Order of Tasks/Milestones Decorations

From OnePager Documentation
Revision as of 17:05, 18 April 2016 by Rfeingold (Talk | contribs)

Jump to: navigation, search

Decorations on tasks/milestones are always drawn in the same z-order from back to front. This fixed ordering from back to front is given below:

a) Connectors in back (baseline to task/milestone, endpoints, and deadline connectors to task/milestone)
b) Task/Milestone
c) Baseline
d) Endpoints/Deadline
e) All text for task/milestone, deadline and endpoints/deadline in front.

Note

The action of the Order command applies to the task/milestone itself and all decorations associated with it.

(10.13)