To update your project view to show the additional rows from your Microsoft Project '''source plan''', click the '''Replace Snapshot''' button as shown below:
 
:c) With the Microsoft Project '''source plan''' updated, go back to '''OPP''' and navigate to the '''Data''' tab on the ribbon where you see several buttons.  To update your project view to show the additional rows from your Microsoft Project '''source plan''', click the '''Replace Snapshot''' button as shown below:
  
 
<center>[[File:P61-3_0_1-61-(19C)-10232017.png]]</center>
 
<center>[[File:P61-3_0_1-61-(19C)-10232017.png]]</center>
<center>P61-3_0_1-61-(19C)-10232017.png</center>
+
<!--center>P61-3_0_1-61-(19C)-10232017.png</center-->
  
 
:d) When you click the '''Replace Snapshot''' button, '''OPP''' goes back to the Microsoft Project '''source plan''' that you just changed, brings in all the rows that changed, and updates your project view.
 
:d) When you click the '''Replace Snapshot''' button, '''OPP''' goes back to the Microsoft Project '''source plan''' that you just changed, brings in all the rows that changed, and updates your project view.
Line 206: Line 205:
  
 
<center>[[File:P61-3_0_1_1-61-(19D)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(19D)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(19D)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(19D)-04302018.png</center-->
  
17) The example above is just one of many uses of the '''Data''' tab’s '''Replace Snapshot''' button when you need to update a project view.  And, you can do this as many times as necessary until the project view is the way you need it.  In addition to adding and removing rows by changing the '''Flag20''' field, you may need to change '''Start Dates''', '''Finish Dates''', or '''Percent Complete''' and display these data changes in the project view.  Using the procedure above you can do this very efficiently.  
+
10) The example above is just one of many uses of the '''Data''' tab’s '''Replace Snapshot''' button when you need to update a project view.  And, you can do this as many times as necessary until the project view is the way you need it.  In addition to adding and removing rows by changing the '''Flag20''' field, you can change '''Start Dates''', '''Finish Dates''', or '''Percent Complete''' and display these data changes in the project view.  Using the procedure above you can do this very efficiently.  
  
18) You can now save the project view by giving it a '''source plan''' name.  When you save the project view in '''OPP''', OnePager saves the '''.TAM''' and saves the Microsoft Project '''source plan''' name and path information.  This is useful when you want to further update the project view or when you want to add a snapshot later on.  In the examples below we assume that the project view is saved as '''BlueGrass Project Report - Pro'''.
+
11) You can now save the project view by giving it a name.  When you save the project view in '''OPP''', OnePager saves the '''.TAM''' and saves the Microsoft Project '''source plan name''' and '''path''' information.  This is useful when you want to further update the project view or when you want to add a snapshot later on.  In the examples below we assume that the project view is saved as '''BlueGrass Project Report - Pro'''.
  
 
===Adding a Snapshot to a Project View===
 
===Adding a Snapshot to a Project View===
  
19) The power of '''OPP''' is illustrated when, after a period of progress on the project, it is time to produce another project view.  OnePager produces your next snapshot with the same look and feel as the original.  Assuming that the Microsoft Project '''source plan''' was updated with actual start and finish, percent complete, and other relevant data during the reporting interval, '''OPP''' can easily generate a new snapshot.   
+
12) The power of '''OPP''' is illustrated when, after a period of progress on the project, it is time to produce another project view.  OnePager produces your next snapshot with the same look and feel as the original.  Assuming that the Microsoft Project '''source plan''' was updated with actual start and finish, percent complete, and other relevant data during the reporting interval, '''OPP''' can easily generate a new snapshot.   
  
20) Suppose we have the following project view created on 7/1/2019 and we want to create another graph from the updated Microsoft Project '''source plan''' on 8/1/2019.
+
13) Suppose we have the following project view created on 7/1/2019 and we want to create another graph from the updated Microsoft Project '''source plan''' on 8/1/2019.
  
 
<center>[[File:P61-3_0_1_1-61-(20)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(20)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(20)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(20)-05012018.png</center-->
  
 
:a) Before creating a new snapshot for 8/1/2019 as planned, we need to update the Microsoft Project '''source plan''' say by updating the '''Percent Complete''' for the ADONIS Subcontractor Selection task to 75%.  When the '''source plan''' is updated with this revised information we can proceed.
 
:a) Before creating a new snapshot for 8/1/2019 as planned, we need to update the Microsoft Project '''source plan''' say by updating the '''Percent Complete''' for the ADONIS Subcontractor Selection task to 75%.  When the '''source plan''' is updated with this revised information we can proceed.
  
:b) Launch '''OPP''' either from Microsoft Project or from the '''desktop''' icon and click the '''UPDATE''' button on the '''OnePager Pro Start''' form.  Doing so will bring up the following '''OnePager choices''' ('''OPC''') form:
+
:b) Launch '''OPP''' either from Microsoft Project or from the '''Desktop''' icon and click the '''UPDATE''' button on the '''OnePager Pro Start''' form.  Doing so accesses the following '''OnePager choices''' ('''OPC''') form:
  
 
<center>[[File:P61-3_0_1_1-61-(20A)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(20A)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(20A)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(20A)-05012018.png</center-->
  
 
:c) In the '''OPC''' form select the '''NEW snapshot at date:''' as shown above.  You want to select a date for the snapshot so that this snapshot represents the project at the status date point in time.  To see which snapshot dates already exist, just position your mouse over the '''NEW snapshot at date:''' window to see a list of the existing dates.   
 
:c) In the '''OPC''' form select the '''NEW snapshot at date:''' as shown above.  You want to select a date for the snapshot so that this snapshot represents the project at the status date point in time.  To see which snapshot dates already exist, just position your mouse over the '''NEW snapshot at date:''' window to see a list of the existing dates.   
  
 
<center>[[File:P61-3_0_1_1-61-(20B)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(20B)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(20B)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(20B)-05012018.png</center-->
  
 
:d) You can use the built in calendar dropdown or type in the new snapshot’s month, day, and year in the window provided as shown below:
 
:d) You can use the built in calendar dropdown or type in the new snapshot’s month, day, and year in the window provided as shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(20C)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(20C)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(20C)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(20C)-05012018.png</center-->
  
 
:e) Uncheck the '''Show field mappings''' checkbox if you want to use the same '''field mappings''' as you used before.    The bottom of the screen now looks like this:
 
:e) Uncheck the '''Show field mappings''' checkbox if you want to use the same '''field mappings''' as you used before.    The bottom of the screen now looks like this:
  
 
<center>[[File:P60-3_0_1-60-(26)-01252017.png]]</center>
 
<center>[[File:P60-3_0_1-60-(26)-01252017.png]]</center>
<center>P60-3_0_1-60-(26)-01252017.png</center>
+
<!--center>P60-3_0_1-60-(26)-01252017.png</center-->
  
 
:f) Pressing the large '''New''' button creates a new snapshot for the project view.  The project view opens at the new snapshot.    The '''color''', '''fonts''', '''title''', and '''swimlane''' assignments are consistent between the two snapshots:
 
:f) Pressing the large '''New''' button creates a new snapshot for the project view.  The project view opens at the new snapshot.    The '''color''', '''fonts''', '''title''', and '''swimlane''' assignments are consistent between the two snapshots:
  
 
<center>[[File:P61-3_0_1_1-61-(20D)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(20D)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(20D)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(20D)-05012018.png</center-->
  
 
:g) You can go back and forth between the two snapshots by using the '''snapshot forward/backward''' buttons on the '''View''' tab as shown below:
 
:g) You can go back and forth between the two snapshots by using the '''snapshot forward/backward''' buttons on the '''View''' tab as shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(20E)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(20E)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(20E)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(20E)-05012018.png</center-->
  
===Editing the Project View===
+
==Editing the Project View==
  
21) You can always edit the '''font sizes''' and '''text positions''' on task shapes to optimize readability.  To do this, hold down the left mouse button and '''drag''' a selection box ('''lasso''') that encloses many tasks/milestones at once:
+
1) You can always '''edit''' the '''font sizes''' and '''text positions''' on task shapes to optimize readability.  To do this, hold down the left mouse button and '''drag''' a selection box ('''lasso''') that encloses many tasks/milestones at once:
  
 
<center>[[File:P61-3_0_1_1-61-(29)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(29)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(29)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(29)-05012018.png</center-->
  
:a) When you release the mouse, the enclosed tasks/milestones will all be selected:
+
:a) When you release the mouse, the enclosed tasks/milestones are all be selected:
  
 
<center>[[File:P61-3_0_1_1-61-(30)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(30)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(30)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(30)-05012018.png</center-->
  
 
:b) Click the '''Increase Font Size''' button on the tool bar shown below:
 
:b) Click the '''Increase Font Size''' button on the tool bar shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(31)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(31)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(31)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(31)-05012018.png</center-->
  
:c) The project view will now look something like this:
+
:c) The project view now looks something like this:
  
 
<center>[[File:P61-3_0_1_1-61-(32)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(32)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(32)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(32)-05012018.png</center-->
  
 
:d) Repeating this operation for the remaining tasks/milestones (we could have done '''Select All''' and done it all at once!), we obtain a project view with larger fonts on all the tasks/milestones:
 
:d) Repeating this operation for the remaining tasks/milestones (we could have done '''Select All''' and done it all at once!), we obtain a project view with larger fonts on all the tasks/milestones:
  
 
<center>[[File:P61-3_0_1_1-61-(33)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(33)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(33)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(33)-05012018.png</center-->
  
22) Another common editing action is to move the task names from their current positions to a positions elsewhere around or on the task bar.   
+
2) Another common '''editing''' action is to move the task names from their current positions to a positions elsewhere around or on the task bar.   
  
 
:a) To do this, select a set of tasks/milestones as before, but this time click one of the '''text-positioning''' buttons on the tool bar:
 
:a) To do this, select a set of tasks/milestones as before, but this time click one of the '''text-positioning''' buttons on the tool bar:
  
 
<center>[[File:P61-3_0_1_1-61-(34)-05012018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(34)-05012018.png]]</center>
<center>P61-3_0_1_1-61-(34)-05012018.png</center>
+
<!--center>P61-3_0_1_1-61-(34)-05012018.png</center-->
  
:b) In case you change your mind about the last editing action you took, you can undo the last editing action by clicking the '''UNDO''' button above the OnePager tool bar.  Successive clicking the '''UNDO''' button will undo editing actions in the reverse order that they were applied.
+
:b) In case you change your mind about the last '''editing''' action you took, you can '''UNDO''' the last '''editing''' action by clicking the '''UNDO''' button above the OnePager tool bar.  Successive clicking the '''UNDO''' button undoes '''editing''' actions in the reverse order that they were applied.
  
<center>[[File:P61-3_0_1-61-(36)-10232017.png]]</center>
+
<center>[[File:P61-3_0_1_1-61-(35)-05012018.png]]</center>
<center>P61-3_0_1-61-(36)-10232017.png</center>
+
<!--center>P61-3_0_1_1-61-(35)-05012018.png</center-->
  
23) Save the edited project view by pressing the '''Save''' button above the tool bar next to the '''UNDO''' button.  All of the '''font size''' changes, text-position edits, and the new legend position are now saved in case you need to update this project view with new data at a later time.
+
3) Save the '''edited''' project view by pressing the '''Save''' button above the tool bar next to the '''UNDO''' button.  All of the '''font size''' changes, '''text-position''' '''edits''', and the new '''Legend''' position are now saved in case you need to update this project view with new data at a later time.
  
 
===Copying the Project View to PowerPoint===
 
===Copying the Project View to PowerPoint===
  
23) Finally, copy the current project view snapshot to the clipboard by pressing the '''Copy''' button on the '''Home''' tab of the ribbon.  Then paste the graph into a PowerPoint slide, as shown below:
+
4) Finally, copy the current project view snapshot to the clipboard by pressing the '''Copy''' button on the '''Home''' tab of the ribbon.  Then paste the graph into a PowerPoint slide, as shown below:
  
<center>[[File:P61-3_0_1-61-(37)-10232017.png]]</center>
+
<center>[[File:P61-3_0_1_1-61-(37)-05012018.png]]</center>
<center>P61-3_0_1-61-(37)-10232017.png</center>
+
<!--center>P61-3_0_1_1-61-(37)-05012018.png</center-->
  
24) That’s it! You’ve now created a professional 1-page schedule summary from a complex Microsoft Project schedule and have copied it into a Microsoft PowerPoint presentation.  You can also print the graph by selecting the '''Print''' button on the '''File''' tab.  OnePager has other features that let you move tasks vertically to different '''rows and swimlanes''', change the number of swimlanes, add swimlane titles, show dependencies among tasks, change task colors, hide tasks, add floating comment boxes, and standardize on graph styles across organizations.  To learn more about these features, read about the specific workflows in this Wiki at [[Basic Workflows for Version 6.1 (Portal) | Basic Workflows (Portal)]] 7.0.1-61 and [[Manual Editing for Version 6.1 (Portal) | Manual Editing]] 9.0.1-61.
+
5) That’s it! You’ve now created a professional 1-page schedule summary from a complex Microsoft Project schedule and have copied it into a Microsoft PowerPoint presentation.   
 +
 
 +
:a) You can also print the graph by selecting the '''Print''' button on the '''File''' tab.   
 +
 
 +
:b) OnePager has other features that let you move tasks vertically to different '''rows and swimlanes''', change the number of swimlanes, add swimlane titles, show dependencies among tasks, change task colors, hide tasks, add floating comment boxes, and standardize on graph styles across organizations.   
 +
 
 +
:c) To learn more about these features, read about the specific workflows in this Wiki at [[Basic Workflows for Version 6.1 (Portal) | Basic Workflows (Portal)]] <!--7.0.1-61--> and [[Manual Editing for Version 6.1 (Portal) | Manual versus Data-Driven Editing (Portal)]]. <!--9.0.1-61.-->
  
 
===Displaying Data-Driven Task Links===
 
===Displaying Data-Driven Task Links===
  
25) OnePager Pro 6.1 is enhanced to assist you with displaying Microsoft Project '''dependency''' fields in your project view.  Typically, this feature is turned '''OFF''' in all '''Templates''' distributed with OnePager.  However, the feature can be turned '''ON''' either before or after the creation of a project view.
+
6) OnePager Pro 6.1 is enhanced to assist you with displaying Microsoft Project '''dependency''' fields in your project view.  Typically, this feature is turned '''OFF''' in all '''Templates''' distributed with OnePager.  However, the feature can be turned '''ON''' either before or after the creation of a project view.
  
:a) To turn the '''data-driven Task Link''' feature '''ON''' prior to creating a project view, go to the '''Template''' form you plan to uses and click on the '''Task Links''' tab and then click the '''Import predecessors''' checkbox in the '''Data-Driven Task Links''' control group as shown below:
+
:a) To turn the '''Data-Driven Task Link''' feature '''ON''' prior to creating a project view, go to the '''Template''' form you plan to uses and click on the '''Task Links''' tab and then click the '''Import predecessors''' checkbox in the '''Data-Driven Task Links''' control group as shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(38)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(38)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(38)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(38)-04302018.png</center-->
  
 
:b) With the '''Import predecessors''' checkbox checked in the '''Template''' form, the project view first created looks like this:
 
:b) With the '''Import predecessors''' checkbox checked in the '''Template''' form, the project view first created looks like this:
  
 
<center>[[File:P61-3_0_1_1-61-(39)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(39)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(39)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(39)-04302018.png</center-->
  
:c) To turn the '''data-driven Task Link''' feature '''ON''' after the project view is created, go to the '''Project-View Properties''' form's '''Task Links''' tab and then click the '''Import predecessors''' checkbox in the '''Data-Driven Task Links''' control group as shown below:
+
:c) To turn the '''Data-Driven Task Link''' feature '''ON''' after the project view is created, go to the '''Project-View Properties''' form's '''Task Links''' tab and then click the '''Import predecessors''' checkbox in the '''Data-Driven Task Links''' control group as shown below:
  
 
<center>[[File:P61-3_0_1_1-61-(40)-04302018.png]]</center>
 
<center>[[File:P61-3_0_1_1-61-(40)-04302018.png]]</center>
<center>P61-3_0_1_1-61-(40)-04302018.png</center>
+
<!--center>P61-3_0_1_1-61-(40)-04302018.png</center-->
  
:d) Once imported, '''data-driven Task Links''' can be '''shown''' or '''hidden''' and can be edited globally using the '''Template/Project-View Properties''' forms as shown above or individually using a selection right-click '''context menu'''.
+
:d) Once imported, '''Data-Driven Task Links''' can be '''shown''' or '''hidden''' and can be '''edited''' globally using the '''Template/Project-View Properties''' forms as shown above or individually using a selection right-click '''context menu'''.
  
 
:e) OnePager Pro 6.1 continues to support manual '''Task Links''' which in previous OnePager Pro versions were called '''Event Links'''.
 
:e) OnePager Pro 6.1 continues to support manual '''Task Links''' which in previous OnePager Pro versions were called '''Event Links'''.
  
26) The OnePager version 6.1 '''Data-Driven Task Links''' feature is flexible and powerful.  More details are provided in the series of articles at:  [[Linking Task and Milestones Using Manual and Data-Driven Task Links for Version 6.1 | Linking Task and Milestone Using Manual and Data-Driven Task Links]] 19.0.1-61.
+
7) The OnePager version 6.1 '''Data-Driven Task Links''' feature is flexible and powerful.  More details are provided in the series of articles at:  [[Linking Task and Milestones Using Manual and Data-Driven Task Links for Version 6.1 | Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)]]. <!--19.0.1-61.-->
  
 
==Related Links==
 
==Related Links==
  
[[What's New with OnePager Release 6.1?]] 0.4-61
+
[[What's New with OnePager Release 6.1?]] <!--0.4-61-->
 +
 
 +
[[Getting Started with OnePager Pro Version 6.1 Desktop | Getting Started with OnePager Pro Desktop]] <!--3.0.1.2-61-->
  
[[Getting Started with OnePager Pro Version 6.1 Desktop | Getting Started with OnePager Pro Desktop]] 3.0.1.2-61
+
[[Conditional Import for Version 6.1 (Portal) | Conditional Import Filters (Portal)]] <!--7.18.1-61-->
  
[[Conditional Import for Version 6.1 (Portal) | Conditional Import Filters (Portal)]] 7.18.1-60
+
[[Basic Workflows for Version 6.1 (Portal) | Basic Workflows (Portal)]] <!--7.0.1-61
  
[[Basic Workflows for Version 6.1 (Portal) | Basic Workflows (Portal)]] 7.0.1-61
+
[[Manual Editing for Version 6.1 (Portal) | Manual versus Data-Driven Editing (Portal)]] <!--9.0.1-61-->
  
[[Manual Editing for Version 6.1 (Portal) | Manual Editing]] 9.0.1-61
+
[[Linking Task and Milestones Using Manual and Data-Driven Task Links for Version 6.1 | Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)]] <!--19.0.1-61-->
  
 
(3.0.1.1-61)
 
(3.0.1.1-61)
Line 352: Line 359:
 
[[Category:Editing a Project View]]
 
[[Category:Editing a Project View]]
 
[[Category:Sharing Output]]
 
[[Category:Sharing Output]]
 +
[[Category:Task Links]]
 
[[Category:OnePager - Tool Bar]]
 
[[Category:OnePager - Tool Bar]]
 
[[Category:Help]]
 
[[Category:Help]]
 
[[Category:OnePager Pro]]
 
[[Category:OnePager Pro]]

Latest revision as of 16:09, 18 December 2018

Overview

1) As with the previous version of OnePager Pro, version 6.1 of OPP can be launched from a Desktop icon as well as from within Microsoft Project (Add-in).

2) Please note that after selecting the Add-in launch option that you are not be able to launch the OnePager Desktop application.

3) Only one of these applications (Add-in or Desktop) can be active at a time.

4) If you attempt to launch both, a warning message appears as shown below.

P53-3 0 1-53-(01)-11062015.png

5) Further note that as mentioned in What's New with OnePager Release 6.1? , this new version has enhanced features such as Task Link Upgrades and Time Axis Upgrades to name a few.

6) This article covers the Getting Started process when you launch OPP from Microsoft Project.

7) The article which provides Getting Started guidance when launching from the Desktop icon is at Getting Started with OnePager Pro Desktop.

Launching OnePager Pro for the First Time

1) The OPP Add-in automatically displays the OnePager icon on the Microsoft Project ribbon once OnePager is installed. That tool bar looks like this:

P53-3 0 1-53-(1)-11062015.png

2) Clicking the OnePager Pro button takes you to the Project View Editor (PVE). Clicking the Templates… button lets you edit' the Templates provided with the product. For now, it is simplest to use the default Template. You can learn how Templates let you customize and standardize graph features later in this document.

3) Before you launch OPP, it is a good idea to unhide the Microsoft Project flag field you intend to use. (Note that when you unhide a field in Microsoft Project, that field can now appear in some of Microsoft Project’s standard reports. Do not forget to hide the field again before generating such reports if you do not want the field to appear in those reports.) The selected flag field allows you to control which tasks get graphed and to store those choices in Microsoft Project for future use. For example, the flag field (e.g., Flag20) is shown below:

P61-3 0 1-61-(2)-10232017.png

4) To control which tasks get graphed, specify the Microsoft Project flag field (e.g. Flag1, Flag2 … Flag20) that you wish to use. Number fields can also be used the same as the flag fields where a 1 in a Number field indicates Yesand a 0 in a Number field indicates No. Unhide that field in Microsoft Project by right-clicking in the field header area and selecting Insert Column:

P61-3 0 1-61-(3)-10232017.png

5) Now put a Yes in this flag field for any task that you want to graph:

P61-3 0 1-61-(4)-10232017.png
a) When making your first project view, we strongly recommend that you mark 50 or fewer tasks with Yes.
b) Please note that OPP is shipped with a number of fully populated Templates that are based on the Microsoft Project source plan used in the tutorial also shipped with the product – BlueGrass Project 2J-303.
c) Starting in Microsoft Project 2010, there is a Manual Scheduling mode that allows you to leave dates blank in your schedule. However, behind the scenes, these dates are still being automatically assigned to the project Start Date, or to Today's Date if the project Start Date is not defined. Even though the dates appear to be undefined, they are defined behind the scenes, and are being passed to OPP. Because Today's Date often equals your Snapshot date, it is not surprising to see all of these dateless tasks appearing near the time cursor.
d) There are two solutions to this issue: :
(1) Define the dates for your tasks and milestones in Microsoft Project. This overwrites any default dates that Microsoft Project is assigning, and makes your project schedule more consistent with your OPP timeline. :
(2) Remove the dateless tasks from your OPP graph. You can leave them in project, but by removing them from the OPP graph, you won't have to explain why certain tasks/milestones are appearing in weird places when they really should not. As a rule of thumb, we recommend defining dates for all tasks and milestones, especially when it comes to graph generation.

6) To launch OPP and make a project view, click the OPP button on the Microsoft Project tool bar’s Add-ins tab, which brings up the OnePager Pro Start form:

P61-1 6-(2)-61-10232017.png

7) The OnePager Pro Start form provides you with three options:

a) NEW Clicking the NEW button brings up the OnePager Pro choices (OPC) form.
b) UPDATE Clicking the UPDATE button allows you to BROWSE FILES for an existing project view or select a recently-opened project view.
c) OPEN Clicking the OPEN button allows you to BROWSE FILES for an existing project view or select a recently-opened project view. Once selected and opened, the project view is available for editing.

Creating a New Project View

1) Clicking the NEW button brings up the OPC form as shown below:

P61-3 0 1 1-61-(6)-04302018.png

Options on the New OnePager Choices form

2) We’ve enhanced the OPC form to give you more options for selecting source plans. The illustration above shows that OPP is initiated from Microsoft Project with the source plan shown in the Selected File(s) group shown above. The Add/Remove button gives you the capability to add more source plans to the source packet or, for multiple file packets, to remove files.

a) Clicking the Add/Remove button brings up the Data source selection form as shown below:
P61-3 0 1 1-61-(7)-04302018.png
b) The Data source selection form displays the current source plan that was loaded with Microsoft Project when you clicked the OnePager Pro button. This form lets you Add more Microsoft Project source plan to create a multi-project project view or Remove a source plan from a multi-file source packet. These options are detailed below.

Adding a New Source Plan

c) Add a new source plan to the source packet: When you click the Add button, OPP gives you the option to bring up a Windows Open form when you select the BROWSE FILES… option as shown here:
P61-3 0 1 1-61-(8)-04302018.png
i) Clicking the BROWSE FILES… option displays a Window’s Open form from which you can select a Microsoft Project source plan to add to the source packet. A sample Open form is shown below:
P61-3 0 1 1-61-(9)-05012018.png
ii) When you select a desired Microsoft Project source plan and click the Open button as shown above, OPP adds the source plan to the source packet and displays it in the Data source selection window as shown below:
P61-3 0 1 1-61-(10)-04302018.png
iii) The selected source plan is added to the source packet as shown above. OPP shows the path name of the source plan in the window if you hover the mouse over the source plan name.
iv) If you select a recently used source plan from the dropdown menu displayed when the Add button is clicked (Data source selection form), OPP adds that source plan to the source packet.

Removing a Source Plan

d) Remove source from source packet: The Remove button allows you to remove a source plan from a source packet if that source plan is not needed to create the new project view. To remove a source plan, first select the source plan in the Data source selection form’s window so that it is highlighted in blue then click the Remove button as shown in the sequence below:
P61-3 0 1 1-61-(11)-04302018.png


P61-3 0 1 1-61-(12)-04302018.png

Other Choices to Make

3) Moving on to the other groups of the OPC form, you are asked to confirm a few things before you build the project view. OPP makes good guesses for each of these choices, but you can change any of them:

P61-3 0 1 1-61-(15)-04302018.png
a) Starting Template: The current Template determines which fields get imported from Microsoft Project and how the initial project view looks. OPP ships with many sample Templates, but you can also customize your own Templates.
i) To choose which Template to use in building your project view, click the Change… button in the top group of the OPC form.
ii) For now, just stick with the default Template entitled Single Project Gantt View – Detailed, but you can always use a different Template to get a different type of project view.
b) Title of the New Project View: This is the Title of the graph and also the suggested save source plan name. You can change the source plan save name when you save it. We recommend that you enter a Title that helps you identify the project view later on.
i) For each project view you create, OnePager remembers colors, titles, legends, font sizes, and all other graph properties so that your work is saved.
ii) Later, you can update the project view with a snapshot of how the project looks on a different date. Then you can browse through the snapshots to see how the project is changing over time.
iii) OPP also saves the path name associated with the source plan (.TAM). Path names are not available in .TAMs produced with versions of OPP prior to version 6.0.
c) Task Selection: This is how you tell OPP which tasks from your Microsoft Project plan to import.
i) Either click the Select all tasks radio button to graph everything or choose a flag field. You can make several project views from a single Microsoft Project source plan, each using a different flag or number field. In OPP if no flags are set to Yes, OPP provides you with a warning message.
ii) Clicking the Select tasks by custom filter button activates the Edit filters... button. Clicking the Edit filters... button takes you to a form that controls the new Conditional Import Filters feature. Please see the article titled Conditional Import Filters (Portal) for more detailed on the use of this feature.
d) Snapshot Date: This is the date of the report and lets you keep track of how schedules change over time. Each project view can have many snapshots.

4) The Show field mappings checkbox near the bottom of the form can be checked. When this box is checked you have a chance to review and change the Microsoft Project field mappings to OPP before you make your first project view. To do this, check the box and click the Next> button. You now see the following form:

P61-3 0 1 1-61-(16)-04302018.png

5) Notice in the form above that OPP has relied on the current Template to make some guesses on which Microsoft Project fields should be used in making the graph. You can easily change any of these field mappings by making selections from the dropdown menus. For example, we show below how to change the Finish Date :

P61-3 0 1 1-61-(17)-04302018.png

Making the Graph

6) Once you are satisfied with the field mappings, click the Create new project view button to import your selected data and create a project view. After a second or two you see a screen that looks like this:

P61-3 0 1 1-61-(18)-04302018.png

7) Note that each task or milestone was color coded based on the value in the Resource Names field.

a) The Legend contains an optional diagram near the bottom explaining that the bars inside the Gantt bars represent percent complete extracted from Microsoft Project.
b) Percent complete comes from a Microsoft Project field that you specified in the field mappings form.
c) Note that the current Template, when you press the Create new project view button, is the Template for how things look in the new project view. The Template form's Task Bars tab shows where the color control is located is shown below:
P61-3 0 1 1-61-(19)-04302018.png

Opening a Project View

8) The right-most button on the OPC form is the OPEN button. Clicking the OPEN button displays a dropdown menu which happens to be the same for the UPDATE button. The options in the dropdown are discussed below:

P61-3 0 1 1-61-(19A)-04302018.png
a) Clicking the BROWSE FILES... option brings up a Windows Open form from which you can select a .TAM that you want to open. Selecting the desired .TAM causes OPP to display the selected project view. From this position, you can edit the project view, save it, or share it with others.
b) Clicking any of the RECENT project views items in the dropdown menu above causes OPP to load the associated .TAM into the Project View Editor (PVE) where you can also edit the project view, save it, or share it with others.

Updating a Project View with Changes Made to the Microsoft Project Source Plan Data

9) Suppose after examining the project view you created before, you realize that it might be best to show more task bars. This, you think, would greatly improve your schedule presentation. Updating the project view at this point is a simple matter. Recall that OPP is active and the PVE is displaying the current project view you want to update. Additionally, the Microsoft Project source plan and the application are active. The original project view looked like this:

P61-3 0 1 1-61-(18)-04302018.png
a) Since Microsoft Project is still an active program and the Microsoft Project source plan you are using is still being displayed, go back to the Microsoft Project application and change the Flag20 field setting for the rows you want to now display from No to Yes. A section of the Microsoft Project source plan where this is done is shown below:
P61-3 0 1-61-(19A)-10232017.png
b) Once you’ve made the Flag20 changes lines 8 through 15 in the Microsoft Project the source plan looks like this:
P61-3 0 1-61-(19B)-10232017.png
c) With the Microsoft Project source plan updated, go back to OPP and navigate to the Data tab on the ribbon where you see several buttons. To update your project view to show the additional rows from your Microsoft Project source plan, click the Replace Snapshot button as shown below:
P61-3 0 1-61-(19C)-10232017.png
d) When you click the Replace Snapshot button, OPP goes back to the Microsoft Project source plan that you just changed, brings in all the rows that changed, and updates your project view.
e) At the conclusion of the operation, the updated project view looks like this:
P61-3 0 1 1-61-(19D)-04302018.png

10) The example above is just one of many uses of the Data tab’s Replace Snapshot button when you need to update a project view. And, you can do this as many times as necessary until the project view is the way you need it. In addition to adding and removing rows by changing the Flag20 field, you can change Start Dates, Finish Dates, or Percent Complete and display these data changes in the project view. Using the procedure above you can do this very efficiently.

11) You can now save the project view by giving it a name. When you save the project view in OPP, OnePager saves the .TAM and saves the Microsoft Project source plan name and path information. This is useful when you want to further update the project view or when you want to add a snapshot later on. In the examples below we assume that the project view is saved as BlueGrass Project Report - Pro.

Adding a Snapshot to a Project View

12) The power of OPP is illustrated when, after a period of progress on the project, it is time to produce another project view. OnePager produces your next snapshot with the same look and feel as the original. Assuming that the Microsoft Project source plan was updated with actual start and finish, percent complete, and other relevant data during the reporting interval, OPP can easily generate a new snapshot.

13) Suppose we have the following project view created on 7/1/2019 and we want to create another graph from the updated Microsoft Project source plan on 8/1/2019.

P61-3 0 1 1-61-(20)-05012018.png
a) Before creating a new snapshot for 8/1/2019 as planned, we need to update the Microsoft Project source plan say by updating the Percent Complete for the ADONIS Subcontractor Selection task to 75%. When the source plan is updated with this revised information we can proceed.
b) Launch OPP either from Microsoft Project or from the Desktop icon and click the UPDATE button on the OnePager Pro Start form. Doing so accesses the following OnePager choices (OPC) form:
P61-3 0 1 1-61-(20A)-05012018.png
c) In the OPC form select the NEW snapshot at date: as shown above. You want to select a date for the snapshot so that this snapshot represents the project at the status date point in time. To see which snapshot dates already exist, just position your mouse over the NEW snapshot at date: window to see a list of the existing dates.
P61-3 0 1 1-61-(20B)-05012018.png
d) You can use the built in calendar dropdown or type in the new snapshot’s month, day, and year in the window provided as shown below:
P61-3 0 1 1-61-(20C)-05012018.png
e) Uncheck the Show field mappings checkbox if you want to use the same field mappings as you used before. The bottom of the screen now looks like this:
P60-3 0 1-60-(26)-01252017.png
f) Pressing the large New button creates a new snapshot for the project view. The project view opens at the new snapshot. The color, fonts, title, and swimlane assignments are consistent between the two snapshots:
P61-3 0 1 1-61-(20D)-05012018.png
g) You can go back and forth between the two snapshots by using the snapshot forward/backward buttons on the View tab as shown below:
P61-3 0 1 1-61-(20E)-05012018.png

Editing the Project View

1) You can always edit the font sizes and text positions on task shapes to optimize readability. To do this, hold down the left mouse button and drag a selection box (lasso) that encloses many tasks/milestones at once:

P61-3 0 1 1-61-(29)-05012018.png
a) When you release the mouse, the enclosed tasks/milestones are all be selected:
P61-3 0 1 1-61-(30)-05012018.png
b) Click the Increase Font Size button on the tool bar shown below:
P61-3 0 1 1-61-(31)-05012018.png
c) The project view now looks something like this:
P61-3 0 1 1-61-(32)-05012018.png
d) Repeating this operation for the remaining tasks/milestones (we could have done Select All and done it all at once!), we obtain a project view with larger fonts on all the tasks/milestones:
P61-3 0 1 1-61-(33)-05012018.png

2) Another common editing action is to move the task names from their current positions to a positions elsewhere around or on the task bar.

a) To do this, select a set of tasks/milestones as before, but this time click one of the text-positioning buttons on the tool bar:
P61-3 0 1 1-61-(34)-05012018.png
b) In case you change your mind about the last editing action you took, you can UNDO the last editing action by clicking the UNDO button above the OnePager tool bar. Successive clicking the UNDO button undoes editing actions in the reverse order that they were applied.
P61-3 0 1 1-61-(35)-05012018.png

3) Save the edited project view by pressing the Save button above the tool bar next to the UNDO button. All of the font size changes, text-position edits, and the new Legend position are now saved in case you need to update this project view with new data at a later time.

Copying the Project View to PowerPoint

4) Finally, copy the current project view snapshot to the clipboard by pressing the Copy button on the Home tab of the ribbon. Then paste the graph into a PowerPoint slide, as shown below:

P61-3 0 1 1-61-(37)-05012018.png

5) That’s it! You’ve now created a professional 1-page schedule summary from a complex Microsoft Project schedule and have copied it into a Microsoft PowerPoint presentation.

a) You can also print the graph by selecting the Print button on the File tab.
b) OnePager has other features that let you move tasks vertically to different rows and swimlanes, change the number of swimlanes, add swimlane titles, show dependencies among tasks, change task colors, hide tasks, add floating comment boxes, and standardize on graph styles across organizations.
c) To learn more about these features, read about the specific workflows in this Wiki at Basic Workflows (Portal) and Manual versus Data-Driven Editing (Portal).

Displaying Data-Driven Task Links

6) OnePager Pro 6.1 is enhanced to assist you with displaying Microsoft Project dependency fields in your project view. Typically, this feature is turned OFF in all Templates distributed with OnePager. However, the feature can be turned ON either before or after the creation of a project view.

a) To turn the Data-Driven Task Link feature ON prior to creating a project view, go to the Template form you plan to uses and click on the Task Links tab and then click the Import predecessors checkbox in the Data-Driven Task Links control group as shown below:
P61-3 0 1 1-61-(38)-04302018.png
b) With the Import predecessors checkbox checked in the Template form, the project view first created looks like this:
P61-3 0 1 1-61-(39)-04302018.png
c) To turn the Data-Driven Task Link feature ON after the project view is created, go to the Project-View Properties form's Task Links tab and then click the Import predecessors checkbox in the Data-Driven Task Links control group as shown below:
P61-3 0 1 1-61-(40)-04302018.png
d) Once imported, Data-Driven Task Links can be shown or hidden and can be edited globally using the Template/Project-View Properties forms as shown above or individually using a selection right-click context menu.
e) OnePager Pro 6.1 continues to support manual Task Links which in previous OnePager Pro versions were called Event Links.

7) The OnePager version 6.1 Data-Driven Task Links feature is flexible and powerful. More details are provided in the series of articles at: Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal).

Related Links

What's New with OnePager Release 6.1?

Getting Started with OnePager Pro Desktop

Conditional Import Filters (Portal)

Basic Workflows (Portal)

Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)

(3.0.1.1-61)