Getting Started with OnePager Express Version 7.0 Desktop

From OnePager Documentation
Revision as of 18:53, 19 February 2019 by Rfeingold (Talk | contribs)

Jump to: navigation, search

Overview

1) As with the previous version of OnePager Express, version 7.0 of OPX can now be launched from a Desktop icon as well as from within Microsoft Excel (Add-in).

2) Please note that after selecting the Desktop launch option that you are not able to launch the OnePager Add-in application.

3) Only one of these applications (Add-in or Desktop) can be active at a time.

4) If you attempt to launch both, a warning message appears as shown for OPX below.

X53-3 0 3-53-(01)-11222015.png

5) Further note that as mentioned in What's New with OnePager Release 7.0? 0.4-70, this new version has enhanced features such as Task Link Upgrades, Time Axis Upgrades, and Legend Upgrades to name a few.

6) This article covers the Getting Started process when you launch OPX the Desktop.

7) The article which provides Getting Started guidance when launching OPX from Microsoft Excel is at Getting Started with OnePager Express Add-in. 3.0.2.1-70

Launching OnePager Express for the First Time from the Desktop

1) OPX version 7.0 can be installed so that it can be launched either from Microsoft Excel’s Add-in tab on its tool bar or from a Desktop icon or both. Additionally, you can also locate and double-click a .TAM to bring up the Desktop OPX.

2) The Desktop icon for launching OPX version 7.0 looks like this:

X61-3 0 3-61-(1)-10242017.png
X61-3_0_3-61-(1)-10242017.png

3) Before you launch OPX, however, you must have certain scheduling fields in your Microsoft Excel source plan. There is a lot of flexibility in how these fields can be named. A typical example is shown below. The only mandatory fields are field representing Start, Finish, and Name. In this example, however, we are also including three optional fields:

a) A category field (Category) that OnePager uses to assign colors to tasks.
b) A selection field (Show It) that OnePager uses to choose which tasks to graph.
c) A Task ID field that OnePager uses to keep track of tasks/milestones as your Microsoft Excel source plan is change through additions or deletions over the course of the project.
X61-3 0 3-61-(2)-10242017.png
X61-3_0_3-61-(2)-10242017.png

4) To control which tasks get graphed, you must specify a flag field (e.g. Show It) that you wish to use. Numeric fields can also be used the same as the text fields where a 1 in a Number field indicates Yes and a 0 in a Number field indicates No. See how this is done in the illustration above.

a) When making your first chart, we strongly recommend that you select 50 or fewer tasks with Yes.
b) Please note that OPX is shipped with a number of fully populated Templates that are based on the Microsoft Excel source plan used in the tutorial also shipped with the product – BlueGrass Project 2J-303.

5) The following table describes field-heading types that OPX uses and shows variations on the heading titles that OnePager recognizes.

a) It is not mandatory that you used these field names, since OPX gives you a chance to choose the actual Microsoft Excel source plan fields that it employs. However, using these names speeds things up because it helps OPX make reasonable guesses on which fields to use as its default selections.
b) Note that it shows that three of the field heading types must always be present: Name, Start, and Finish.
c) We recommend the inclusion of an ID field with sequential numbering from top to bottom. This assists OnePager maintain a correspondence with Microsoft Excel’s rows after the Microsoft Excel source plan is updated.
X53-3 0 3-53-(3)-11092015.png

6) Clicking the OnePager Express button on the Desktop first displays a splash page and then takes you to the Chart Editor.

X61-3 0 4-61-(2A)-10242017.png
X61-3_0_4-61-(2A)-10242017.png


X61-3 0 2 2-61-(3)-05032018.png
X61-3_0_2_2-61-(3)-05032018.png

7) The OnePager Express Start form provides you with three options:

a) NEW Clicking the NEW button accesses the OnePager choices (OPC) form.
b) UPDATE Clicking the UPDATE button allows you to BROWSE FILES for an existing chart file or select a recently-opened chart file.
c) OPEN Clicking the OPEN button allows you to BROWSE FILES for an existing chart file or select a recently-opened chart file. Once selected and opened, the chart is available for editing.

Creating a New Chart

1) Clicking the NEW button brings up the OPC form as shown below:

X61-3 0 2 2-61-(4)-05032018.png
X61-3_0_2_2-61-(4)-05032018.png

Options on the New OnePager Choices form

2) We’ve enhanced the OPC form to give you more options for selecting source files.

a) Clicking the Select... button displays a dropdown menu with a BROWSE FILES... option as well as a list of recently accessed Microsoft Excel source plan as shown here:
X61-3 0 2 2-61-(5)-05032018.png
X61-3_0_2_2-61-(5)-05032018.png
b) When you click the Select... button and the BROWSE FILES... option, a Windows Open form appears from which you can select the desired Microsoft Excel source plan:
X61-3 0 2 2-61-(6)-05032018.png
X61-3_0_2_2-61-(6)-05032018.png
c) When you select the Microsoft Excel source plan and click the Open button on the Windows Open form, OPX loads the Microsoft Excel source plan and expands the “OPC form as shown below:
X61-3 0 2 2-61-(6A)-05032018.png
X61-3_0_2_2-61-(6A)-05032018.png

3) At this point you have additional options with respect to the expanded of the OPC form. The Add/Remove button gives you the capability to add more source plans to the source packet or, for multiple file, to remove files.

a) Clicking the Add/Remove button brings up the Data source selection form as shown below:
X61-3 0 2 1-61-(6)-5022018.png
X61-3_0_2_1-61-(6)-5022018.png
b) The Data source selection form displays the current source plan that was loaded with Microsoft Excel when you clicked the OnePager Express... button. This form lets you Add more source Microsoft Excel source plan to create a multi-project chart or Remove a source plans from a multi-file source packet. These options are detailed below.

Adding a New Source Plan

c) Add a new source plan to the source packet When you click the Add button, OPX gives you the option to bring up a Windows Open form when you select the BROWSE FILES… option as shown here:
X61-3 0 2 1-61-(7)-5022018.png
X61-3_0_2_1-61-(7)-5022018.png
i) Clicking the BROWSE FILES… option displays a Window’s Open from which you can select a Microsoft Excel source plan to add to the source packet. A sample Open form is shown below:
X61-3 0 2 1-61-(8)-5022018.png
X61-3_0_2_1-61-(8)-5022018.png
ii) When you select a desired Microsoft Excel source plan and click the Open button as shown above, OPX adds the file to the source packet and display it in the Data source selection window as shown below:
X61-3 0 2 1-61-(9)-5022018.png
X61-3_0_2_1-61-(9)-5022018.png
iii) The selected file is added to the source packet as shown above. OPX shows the path name of the source plans in the window if you hover the mouse over the source plan name.
iv) If you select a recently used file from the dropdown menu displayed with the Add button is clicked in the Data source selection form, OPX adds that source plan to the source packet.

Removing a Source Plan

d) Remove source plan from source packet The Remove button allows you to remove a source plan from a source packet. if that source plan is not needed to create the new chart. To remove a source plan, first select the source plan in the Data source selection form’s window so that it is highlighted in blue then click the Remove button as shown in the sequence below:
X61-3 0 2 1-61-(10)-5022018.png
X61-3_0_2_1-61-(10)-5022018.png


X61-3 0 2 1-61-(11)-5022018.png
X61-3_0_2_1-61-(11)-5022018.png

Other Choices to Make

4) Moving on to the other groups of the OPC form asks you to confirm a few things before you build the chart. It makes good guesses for each of these choices, but you can change any of them:

X61-3 0 2 1-61-(15)-5022018.png
X61-3_0_2_1-61-(15)-5022018.png
a) Starting Template The current Template determines which fields get imported from Microsoft Excel and how the initial chart looks. OPX ships with many sample Templates, but you can also customize your own Templates.
i) To choose which Template to use in building your chart, click the Change… button in the top group of the OPC form.
ii) For now, just stick with the default Template entitled Single Project Gantt View – Detailed, but you can always use a different Template to get a different type of chart.
b) Title of the New Chart This is the title of the graph and also the suggested source plan name in which it is saved. You can change the source plan name when you save it. We recommend that you enter a title that helps you identify the view later on.
i) For each chart that you create, OnePager remembers colors, titles, legends, font sizes, and all other graph properties so that your work is saved for future use.
ii) Later, you can update the chart with a snapshot of how the project looks on a different date. Then you can browse through the snapshots to see how the project is changing over time.
iii) OPX also saves the path name associated with the .TAM. Path names are not available in .TAM produced with previous version of OPX.
c) Task Selection This is how you tell OPX which tasks from your Microsoft Excel source plan to include.
i) Either click the Select all tasks radio button to graph everything or choose a flag field. You can make several charts from a single Microsoft Excel source plan, each using a different flag or number field. In OPX if no flags are set to Yes, OPX provides the user with a warning message.
ii) Clicking the Select tasks by custom filter button enables the Edit filters... button. Clicking the Edit filters... button accesses a form that controls the new Conditional Import Filters feature. Please see the article titled Conditional Import Filters (Portal) 7.18.1-70 for more detailed on the use of this new feature.
d) Snapshot Date: This is the date of the report and lets you keep track of how schedules change over time. Each chart can have several snapshots.

5) The Show field mappings checkbox near the bottom of the form can be checked in the OPC form and gives a chance to review and change the Microsoft Excel field mappings to OPX before you make your first chart. To do this, click the Next> button. You see the following screen:

X60-3 0 3-60-(15AA)-03072017.png
X60-3_0_3-60-(15AA)-03072017.png

6) Notice in the graphic above that OPX has relied on the current Template to make some guesses on what Microsoft Excel fields should be used in making the graph. You can easily change any of these field mappings by making selections from the dropdown menus. For example, we show below how to change the Finish Date:

X60-3 0 3-60-(16AA)-03072017.png
X60-3_0_3-60-(16AA)-03072017.png

Making the Graph

7) Once you are satisfied with the field mappings, click on Create new chart button to import your selected data and create a chart. After a very few moments you see a screen that looks like this:

X61-3 0 2 1-61-(17-1)-5022018.png
X61-3_0_2_1-61-(17-1)-5022018.png

8) Note that each task or milestone was color coded based on the value in the Category field.

a) The legend contains an optional diagram near the bottom, explaining that the bars inside the Gantt bars represent percent complete extracted from Microsoft Excel.
b) Percent complete comes from a Microsoft Excel field that you specified in the field mappings form.
c) Note that the current Template, when you press the Create new chart button, is the Template for how things look in the new chart. The Template form’s Task Bars tab showing where the color control is located is shown below:
X61-3 0 2 1-61-(18)-5022018.png
X61-3_0_2_1-61-(18)-5022018.png

Opening a Chart

9) The right-most button on the OPC form is the OPEN button. Clicking the OPEN button displays a dropdown menu which happens to be the same for the NEW and UPDATE buttons. The options in the dropdown are discussed below:

X61-3 0 2 2-61-(18A)-5022018.png
X61-3_0_2_2-61-(18A)-5022018.png
a) Clicking the BROWSE FILES... option accesses a Windows Open form from which you can select a .TAM file that you want to open. Selecting the desired .TAM file causes OPX to display the selected chart. From this position, you can edit the chart, save it, or share it with others.
b) Clicking any of the RECENT chart items in the dropdown menu above causes OPX to load the associated .TAM file into the Chart Editor where you can also edit the chart, save it, or share it with others.

Updating a Chart with Changes Made to the Microsoft Excel Source Plan Data

10) Suppose after examining the chart you created before you realize that it would be best to show more task bars. This, you think, would greatly improve the schedule discussion you are about to attend. Updating the chart at this point is a simple matter. Recall that OPX is active and the Chart is displaying the current chart you want to update. Additionally, the Microsoft Excel source plan and the application are active. The original chart looked like this:

X61-3 0 2 1-61-(18B)-5022018.png
X61-3_0_2_1-61-(18B)-5022018.png
a) Since Microsoft Excel is still an active program and the Microsoft Excel source plan you are using is still being displayed, go back to the Microsoft Excel application and change the Show It field setting for the rows you want to now display from No to Yes. As section of the Microsoft Excel source plan where this is done is shown below:
X61-3 0 2 1-61-(18C)-5022018.png
X61-3_0_2_1-61-(18C)-5022018.png
b) Once you’ve made the Show It field changes lines 7 through 15 in the Microsoft Excel the source plan looks like this:
X61-3 0 2 1-61-(18D)-5022018.png
X61-3_0_2_1-61-(18D)-5022018.png
c) With the Microsoft Excel source plan updated, go back to OPX and navigate to the Data tab on the ribbon where you’ll see several buttons. To update your chart to now show the additional rows from your Microsoft Excel source plan click the Replace Snapshot button as shown below:
X60-3 0 3-60-(17C)-01272017.png
X60-3_0_3-60-(17C)-01272017.png
d) When you click the Replace Snapshot button, OPX goes back to the associated Microsoft Excel source plan that you just changed, bring in all the rows that changed, and update your chart.
e) At the conclusion of the operation, the updated chart looks like this:
X61-3 0 2 1-61-(18E)-5022018.png
X61-3_0_2_1-61-(18E)-5022018.png

11) The example above is just one of many uses of the Data tab’s Replace Snapshot button when you need to update a chart. And, you can do this as many times as necessary until the chart is the way you need it. In addition to adding and removing rows by changing the Show It field, you can need to change Start Dates, Finish Dates, or Resource Names and display these data changes in the chart. Using the procedure above you can do this very efficiently.

12) You can now save the chart by giving it a name. When you save the chart in OPX, OnePager saves the .TAM and saves the Microsoft Excel source plan name and path information. This is useful when you want to further update the chart or when you want to add a snapshot later on. In the examples below it is assumes that the chart is saved as BlueGrass Project Report - Express.

Adding a Snapshot to a Chart

13) The power of OPX is illustrated when, after a period of progress on the project, it is time to produce another chart. OnePager produces your next snapshot with the same look and feel as the original. Assuming that the Microsoft Excel source plan was updated with actual start and finish, percent complete, and other relevant data during the reporting interval, OPX can easily generate a new snapshot.

14) Suppose we have the following chart created on 11/1/2018 and we want to create another graph from the updated Microsoft Project source plan on 12/1/2018.

X61-3 0 2 1-61-(18F)-5022018.png
X61-3_0_2_1-61-(18F)-5022018.png
a) Before creating a new snapshot for 12/1/2018 as planned, we need to update the Microsoft Excel source plan say by updating the Percent Complete for the following tasks to the percentage indicated:
i) Eng. Team 1 Dev. - 100%
ii) Internal Perf. Test - 10%
iii) Create MERLIN System - 100%
iv) Create ADONIS System - 25%
b) When the source plan is updated with this revised information we can proceed.
c) Launch OPV either from Microsoft Excel or from the desktop icon and click the UPDATE button on the OnePager Express Start form. Doing so accesses the following OnePager choices (OPC) form:
X61-3 0 2 1-61-(18G)-5022018.png
X61-3_0_2_1-61-(18G)-5022018.png
d) In the OPC form select the NEW snapshot at date: as shown above. You can select a current date for the snapshot so that this snapshot represents the project at the status date point in time. To see which snapshot dates already exist, just position your mouse over the NEW snapshot-date: window to see a list of the existing dates.
X61-3 0 2 1-61-(18H)-5022018.png
X61-3_0_2_1-61-(18H)-5022018.png
e) Use the built in calendar dropdown or type in the new snapshot’s month, day, and year in the window provided as shown below:
X61-3 0 2 1-61-(18I)-5022018.png
X61-3_0_2_1-61-(18I)-5022018.png
f) Uncheck the Show field mappings checkbox if you want to use the same field mappings as you used before. The bottom of the screen now looks like this:
P60-3 0 1-60-(26)-01252017.png
P60-3_0_1-60-(26)-01252017.png
g) Pressing the large New button creates a new snapshot for the chart. The chart opens at the new snapshot. The color, fonts, title, and swimlane assignments are consistent between the two snapshots:
X61-3 0 2 1-61-(22)-5022018.png
X61-3_0_2_1-61-(22)-5022018.png
h) You can go back and forth between the two snapshots by using the snapshot forward/backward buttons on the View tab as shown below:
X61-3 0 2 1-61-(23)-5022018.png
X61-3_0_2_1-61-(23)-5022018.png

Editing the Chart

1) You can edit the font sizes and text positions to optimize readability. To do this, hold down the left mouse button and drag a selection box that encloses many tasks/milestones at once (Lasso):

X61-3 0 2 1-61-(24)-5022018.png
X61-3_0_2_1-61-(24)-5022018.png
a) When you release the mouse, the enclosed tasks/milestones are all be selected:
X61-3 0 2 1-61-(25)-5022018.png
X61-3_0_2_1-61-(25)-5022018.png
b) Click on the Increase Font Size button on the tool bar shown below:
X61-3 0 2 1-61-(26)-5022018.png
X61-3_0_2_1-61-(26)-5022018.png
c) The chart now looks something like this:
X61-3 0 2 1-61-(27)-5022018.png
X61-3_0_2_1-61-(27)-5022018.png
d) Repeating this operation for the remaining tasks/milestones (we could have done Select All and done it all at once!), we obtain a chart with larger fonts on all the tasks/milestones:
X61-3 0 2 1-61-(28)-5022018.png
X61-3_0_2_1-61-(28)-5022018.png

2) Another common editing action is to move the task names from their current positions to a positions elsewhere around or on the task bar.

a) To do this, select a set of tasks/milestones as before, but this time click one of the text-positioning buttons on the tool bar:
X61-3 0 2 1-61-(29)-5032018.png
X61-3_0_2_1-61-(29)-5032018.png
b) In case you change your mind about the last editing action you took, you can UNDO the last editing action by clicking the UNDO button above the OnePager tool bar. Successive clicking the UNDO button undoes editing actions in the reverse order that they were applied.
X61-3 0 2 1-61-(31)-5032018.png
X61-3_0_2_1-61-(31)-5032018.png

3) Save the edited chart by clicking the Save button above the tool bar next to the UNDO button. All of the font size changes, text-position edits, and the new Legend position are now saved in the file structure in case you need to update this chart with new data at a later time.

Copying the Chart to PowerPoint

4) Finally copy the current snapshot of the chart to the clipboard by clicking the Copy button on the Home ribbon. Then paste the graph into a PowerPoint slide, as shown below:

X61-3 0 2 1-61-(32)-5032018.png
X61-3_0_2_1-61-(32)-5032018.png

5) That’s it! You have now created a professional 1-page schedule summary from a complex Microsoft Excel schedule and have copied it into a PowerPoint presentation.

a) You can also print the graph by selecting the Print button on the File tab.
b) OnePager has other features that let you move tasks vertically to different rows and swimlanes, change the number of swimlanes, add swimlane titles, show dependencies among tasks, change task colors, hide tasks, add floating comment boxes, and standardize on graph styles across organizations.
c) To learn more about these features, read about the specific workflows in this Wiki at Basic Workflows (Portal) 3.0.1-70 and Manual versus Data-Driven Editing (Portal). 9.0.1-70

Displaying Data-Driven Task Links

6) OnePager Express 7.0 is enhanced to assist you with displaying Task Link dependencies from data you provide in your Microsoft Excel source plan. Typically, this feature is turned OFF in all Templates distributed with OnePager. However, the feature can be turned ON either before or after the creation of a chart.

a) To turn the data-driven Task Link feature ON prior to creating a chart, go to the Template form you plan to uses and click on the Task Links tab and then click the Import predecessors checkbox in the Data-Driven Task Links control group as shown below:
X61-3 0 2 1-61-(38)-05032018.png
X61-3_0_2_1-61-(38)-05032018.png
b) In the Template Task Link tab above there are two additional controls that need to be set to tell OnePager Express which data field you are using to express task dependencies in the form of predecessors and which dependency format you are using either (1) Microsoft Project or (2) Oracle Primavera. These controls are in the form of dropdown menus as shown for the dependency format selector below:
X61-3 0 2 1-61-(38A)-05032018.png
X61-3_0_2_1-61-(38A)-05032018.png
c) With the Import predecessors checkbox checked and the dependency data field and dependency format selections made in the Template form, the chart first created looks like this:
X61-3 0 2 1-61-(39)-05032018.png
X61-3_0_2_1-61-(39)-05032018.png
d) To turn the data-driven Task Link feature ON after the chart is created, go to the Chart Properties form's Task Links tab and then click the Import predecessors checkbox in the Data-Driven Task Links control group as shown below:
X61-3 0 2 1-61-(40)-05032018.png
X61-3_0_2_1-61-(40)-05032018.png
e) Once imported, data-driven Task Links can be shown or hidden and can be edited globally using the Template/Chart Properties forms as shown above or individually using a selection right-click context menu.
f) OnePager Express 7.0 continues to support manual Task Links which in previous OnePager Express versions were called Event Links.

7) The OnePager version 7.0 Data-Driven Task Links feature is flexible and powerful. More details are provided in the series of articles at: Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal). 19.0.1-70

Related Links

What's New with OnePager Release 7.0? 0.4-70

Getting Started with OnePager Pro Desktop 3.0.1.1-70

Conditional Import Filters (Portal) 7.18.1-70

Basic Workflows (Portal) 3.0.1-70

Manual versus Data-Driven Editing (Portal) 9.0.1-70

Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal) 19.0.1-70

(3.0.2.2-70)