Order of Tasks/Milestones Decorations for Version 6.1

From OnePager Documentation
Revision as of 16:52, 19 December 2018 by Rfeingold (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Decorations on tasks/milestones are always drawn in the same z-order from back to front. This fixed ordering from back to front is given below:

a) Connectors in back (e.g., baseline to task/milestone, endpoints, and deadline connectors to task/milestone)
b) Task/Milestone
c) Baseline
d) Endpoints/Deadline
e) All text for task/milestone, deadline and endpoints/deadline in front.

Note

The action of the Order command applies to the task/milestone itself and all decorations associated with it including Task Links.

(10.13.1-61)