Conditional Formatting Rules and the Legend for OnePager Pro for Version 7.0

From OnePager Documentation
Revision as of 20:29, 26 September 2019 by Rfeingold (Talk | contribs) (Basic Chart From Microsoft Project Source Plan=)

Jump to: navigation, search

Overview

1) Because Conditional Formatting Rules can become complex, OnePager provides a means to show the colors and shapes in the legend item text for task/milestones involved in conditional formatting rules.

2) Entries are added to the Legend, as is shown in this article, whenever a conditional formatting rule is applied to a task/milestone color or shape when the Legend is displayed in the chart.

3) You always have the option to subsequently decide to edit these legend-item text item entries after the rules are applied to the chart.

4) The example that follows shows how the Legend is handled when 'conditional formatting rules are used with a simple Microsoft Project source plan.

Example

1) Suppose you have the Microsoft Project source plan shown below where the Text20 field is used to represent the project’s Phases.

2) Highlighted below are four tasks of which three are in Phase THREE and one is in Phase END.

3) In this example, suppose you want to represent these four tasks in black with a left pointing arrow symbol.

Example Microsoft Project Source Plan

4) Here is the proposed Microsoft Project source plan:

P70-11 11 1-70-(1)-09262019.png
P70-11_11_1-70-(1)-09262019.png

Basic Chart From Microsoft Project Source Plan

2) When the basic chart is created with round-robin color assigned from Text20 (Phase), it looks like this:

P70-11 11 1-70-(2)-09262019.png
P70-11_11_1-70-(2)-09262019.png-Need to re-shoot for SL and Row Header fix-Bugzilla 7111


3) To implement the desired results for tasks in Phases THREE and END, you can create conditional formatting rules that look like this:

P70-11 11 1-70-(3)-09262019.png
P70-11_11_1-70-(3)-09262019.png
P61-11 11 1-61-(3)-10312017.png
P61-11_11_1-61-(3)-10312017.png

4) When the chart is created, the highest priority rule shown above is applied, and the four tasks highlighted in the Microsoft Project source plan have these rules applied. Thus, tasks I, J, K, L, and Q shows the results of applying the highest priority conditional formatting rule as shown here:

P70-11 11 1-70-(4)-09262019.png
P70-11_11_1-70-(4)-09262019.png
P61-11 11 1-61-(4)-10312017.png
P61-11_11_1-61-(4)-10312017.png

5) Notice that the legend entry for Phase THREE shows that the Not O conditional formatting rule was applied to the tasks that have the black reverse arrow tasks.