==About Date Labels==
+
==About Editing Baselines==
  
'''Date label''' displays are driven by the '''start and finish date''' data imported from the Microsoft Excel '''source plan'''.  Every task in a Microsoft Excel '''source plan''' has a designated '''start and finish date'''.  A milestone's '''start and finish dates''' are usually the same. You can choose to use '''date labels''' for tasks, milestones, or both.
+
'''Baseline property''' displays are driven by the '''baseline start and finish dates imported''' from the Microsoft Project '''source plan'''.  Not every task bar/milestone symbol in a Microsoft Project '''source plan''' has designated '''baseline start and finish dates'''.  A milestone symbols’ '''start and finish dates''' are usually the same. When you need to display '''baseline property''' information, it is essential that the associated data be properly represented in your Microsoft Project '''source plan''' before the data are '''imported''' to OnePager Pro ('''OPP''').
  
==Using the Chart Properties Form to Edit Date Labels==   
+
==Editing All Task/Milestone Baseline Properties==   
  
''All''' task and milestone shape '''date labels''' cab be '''edited''' without changing the settings in the current '''Template''' by clicking the '''Chart Properties''' button on the '''Home''' ribbon in the '''Settings''' group as shown here:
+
All task bars and milestone symbol '''baseline properties''' can be modified without changing the settings in the current '''Template Properties''' form by clicking the '''Chart Properties''' button on the OnePager '''Home''' ribbon tool bar tab in the '''Settings''' group. Next, navigate to either the '''Task Bars''' or '''Milestones''' tab as appropriate and ensure that the '''Baseline markers''' checkbox is checked '''ON''' as shown below:
  
<center>[[File:X70-10_2_1-70-(1)-09142019.png]]</center>
+
<center>[[File:P70-10_5_1-(1-1)-06022020.png]]</center>
<!--<center>X70-10_2_1-70-(1)-09142019.png</center>-->
+
<!--<center>P70-10_5_1-(1-1)-06022020.png</center>-->
  
Clicking the '''Chart Properties''' button accesses the '''Chart Properties''' form. Next, navigate to either the '''Task Bars''' or '''Milestones''' tab as appropriate.  On the '''Task Bars''' tab, as shown below, ensure that the '''Date Labels''' checkbox is checked '''On''':
+
Once the '''Baseline markers''' checkbox is checked '''ON''', '''baselines''' can be customized by clicking the '''Baseline Properties''' button which accesses the '''Set baseline properties''' form shown here:
  
<center>[[File:X70-10_2_1-70-(2-1)-09252020.png]]</center>
+
<center>[[File:P70-10_5_1-(2)-06022020.png]]</center>
<!--<center>X70-10_2_1-70-(2-1)-09252020.png</center>-->
+
<!--<center>P70-10_5_1-(2)-06022020.png</center>-->
  
Clicking the '''Date Label Properties...''' button to the right of the '''Date Labels''' checkbox accesses the '''Set Date Label Properties''' form as shown here:
+
You can now '''edit''' '''baseline properties''' for task bars/milestone symbols using the '''Set Baseline Properties''' form.
  
<center>[[File:X70-10_2_1-70-(3-1)-09252020.png]]</center>
+
===Change Baseline Shape===
<!--<center>X70-10_2_1-70-(3-1)-09252020.png</center>-->
+
  
There are eight (8) controls in the form above.  All actions are consistent with identical controls found elsewhere in OnePager Express ('''OPX''').
+
The controls for changing the '''shape''' of the '''baseline''' are the same as for task bars/milestone symbols discussed in this article at:  [[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] <!-9.2.1-70-->
  
===Date Label Font===
+
The '''baseline shapes''' available are the same as for task bars/milestone symbols as shown in the '''Set baseline properties''' form below:
  
This control causes the '''Font properties''' form shown below to appear when the dropdown button is clicked.  
+
<center>[[File:P70-10_5_1-(3)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(3)-06022020.png</center>-->
  
<center>[[File:X70-10_2_1-70-(3A)-09142019.png]]</center>
+
There are numerous '''baseline''' shapes that can be selected. Use the scroll bar on the right of the dropdown list to make your selection. When the selection is made, either continue to make additional properties changes or click the '''OK''' button to get back to the '''Chart Properties''' form where all '''edits''' are applied.
<!--<center>X70-10_2_1-70-(3A)-09142019.png</center>-->
+
  
Within this form are controls for date text '''font style''', '''color''' and '''size'''. Additionally, you can set the date text to '''Bold''', ''Italic'', or [[Underline]].
+
===Change Baseline Fill Pattern===
  
===Show (start/finish) and Position Date Label Text===
+
In a fashion very similar to the way '''fill patterns''' are changed for task bars/milestone symbols, once again access the '''Set baseline properties''' form as before, navigate to the '''Use custom fills''' checkbox, check it '''ON''' to '''enable''' the dropdown, and use the associated dropdown list to make your selection as shown below:
  
The two checkboxes, '''Show start date''' and '''Show finish date''', control the display of these two dates, respectively. When checked, you have the option of selecting the position of the dates individually or together:
+
<center>[[File:P70-10_5_1-(4)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(4)-06022020.png</center>-->
  
<center>[[File:X70-10_2_1-70-(4)-09142019.png]]</center>
+
When the selection is made, either continue to make additional properties changes or click the '''OK''' button to get back to the '''Chart Properties''' form where all changes can be applied.
<!--<center>X70-10_2_1-70-(4)-09142019.png</center>-->
+
  
The '''Start field''' and '''Finish field''' are dropdown lists of all '''date type fields imported''' from your '''source plan''' giving you the options to select a different '''start date field''' or '''finish date field''' for use in the chart.  A '''Start field''' dropdown list example is shown below:
+
===Change Baseline Height Percentage===
  
<center>[[File:X70-10_2_1-70-(5)-09142019.png]]</center>
+
The '''Height percentage''' control is located just below the '''Baseline custom shape''' dropdown.  This control, shown above, allows you to change the '''height''' of the '''baseline''' as a percentage of the total '''height''' of the parent task bar/milestone symbol (task and baseline information included). The '''default setting''' is 30 percent (%) and a portion of the chart with '''baselines''' checked '''ON''' looks like this:
<!--<center>X70-10_2_1-70-(5)-09142019.png</center>-->
+
  
The combination of '''task label''' display and '''date label''' display for '''all''' task/milestone shapes can cause a crowded appearance around the task/milestone shape.  Use the '''date label''' positioning controls to achieve the appearance desired in combination with '''task labels'''.
+
<center>'''Baseline Shapes with 30 Percent Height Setting'''</center>
 +
<center>[[File:P70-10_5_1-(5)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(5)-06022020.png</center>-->
  
===Date Format===
+
Increasing this value makes the '''baseline''' taller (higher) with respect to the task bar/milestone symbol.  To change the value, navigate to the '''Height percentage''' control in the '''Specify how to display baseline properties''' control group of the '''Set baseline properties''' form.  Change the value with the controls provided. If you double the value to 60 percent, for example, the resulting baselines would look like this:
  
OnePager provides a great deal of variety for the selection of '''date formats''' for task/milestones. For consistency, the available formats for task/milestone shape's '''date formats''' are the same as for '''date formats''' used for the '''time axis''' at the top/bottom of the chart. A sample of '''date formats''' are shown below:
+
<center>'''Baseline Shapes with 60 Percent Height Setting'''</center>
 +
<center>[[File:P70-10_5_1-(6)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(6)-06022020.png</center>-->
  
<center>[[File:X70-10_2_1-70-(6)-09142019.png]]</center>
+
===Change Baseline Transparency===
<!--<center>X70-10_2_1-70-(6)-09142019.png</center>-->
+
  
===Separator===
+
The '''transparency''' control makes the '''baseline less transparent''' (opaque) when the value in the window of the form is '''decreased''' or as shown below where the value is set at its default of 0% (the '''baseline''' is highlighted in orange): 
  
The '''separators''' are pairs of symbols that help differentiate the '''date label''' from other nearby text (e.g., '''task labels''' or '''percent complete'''). There are several '''separator''' options to select from as shown below:
+
<center>[[File:P70-10_5_1-(7)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(7)-06022020.png</center>-->
  
<center>[[File:X70-10_2_1-70-(7)-09142019.png]]</center>
+
With this setting for '''transparency''' and '''baseline''' shape '''color''', the chart portion looks like this:
<!--<center>X70-10_2_1-70-(7)-09142019.png</center>-->
+
  
===Use Fiscal Year===
+
<center>[[File:P70-10_5_1-(8)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(8)-06022020.png</center>-->
  
The '''Use fiscal year''' checkbox is an instruction, if checked '''On''', to OnePager to show the displayed '''date''' in the '''fiscal year''' format for the chart’s '''time axis'''.  OnePager takes the action only if the '''time axis''' for the chart is, indeed, displaying the '''time axis''' in a '''fiscal year''' format.  Make sure that the '''time axis''' is in '''fiscal''' mode to assure that '''date labels''' displayed are consistent.
+
When you need to make the '''baseline shape more transparent''' '''increase''' the percentage value as shown below where the value is '''increased''' to 60%:
  
===Sample Start and Finish Date Labels in the Chart===
+
<center>[[File:P70-10_5_1-(9)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(9)-06022020.png</center>-->
  
When the '''Date Labels''' checkbox is checked '''On''' and both the '''Show start date''' and '''Show finish date''' checkboxes are checked '''On''' in the '''Set date label properties''' form, the '''date labels''' looks like this:
+
With the '''transparency''' for the '''baseline''' set at 60%, the chart portion looks like this:
  
<center>[[File:X70-10_2_1-70-(8)-09142019.png]]</center>
+
<center>[[File:P70-10_5_1-(10)-06022020.png]]</center>
<!--<center>X70-10_2_1-70-(8)-09142019.png</center>-->
+
<!--<center>P70-10_5_1-(10)-06022020.png</center>-->
  
'''Date Label fonts''' are overridden by '''Task Label fonts''' when the '''Date Label''' and '''Task Label''' are in the '''same position'''. If the '''Date Label''' is put in a '''different''' position than the '''Task Label''', the '''Date Label font's''' properties are honored.
+
===Change Baseline Color===
  
==Editing Individual Date Labels in the Chart==
+
You can also make the '''baseline''' any '''color''' different from the parent task bar/milestone symbol as we did above.  To '''edit''' the '''color properties''' of the '''baseline''' follow these steps. Go to the same '''Set baseline properties''' form as described above.  Check the '''Use custom color''' checkbox '''ON'''.  Then, click the dropdown to access to the '''Color Chooser''' form as shown below:
  
There are three (3) methods for accessing the controls for '''editing''' individual '''date labels''' on individual tasks and milestones:
+
<center>[[File:P70-10_5_1-(11)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(11)-06022020.png</center>-->
  
:*  You can right-click on the selected task/milestone shape to access the context menu followed by clicking the '''Format...''' command in the menu.
+
Finally, select a desired '''color''', for example, orange as used above. When the '''color''' is selected, the '''Color Chooser''' form closes and after clicking '''OK''' in the '''Set baseline properties''' form, the chart looks like this:
:* You can right-click on the selected '''date label''' itself to access the '''one command''' context menu followed by clicking the '''Format...''' command.
+
:* You can click the '''Format...''' button on the '''Home''' ribbon tab.
+
  
Each of these methods is discussed below.
+
<center>[[File:P70-10_5_1-(12)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(12)-06022020.png</center>-->
  
===Right-Clicking a Task/Milestone===
+
===Connect Baselines and Actual Task Bars/Milestone Symbols===
  
Accessing the '''Change Task/Milestone Properties''' form with this method requires you to right-click on the task or milestone shape.  This action accesses the available commands in the '''context menu''' shown below:
+
The '''Connecting Lines''' control group in the '''Set baseline properties''' form tells the OnePager whether you want to connect '''baseline shapes''' to their task bars with a '''line'''.  This control group is shown below with its controls highlighted:
  
<center>[[File:X70-10_2_1-70-(8A-1)-09092020.png]]</center>
+
<center>[[File:P70-10_5_1-70-(11)-09162019.png]]</center>
<!--<center>X70-10_2_1-70-(8A-1)-09092020.png</center>-->
+
<!--<center>P70-10_5_1-70-(11)-09162019.png</center>-->
  
Clicking the '''Format…''' command accesses the '''Change Task/Milestone Properties''' form at the '''Format''' tab as shown here:
+
Check the '''Connect baselines and actuals''' checkbox '''ON''' to '''enable''' the control group and apply the '''default baseline connection''' settings. To change the '''color''' of the '''connecting line''', check the '''Use custom color''' checkbox '''ON'''.  Then, click the '''color''' window dropdown button to access the standard '''Color Chooser''' form.  Making a selection changes the '''color''' of the '''connecting line'''.  If you do not check this checkbox '''ON''', OnePager uses the '''color''' of the task bar/milestone symbol as the '''color''' of the '''connecting line''' segments.
  
<center>[[File:X70-10_2_1-70-(8B-1)-09092020.png]]</center>
+
To change the '''type of line segment''' ('''solid, dotted, dashed, etc.'''), click the '''Line style''' dropdown button and make your selection. Finally, you can '''edit''' the '''width''' of the '''line''' by changing the value in the '''Line width''' control window.
<!--<center>X70-10_2_1-70-(8B-1)-09092020.png</center>-->
+
  
The '''Format''' tab is shown above where you can '''edit''' the task/milestone shape's properties shown. Navigate to the '''Dates''' tab on the '''Change Task/Milestones Properties''' form to make your '''edits''' to the selected '''dates'''. The controls in the '''Change Task/Milestone Properties''' form's '''Date''' tab are discussed below.
+
Click '''OK''' on the '''Set baseline properties form''' click the '''OK''' button on the '''Chart Properties''' form to see the '''baselines''' connected to their current schedule task bars/milestone symbols as shown in the sample below:
  
===Right-Clicking the Date Label===
+
<center>[[File:P70-10_5_1-70-(12)-09162019.png]]</center>
 +
<!--<center>P70-10_5_1-70-(12)-09162019.png</center>-->
  
The '''Date Label''' when displayed can also be right-clicked to access the one command context menu as shown below:
+
In the sample above, two of the three orange '''baselines''' are '''connected''' to their respective task bars with a '''red dash-dot line''' that was '''widened''' to '''2.0'''  to enhance visibility. The third '''baseline''' shown above does not display a '''connecting''' like because its '''finish date''' is within the '''start/finish dates''' boundaries of its task bar.
  
<center>[[File:X70-10_2_1-70-(8C-1)-09092020.png]]</center>
+
===Showing Baseline Dates===
<!--<center>X70-10_2_1-70-(8C-1)-09092020.png</center>-->
+
  
Clicking the '''Format…''' command accesses the '''Change Task/Milestone Properties''' form at the '''Dates''' tab as shown here:
+
'''Baseline start/finish dates''' are automatically '''imported''' by OnePager.  The '''Baseline dates''' control group on the '''Set baseline properties''' form provides the controls for '''showing, positioning, and editing''' '''baseline dates''' near the '''baselines''' for a more detailed information of target dates:
  
<center>[[File:X70-10_2_1-70-(8D-1)-09092020.png]]</center>
+
<center>[[File:P70-10_5_1-(14)-06022020.png]]</center>
<!--<center>X70-10_2_1-70-(8D-1)-09092020.png</center>-->
+
<!--<center>P70-10_5_1-(14)-06022020.png</center>-->
  
===Format button on the OnePager Express Home Ribbon===
+
By checking the '''Show start date''' and/or '''Show finish date''' '''ON''' you can select the '''date format''' that OnePager uses in annotating the '''baseline date''', including whether or not to use the '''fiscal year'''.  If you choose to show both '''start and finish dates''' the same '''date format''' is applied both.
  
The '''Change Task/Milestone Properties''' form can also be accessed by clicking the '''Format…''' button after you selected one or more task/milestone shapes to '''edit'''.  The '''Format...'''button on the ribbon is shown below:
+
The controls in this control group are very similar to the '''date controls''' associated with task bar/milestone symbol '''date labels''' as described in the article at: [[Labeling Task/Milestone Dates for Version 7.0 (OnePager Pro) | Labeling Task/Milestone Dates for OnePager Pro]] <!-10.1.1-70-->
 +
 
 +
A sample of the '''date''' formats from the '''Date format''' dropdown menu is shown here:
  
<center>[[File:X70-10_2_1-70-(8E)-09142019.png]]</center>
+
<center>[[File:P70-10_5_1-(15)-06022020.png]]</center>
<!--<center>X70-10_2_1-70-(8E)-09142019.png</center>-->
+
<!--<center>P70-10_5_1-(15)-06022020.png</center>-->
  
After clicking the '''Format...''' button as shown above, the '''Change Task/Milestone Properties''' form is accessed at the '''Format''' tab as shown here:
+
To specify the location of the '''baseline (date) label/text''', relative to the '''baseline''', use the dropdown menu shown below from the '''Baseline dates''' group:
  
<center>[[File:X70-10_2_1-70-(8B-1)-09092020.png]]</center>
+
<center>[[File:P70-10_5_1-(16)-06022020.png]]</center>
<!--<center>X70-10_2_1-70-(8B-1)-09092020.png</center>-->
+
<!--<center>P70-10_5_1-(16)-06022020.png</center>-->
  
Navigate to the '''Dates''' tab on the '''Change Task/Milestones Properties''' form to make your '''edits''' to the selected '''dates'''. The controls in the '''Change Task/Milestone Properties''' form's '''Date''' tab are discussed below.
+
Some care needs to be taken when determining the positions of '''baseline start/finish dates''' as the settings discussed here are '''global''' setting and may result in the '''baseline start/finish date label/text colliding''' with other '''label information''' on the chart. When these '''baseline start/finish date label/text collisions''' do occur they can be corrected by individual '''editing''' of the '''baseline properties''' associated with the offending tasks.  
  
===Using the Change Task/Milestone Properties Form's Date Tab===
+
For more information on '''Editing''' individual task bar '''baseline properties''', please see the section in the article at: [[Baselines for Version 7.0 (OnePager Pro)#Editing Individual Task/Milestone Baseline Properties | Editing Individual Task/Milestone Baseline Properties]] <!-10.5.1-70-->
  
Any method you use the '''Date''' tab in the '''Change Task/Milestone Properties''' form looks like this:
+
The '''Use fiscal year''' checkbox in the '''Baseline dates''' control group is an instruction, if checked '''ON''', tells OnePager to show the displayed '''baseline date''' in the '''fiscal year''' format in coordination with the chart’s '''time axis'''.  OnePager takes the action only if the '''time axis''' is, indeed, displaying the '''time axis''' in a '''fiscal year''' format.  To '''edit the '''font properties''' for '''baseline start/finish dates''', click the '''Date font''' dropdown button.  This accesses the '''Font properties''' form.  The controls in this form are the same as the controls for '''editing''' any '''label/text font''' in OnePager. 
  
<center>[[File:X70-10_2_1-70-(8G-1)-09092020.png]]</center>
+
The '''Font properties''' form is shown below:
<!--<center>X70-10_2_1-70-(8G-1)-09092020.png</center>-->
+
  
====Show Dates====
+
<center>[[File:P70-10_5_1-(17)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(17)-06022020.png</center>-->
  
When the '''Show Dates''' checkbox is checked '''On''' as shown above, you can decide if you want to '''Show Start Date''', '''Show Finish Dates''' or both by checking the appropriate checkbox '''On''' also shown above.
+
The chart below is an example of positioning '''baseline start''' and '''finish dates''' below the '''baseline''':
  
====Date Position Options====
+
<center>[[File:P70-10_5_1-70-(17)-09162019.png]]</center>
+
<!--<center>P70-10_5_1-70-(17)-09162019.png</center>-->
You have the option to change either the '''Start Date Position''' or the '''Finish Date Position''' or both by clicking the dropdown menu buttons to the immediate right of the checkboxes as shown here:
+
  
<center>[[File:X70-10_2_1-70-(8H-1)-09092020.png]]</center>
+
==Editing Individual Task/Milestone Baseline Properties==
<!--<center>X70-10_2_1-70-(8H-1)-09092020.png</center>-->
+
  
====Date Font Properties====
+
The default settings for displaying '''baseline information''' for individual task bars/milestone symbols can be '''edited''' by using the following steps:
  
Clicking the '''Date Font''' dropdown menu button accesses the '''Font properties''' form shown below:
+
===Selecting Individual Task Bar or Bars===
  
<center>[[File:X70-10_2_1-70-(8I-1)-09092020.png]]</center>
+
Before you can do so, you must confirm that the '''Baseline markers''' checkbox in either the '''Template Properties''' or '''Chart Properties''' form's '''Task Bars''' and/or '''Milestones''' tab is checked '''ON'''. You can select the task bar by right-clicking on it to access the task bar right-click '''context menu''' with the '''Format…''' command, right-clicking on the '''task bar name label''', or click the '''Format…''' button on the OnePager '''Home''' ribbon tool bar tab after selecting the desired task bars/milestone symbols.
<!--<center>X70-10_2_1-70-(8I-1)-09092020.png</center>-->
+
  
Within the '''Font properties''' form are controls for date text '''font style''', '''color''' and '''size'''. Additionally, you can set the date text to '''Bold''', ''Italic'', or [[Underline]].
+
===Accessing the Change Task/Milestone Properties Form===
 +
 
 +
Using any of the available method to select, click the '''Format...''' command to access the '''Change Task/Milestone Properties''' form.  Then, navigate to the '''Baselines''' tab in the '''Change Task/Milestone Properties''' form which looks like this:
 +
 
 +
<center>[[File:P70-10_5_1-(18)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(18)-06022020.png</center>-->
 +
 
 +
====Baseline Tab Editing Controls====
 +
 
 +
The '''Baselines''' tab, shown above, controls the display of the '''baseline dates''' and '''connectors''' for the selected task bar/milestone symbol and the placement of the numeric label/text (dates) for '''baseline''' information.  The '''Show Baseline''' checkbox allows you to turn '''ON''' and '''OFF''' the display of '''baseline''' information for the selected task bar/milestone symbol. When the '''Show Baseline''' checkbox is checked '''ON''', you have the option to specify the display of the '''connector''' and the display of '''baseline start and baseline finish dates''' or both for the selected task bar/milestone symbol. When the '''Show Baseline Start Date''' checkbox is checked '''ON''' or when the '''Show Baseline Finish Date''' checkbox is checked '''ON''' (or both) you have access to control over the '''date positions''' and '''font properties''' as discussed above related to modifying all task bar/milestone symbol '''baseline information'''.
 +
 
 +
====Use Baseline Defaults====
 +
 
 +
Clicking the '''Use Baseline Defaults''' button in the '''Baselines''' tab of the '''Change Task/Milestone Properties''' form resets all '''format properties of the selected '''date label or labels''' back to the settings established in the '''Chart Properties''' form. The '''Use Baseline Defaults''' button looks like this:
 +
 
 +
<center>[[File:P70-10_5_1-(19)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(19)-06022020.png</center>-->
 +
 
 +
===Example===
 +
 
 +
Below is an example of a single task bar’s '''baseline information''' modified:
 +
 
 +
<center>[[File:P70-10_5_1-70-(19)-09172019.png]]</center>
 +
<!--<center>P70-10_5_1-70-(19)-09172019.png</center>-->
 +
 
 +
The controls at the '''Baselines''' tab of the '''Change Task/Milestone Properties''' form for '''Show Baseline Start Date''' and '''Show Baseline Finish Date''', that is, the '''Position''' and '''Font''' controls operate exactly as described for other '''start/finish date''' displays in OnePager. 
 +
 
 +
For more information on '''Percent Complete tab of this form''', please see the section of this article at: [[Percent complete for Version 7.0 (OnePager Pro)#Example | Percent complete for OnePager Pro - Example]] <!--10.3.1-70-->
 +
 
 +
There are no controls available in the '''Baseline''' tab of the '''Change Task/Milestone Properties''' form to '''edit''' the properties of the '''connector line''' for an '''individually''' selected task bar/milestone symbol.
  
 
==Related Link==
 
==Related Link==
  
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!--9.0.1-70-->
+
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!-9.0.1-70-->
 +
 
 +
[[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] <!--9.2.1-70-->
 +
 
 +
[[Labeling Task/Milestone Dates for Version 7.0 (OnePager Pro) | Labeling Task/Milestone Dates for OnePager Pro]] <!--10.1.1-70-->
 +
 
 +
[[Percent complete for Version 7.0 (OnePager Pro) | Percent complete for OnePager Pro]] <!--10.3.1-70
  
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] <!--21.0.1-70-->
+
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] <!-21.0.1-70-->
  
 
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
 
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
  
(10.2.1-70)
+
(10.5.1-70)
  
 
[[Category:Version 7.0]]
 
[[Category:Version 7.0]]
Line 165: Line 201:
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Decorations]]
 
[[Category:Task/Milestone Decorations]]
[[Category:Labels]]
+
[[Category:Baselines]]
 
[[Category:Mavericks]]
 
[[Category:Mavericks]]
[[Category:OnePager Express]]
+
[[Category:OnePager Pro]]

Revision as of 21:24, 12 January 2021

About Editing Baselines

Baseline property displays are driven by the baseline start and finish dates imported from the Microsoft Project source plan. Not every task bar/milestone symbol in a Microsoft Project source plan has designated baseline start and finish dates. A milestone symbols’ start and finish dates are usually the same. When you need to display baseline property information, it is essential that the associated data be properly represented in your Microsoft Project source plan before the data are imported to OnePager Pro (OPP).

Editing All Task/Milestone Baseline Properties

All task bars and milestone symbol baseline properties can be modified without changing the settings in the current Template Properties form by clicking the Chart Properties button on the OnePager Home ribbon tool bar tab in the Settings group. Next, navigate to either the Task Bars or Milestones tab as appropriate and ensure that the Baseline markers checkbox is checked ON as shown below:

P70-10 5 1-(1-1)-06022020.png

Once the Baseline markers checkbox is checked ON, baselines can be customized by clicking the Baseline Properties button which accesses the Set baseline properties form shown here:

P70-10 5 1-(2)-06022020.png

You can now edit baseline properties for task bars/milestone symbols using the Set Baseline Properties form.

Change Baseline Shape

The controls for changing the shape of the baseline are the same as for task bars/milestone symbols discussed in this article at: Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.) <!-9.2.1-70-->

The baseline shapes available are the same as for task bars/milestone symbols as shown in the Set baseline properties form below:

P70-10 5 1-(3)-06022020.png

There are numerous baseline shapes that can be selected. Use the scroll bar on the right of the dropdown list to make your selection. When the selection is made, either continue to make additional properties changes or click the OK button to get back to the Chart Properties form where all edits are applied.

Change Baseline Fill Pattern

In a fashion very similar to the way fill patterns are changed for task bars/milestone symbols, once again access the Set baseline properties form as before, navigate to the Use custom fills checkbox, check it ON to enable the dropdown, and use the associated dropdown list to make your selection as shown below:

P70-10 5 1-(4)-06022020.png

When the selection is made, either continue to make additional properties changes or click the OK button to get back to the Chart Properties form where all changes can be applied.

Change Baseline Height Percentage

The Height percentage control is located just below the Baseline custom shape dropdown. This control, shown above, allows you to change the height of the baseline as a percentage of the total height of the parent task bar/milestone symbol (task and baseline information included). The default setting is 30 percent (%) and a portion of the chart with baselines checked ON looks like this:

Baseline Shapes with 30 Percent Height Setting
P70-10 5 1-(5)-06022020.png

Increasing this value makes the baseline taller (higher) with respect to the task bar/milestone symbol. To change the value, navigate to the Height percentage control in the Specify how to display baseline properties control group of the Set baseline properties form. Change the value with the controls provided. If you double the value to 60 percent, for example, the resulting baselines would look like this:

Baseline Shapes with 60 Percent Height Setting
P70-10 5 1-(6)-06022020.png

Change Baseline Transparency

The transparency control makes the baseline less transparent (opaque) when the value in the window of the form is decreased or as shown below where the value is set at its default of 0% (the baseline is highlighted in orange):

P70-10 5 1-(7)-06022020.png

With this setting for transparency and baseline shape color, the chart portion looks like this:

P70-10 5 1-(8)-06022020.png

When you need to make the baseline shape more transparent increase the percentage value as shown below where the value is increased to 60%:

P70-10 5 1-(9)-06022020.png

With the transparency for the baseline set at 60%, the chart portion looks like this:

P70-10 5 1-(10)-06022020.png

Change Baseline Color

You can also make the baseline any color different from the parent task bar/milestone symbol as we did above. To edit the color properties of the baseline follow these steps. Go to the same Set baseline properties form as described above. Check the Use custom color checkbox ON. Then, click the dropdown to access to the Color Chooser form as shown below:

P70-10 5 1-(11)-06022020.png

Finally, select a desired color, for example, orange as used above. When the color is selected, the Color Chooser form closes and after clicking OK in the Set baseline properties form, the chart looks like this:

P70-10 5 1-(12)-06022020.png

Connect Baselines and Actual Task Bars/Milestone Symbols

The Connecting Lines control group in the Set baseline properties form tells the OnePager whether you want to connect baseline shapes to their task bars with a line. This control group is shown below with its controls highlighted:

P70-10 5 1-70-(11)-09162019.png

Check the Connect baselines and actuals checkbox ON to enable the control group and apply the default baseline connection settings. To change the color of the connecting line, check the Use custom color checkbox ON. Then, click the color window dropdown button to access the standard Color Chooser form. Making a selection changes the color of the connecting line. If you do not check this checkbox ON, OnePager uses the color of the task bar/milestone symbol as the color of the connecting line segments.

To change the type of line segment (solid, dotted, dashed, etc.), click the Line style dropdown button and make your selection. Finally, you can edit the width of the line by changing the value in the Line width control window.

Click OK on the Set baseline properties form click the OK button on the Chart Properties form to see the baselines connected to their current schedule task bars/milestone symbols as shown in the sample below:

P70-10 5 1-70-(12)-09162019.png

In the sample above, two of the three orange baselines are connected to their respective task bars with a red dash-dot line that was widened to 2.0 to enhance visibility. The third baseline shown above does not display a connecting like because its finish date is within the start/finish dates boundaries of its task bar.

Showing Baseline Dates

Baseline start/finish dates are automatically imported by OnePager. The Baseline dates control group on the Set baseline properties form provides the controls for showing, positioning, and editing baseline dates near the baselines for a more detailed information of target dates:

P70-10 5 1-(14)-06022020.png

By checking the Show start date and/or Show finish date ON you can select the date format that OnePager uses in annotating the baseline date, including whether or not to use the fiscal year. If you choose to show both start and finish dates the same date format is applied both.

The controls in this control group are very similar to the date controls associated with task bar/milestone symbol date labels as described in the article at: Labeling Task/Milestone Dates for OnePager Pro <!-10.1.1-70-->

A sample of the date formats from the Date format dropdown menu is shown here:

P70-10 5 1-(15)-06022020.png

To specify the location of the baseline (date) label/text, relative to the baseline, use the dropdown menu shown below from the Baseline dates group:

P70-10 5 1-(16)-06022020.png

Some care needs to be taken when determining the positions of baseline start/finish dates as the settings discussed here are global setting and may result in the baseline start/finish date label/text colliding with other label information on the chart. When these baseline start/finish date label/text collisions do occur they can be corrected by individual editing of the baseline properties associated with the offending tasks.

For more information on Editing individual task bar baseline properties, please see the section in the article at: Editing Individual Task/Milestone Baseline Properties <!-10.5.1-70-->

The Use fiscal year checkbox in the Baseline dates control group is an instruction, if checked ON, tells OnePager to show the displayed baseline date in the fiscal year format in coordination with the chart’s time axis. OnePager takes the action only if the time axis is, indeed, displaying the time axis in a fiscal year format. To edit the font properties for baseline start/finish dates, click the Date font dropdown button. This accesses the Font properties form. The controls in this form are the same as the controls for editing any label/text font in OnePager.

The Font properties form is shown below:

P70-10 5 1-(17)-06022020.png

The chart below is an example of positioning baseline start and finish dates below the baseline:

P70-10 5 1-70-(17)-09162019.png

Editing Individual Task/Milestone Baseline Properties

The default settings for displaying baseline information for individual task bars/milestone symbols can be edited by using the following steps:

Selecting Individual Task Bar or Bars

Before you can do so, you must confirm that the Baseline markers checkbox in either the Template Properties or Chart Properties form's Task Bars and/or Milestones tab is checked ON. You can select the task bar by right-clicking on it to access the task bar right-click context menu with the Format… command, right-clicking on the task bar name label, or click the Format… button on the OnePager Home ribbon tool bar tab after selecting the desired task bars/milestone symbols.

Accessing the Change Task/Milestone Properties Form

Using any of the available method to select, click the Format... command to access the Change Task/Milestone Properties form. Then, navigate to the Baselines tab in the Change Task/Milestone Properties form which looks like this:

P70-10 5 1-(18)-06022020.png

Baseline Tab Editing Controls

The Baselines tab, shown above, controls the display of the baseline dates and connectors for the selected task bar/milestone symbol and the placement of the numeric label/text (dates) for baseline information. The Show Baseline checkbox allows you to turn ON and OFF the display of baseline information for the selected task bar/milestone symbol. When the Show Baseline checkbox is checked ON, you have the option to specify the display of the connector and the display of baseline start and baseline finish dates or both for the selected task bar/milestone symbol. When the Show Baseline Start Date checkbox is checked ON or when the Show Baseline Finish Date checkbox is checked ON (or both) you have access to control over the date positions and font properties as discussed above related to modifying all task bar/milestone symbol baseline information.

Use Baseline Defaults

Clicking the Use Baseline Defaults button in the Baselines tab of the Change Task/Milestone Properties form resets all format properties of the selected date label or labels back to the settings established in the Chart Properties form. The Use Baseline Defaults button looks like this:

P70-10 5 1-(19)-06022020.png

Example

Below is an example of a single task bar’s baseline information modified:

P70-10 5 1-70-(19)-09172019.png

The controls at the Baselines tab of the Change Task/Milestone Properties form for Show Baseline Start Date and Show Baseline Finish Date, that is, the Position and Font controls operate exactly as described for other start/finish date displays in OnePager.

For more information on Percent Complete tab of this form, please see the section of this article at: Percent complete for OnePager Pro - Example

There are no controls available in the Baseline tab of the Change Task/Milestone Properties form to edit the properties of the connector line for an individually selected task bar/milestone symbol.

Related Link

Manual Editing Task/Milestone Shapes and Text Labels (Portal) <!-9.0.1-70-->

Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)

Labeling Task/Milestone Dates for OnePager Pro

Percent complete for OnePager Pro

Managing Templates (Portal)

(10.5.1-70)