About Absorbing One Task Into Another

1) Task/milestone shape absorption is a handy way to compress information.

2) The idea is to absorb one short duration task shape or milestone shape into another task shape or milestone shape with a longer duration, leaving behind only a Comment box (or perhaps two Comment boxes) to indicate the presence of the absorbed (or shorter duration) task/milestone shapes.

Absorbing Tasks

1) To absorb one task/milestone shape into another, drag the shorter duration task/milestone shape to be absorbed on top of the longer duration task/milestone shape that is to absorb it, as shown below.

2) In the example below, we are absorbing the Resistance calculation task shape into the Engineering Team 2 Development task shape.

3) If the absorbed task/milestone shape fits entirely inside the absorbing task/milestone shape (in time), the Absorption Options form appears asking if you want to replace the absorbed task shape name by one or two Comment boxes.

4) At what date position (End or Start Date).

P61-17 0 1-61-(1)-11032017.png
P61-17_0_1-61-(1)-11032017.png

2) After making a choice and clicking OK, the absorbed task/milestone is hidden and is replaced by one or two comment boxes. The comment boxes mark its start time, its end time, or both depending on your previous selection.

3) If the task/milestone to be absorbed does not fit entirely inside the absorbing task/milestone, then it is not possible to carry out this absorption operation.

P61-17 0 1-61-(2)-11032017.png
P61-17_0_1-61-(2)-11032017.png

Absorbed Task's Comment Box

1) Comment boxes originating by absorption can be edited just like any other comment box. To edit these comment boxes, right-click on the comment box and click the Properties… command.

P61-17 0 1-61-(3)-11032017.png
P61-17_0_1-61-(3)-11032017.png

2) Any Task Links associated with the absorbed tasks are retained in the resulting absorbing task representation.

Unabsorbing Tasks

1) To un-absorb a task/milestone that was replaced by one or two comment boxes, right-click on the absorbing task/milestone and then click the Un-absorb tasks command as shown below:

P61-17 0 1-61-(4)-11032017.png
P61-17_0_1-61-(4)-11032017.png

2) This returns both the absorbed tasks/milestones and the absorbing task/milestone to the way they were before as shown here:

P61-17 0 1-61-(5)-11032017.png
P61-17_0_1-61-(5)-11032017.png

3) To complete the un-absorb process, drag the previously absorbed task back to its original position as shown below:

P61-17 0 1-61-(6)-11032017.png
P61-17_0_1-61-(6)-11032017.png

4) Task Links associated with the previously absorbed task are restored after the unabsorb process is completed.

Task Links and Absorbed Tasks

1) If tasks/milestones either being absorbed or are absorbing other tasks/milestones have either Data-Driven or manual Task Links it is important to be aware of how those Task Links appear after the Absorb processes is complete.

2) For more information on the subject of Task Links and Absorption please see the section on this subject at this link: Manual Editing of Task Links for OnePager Pro - Task Links for Absorbed Tasks. 19.4.1-70

Notes

1) Changing the text in the comment box for an absorbed task/milestone has the same effect as editing the Task-Name of the absorbed task/milestone.

2) If you accidentally delete the comment box containing the absorbed task/milestone and want to get it back, all you have to do is go to the Home tab, click the Show/Hide button, and then click the Show all Markers sub-command to unhide all the hidden tasks/milestones:

P61-17 0 1-61-(7)-11032017.png
P61-17_0_1-61-(7)-11032017.png

3) For reverting back (Unabsorbing), we recommend that you use the Undo function if it can be performed immediately after the absorb function is applied.

(17.0.1-70)