Difference between revisions of "Endpoints for Version 7.0 (OnePager Pro)"

From OnePager Documentation
Jump to: navigation, search
(Example)
Line 1: Line 1:
 
==About Editing Endpoints==
 
==About Editing Endpoints==
  
1) There are four (4) '''endpoints''' definable in OnePager for each task shape.   
+
1) There are four (4) '''endpoints''' definable in OnePager for each task bar.   
  
2) Although '''deadlines''' can be applied to both task and milestone shapes, the four '''endpoints''' apply only to task shapes.
+
2) By definition, milestone symbols in OnePager do not have multiple '''endpoints'''.
  
3) Accordingly, and for all practical purposes, the four possible '''endpoints''' ('''Endpoint1, Endpoint2, Endpoint3, and Endpoint4''') can be thought of as additional '''deadlines dates''' for task shapes that can be defined to meet your needs.  
+
3) Accordingly, '''endpoints''' for milestone symbols are not supported and there is no '''decoration''' controls for '''endpoints''' in the '''Template Properties''' or '''Chart Properties''' form's '''Milestones''' tab.
  
4) The control and the behavior of all four '''endpoints''' are identical to that discussed for '''deadlines'''.
+
4) For all practical purposes, the four possible '''endpoints''' ('''Endpoint1, Endpoint2, Endpoint3, and Endpoint4''') can be thought of as additional '''deadlines dates''' for task bars that can be defined to communicate related '''dates''' associated with the task bar.
  
5) For more information on '''Deadlines''', please see the article at:  [[Deadlines for Version 7.0 (OnePager Pro) | Deadlines for OnePager Pro]] 10.9.1-70.  
+
5) As an additional thought, you can consider the four '''endpoints''' as task-oriented '''milestones''' as they occupy the same row as their parent task shape.
 +
 +
6) The control and the behavior of all four '''endpoints''' are identical to that discussed for '''deadlines'''.
  
6) As an additional thought, you can consider the four '''endpoints''' as task-oriented '''milestones''' as they occupy the same row as their parent task shape.
+
7) For more information on '''Deadlines''', please see the article at:  [[Deadlines for Version 7.0 (OnePager Pro) | Deadlines for OnePager Pro]] 10.9.1-70.  
  
7) By '''convention and as a default''', the initial association of '''Endpoints 1 through 4''' are to Microsoft Project '''source plan''' fields is as follows:
+
8) By '''convention and as a default''', the initial association of '''Endpoints 1 through 4''' are to Microsoft Project '''source plan''' fields is as follows:
  
 
:* '''Endpoint 1: Start Date'''.
 
:* '''Endpoint 1: Start Date'''.
Line 20: Line 22:
 
:* '''Endpoint 4: Baseline Finish Date'''.
 
:* '''Endpoint 4: Baseline Finish Date'''.
  
8) These default settings are contained in all distributed OnePager Pro '''Template''' forms.
+
9) These '''default settings''' are contained in all distributed OnePager Pro '''Template Properties''' forms.
  
9) Since controls are provided as described below whereby you can '''edit''' the '''endpoint''' association with Microsoft Project '''source plan''' fields, it is recommended that you establish your '''endpoint''' relationships to specific Microsoft Project '''date''' fields before creating the first chart.
+
10) Since controls are provided as described below whereby you can '''edit''' the '''endpoint''' association with Microsoft Project '''source plan''' fields, it is recommended that you establish your '''endpoint''' relationships to specific Microsoft Project '''date''' fields before creating the first chart.
  
10)  This recommendation can be done by '''editing''' the '''Template''' form you plan to use before launching OnePager Pro or after launching OnePager Pro by '''editing''' the '''Template''' using the '''access point''' in the '''OnePager choices''' ('''OPC''') form described in the following section.
+
11)  This recommendation can be done by '''editing''' the '''Template Properties''' form you plan to use before launching OnePager Pro or after launching OnePager Pro by '''editing''' the '''Template Properties''' form using the '''access point''' in the '''OnePager choices''' ('''OPC''') form described in the following section.
  
 
==Displaying Endpoints==
 
==Displaying Endpoints==
Line 32: Line 34:
 
2) A sample, Microsoft Project '''source plan''' is shown below with both '''deadline''' and '''endpoint''' definitions:
 
2) A sample, Microsoft Project '''source plan''' is shown below with both '''deadline''' and '''endpoint''' definitions:
  
 +
<center>[[File:P70-10_11_1-(1)-06042020.png]]</center>
 +
<center>P70-10_11_1-(1)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(1-1)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(1-1)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(1-1)-09192019.png</center>
 
<center>P70-10_11_1-70-(1-1)-09192019.png</center>
  
3) In the sample above, we see the typical task information with '''Flag20''' used to signal OnePager which rows to import, the Microsoft Project '''Deadline''' field and four '''Date''' fields ('''Date1, Date2, Date3, and Date4''') which are used to '''import''' information to OnePager representing '''Endpoints 1 through 4''' respectively.
+
3) In the sample above, we see the typical task information with '''Flag20''' used to signal OnePager which '''rows''' to '''import''', the Microsoft Project '''Deadline''' field and four '''Date''' fields ('''Date1, Date2, Date3, and Date4''') which are used to '''import''' information to OnePager representing '''Endpoints 1 through 4''' respectively.
  
4) When the '''OnePager''' button is clicked on the Microsoft Project tool bar and you click the '''NEW''' button on the '''OnePager Pro Start''' form, OnePager displays the first page of the '''OPC''' form as shown below:
+
4) When the '''OnePager''' button is clicked on the Microsoft Project '''Add-ins''' tool bar tab and you click the '''NEW''' button on the '''OnePager Pro Start''' form, OnePager displays the first page of the '''OPC''' form as shown below:
  
 +
<center>[[File:P70-10_11_1-(2)-06042020.png]]</center>
 +
<center>P70-10_11_1-(2)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(2)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(2)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(2)-09192019.png</center>
 
<center>P70-10_11_1-70-(2)-09192019.png</center>
  
5) Clicking the '''Next&gt;''' button with the '''Show field mappings''' checkbox checked '''On''' accesses the second page of the '''OPC''' form shown below:
+
5) Clicking the '''Next&gt;''' button with the '''Show field mappings''' checkbox checked '''ON''' accesses the second page of the '''OPC''' form shown below:
  
 +
<center>[[File:P70-10_11_1-(3)-06042020.png]]</center>
 +
<center>P70-10_11_1-(3)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(3)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(3)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(3)-09192019.png</center>
 
<center>P70-10_11_1-70-(3)-09192019.png</center>
Line 51: Line 59:
 
7) Navigate to the '''Task Bars''' tab and the '''Endpoints''' checkbox in the '''Task Bar Decorations''' control group of the form as shown below:
 
7) Navigate to the '''Task Bars''' tab and the '''Endpoints''' checkbox in the '''Task Bar Decorations''' control group of the form as shown below:
  
 +
<center>[[File:P70-10_11_1-(4)-06042020.png]]</center>
 +
<center>P70-10_11_1-(4)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(4)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(4)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(4)-09192019.png</center>
 
<center>P70-10_11_1-70-(4)-09192019.png</center>
  
8) Clicking the '''Endpoint Properties..." button accesses the '''Set endpoint properties''' form shown below where you can '''set and edit''' the properties of any one '''endpoint''' or all four.
+
8) Check the checkbox to '''ON''' and Clickthe '''Endpoint Properties..." button to access the '''Set endpoint properties''' form shown below where you can '''set and edit''' the properties of any one '''endpoint''' or all four.
  
 
==Editing All Endpoint Properties==
 
==Editing All Endpoint Properties==
  
1) The '''Set endpoint properties''' form is a '''multi-endpoint''' form in that using this one form you are able to '''edit''' the properties of all four '''endpoint shapes''' available for display in the chart.
+
1) The '''Set endpoint properties''' form is a '''multi-endpoint''' form in that using this one form allows you to '''edit''' the properties of all four '''endpoint shapes''' available for display in the chart.
  
 
===Set Endpoint Properties Form===
 
===Set Endpoint Properties Form===
Line 64: Line 74:
 
2) Clicking the '''Endpoint Properties...''' button accesses the '''Set endpoint properties''' form where the '''Choose endpoint''' dropdown is shown below allowing you the option to select to '''edit''' one of the four available '''endpoints''':
 
2) Clicking the '''Endpoint Properties...''' button accesses the '''Set endpoint properties''' form where the '''Choose endpoint''' dropdown is shown below allowing you the option to select to '''edit''' one of the four available '''endpoints''':
  
 +
<center>[[File:P70-10_11_1-(5)-06042020.png]]</center>
 +
<center>P70-10_11_1-(5)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(5)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(5)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(5)-09192019.png</center>
 
<center>P70-10_11_1-70-(5)-09192019.png</center>
  
3) In the illustration above, '''Endpoint 1''' is shown '''edited''' with all its available elements turned '''On'''.
+
3) In the illustration above, '''Endpoint 1''' is shown '''edited''' with all its available elements turned '''ON'''.
  
 
4) The above form is almost identical to the '''Set deadline properties''' form.  
 
4) The above form is almost identical to the '''Set deadline properties''' form.  
Line 73: Line 85:
 
5) The difference is the '''Show this endpoint''' checkbox which refers to the dropdown menu shown above whereby you can select which '''endpoint''' to control.  
 
5) The difference is the '''Show this endpoint''' checkbox which refers to the dropdown menu shown above whereby you can select which '''endpoint''' to control.  
  
6) In effect, this form is four (4) forms in one allowing you to turn '''On''' and '''Off''' each individual '''endpoint''' and configure the properties of each '''endpoint''' separately.
+
6) In effect, this form is four (4) forms in one allowing you to turn '''ON''' and '''OFF''' each individual '''endpoint''' and configure the properties of each '''endpoint''' separately.
  
 
7) The illustration above covers up two important controls that need to be addressed.  
 
7) The illustration above covers up two important controls that need to be addressed.  
Line 81: Line 93:
 
9) These controls are shown here:
 
9) These controls are shown here:
  
 +
<center>[[File:P70-10_11_1-(6)-06042020.png]]</center>
 +
<center>P70-10_11_1-(6)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(6)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(6)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(6)-09192019.png</center>
 
<center>P70-10_11_1-70-(6)-09192019.png</center>
Line 88: Line 102:
 
===Saving the Current Template Properties Form===
 
===Saving the Current Template Properties Form===
  
11) Now that the '''endpoints''' are defined with distinct properties for all task shapes in our example, go back to the '''Template Properties''' form, click the '''Save and use''' button to get back to the second page of the '''OPC''' form
+
11) Now that the '''endpoints''' are defined with distinct properties for all task bars in our example, go back to the '''Template Properties''' form, click the '''Save and use''' button to get back to the second page of the '''OPC''' form
  
 
12) Then, click the '''Create new chart''' button and OnePager produces the following chart:  
 
12) Then, click the '''Create new chart''' button and OnePager produces the following chart:  
  
 +
<center>[[File:P70-10_11_1-(7)-06042020.png]]</center>
 +
<center>P70-10_11_1-(7)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(7)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(7)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(7)-09192019.png</center>
 
<center>P70-10_11_1-70-(7)-09192019.png</center>
Line 105: Line 121:
 
16) For more information on '''Deadlines''', please see the article at:  [[Deadlines for Version 7.0 (OnePager Pro) | Deadlines for OnePager Pro]] 10.9.1-70.
 
16) For more information on '''Deadlines''', please see the article at:  [[Deadlines for Version 7.0 (OnePager Pro) | Deadlines for OnePager Pro]] 10.9.1-70.
  
17) The exception is only for the necessity to turn '''On''' and '''Off''' the individual '''endpoints''' through their respective '''Show this endpoint''' checkbox and to enter the Microsoft Project '''source plan''' field you need to use for the respective '''endpoints''' in the '''Field''' dropdown menu of the '''Set endpoint properties''' form.
+
17) The exception is only for the necessity to turn '''ON''' and '''OFF''' the individual '''endpoints''' through their respective '''Show this endpoint''' checkbox and to enter the Microsoft Project '''source plan''' field you need to use for the respective '''endpoints''' in the '''Field''' dropdown menu of the '''Set endpoint properties''' form.
  
 
==Editing Individual Task Endpoint Properties==
 
==Editing Individual Task Endpoint Properties==
  
1) '''Endpoint properties''' can be set or '''edited''' for individual task shapes.
+
1) '''Endpoint properties''' can be set or '''edited''' for individual task bars.
  
2) In addition to the capabilities for '''editing all Endpoint properties''' using the '''Template''' and/or '''Chart Properties''' forms, you can select and individually '''edit Endpoint properties''' showing in the chart.  
+
2) In addition to the capabilities for '''editing all Endpoint properties''' using the '''Template Properties''' and/or '''Chart Properties''' forms, you can select and individually '''edit Endpoint properties''' showing in the chart.  
  
 
3) A prerequisite for '''editing''' individual '''endpoint properties''' is the necessity for '''endpoint''' data to be '''imported''' from the Microsoft Project '''source plan'''.  
 
3) A prerequisite for '''editing''' individual '''endpoint properties''' is the necessity for '''endpoint''' data to be '''imported''' from the Microsoft Project '''source plan'''.  
  
===Selecting Individual Task or Tasks===
+
===Selecting Individual Task Bar or Bars===
  
4) Individual task shape '''endpoint properties''' can be '''edited''' by selecting the desired task shape or task shapes with a left-click operation and then right-clicking on the '''Format...''' command in the '''context menu''' as shown below:
+
4) Individual task bar '''endpoint properties''' can be '''edited''' by selecting the desired task bar or task bars with a right-click operation to access the task bar right-click '''context menu''' and then clicking on the '''Format...''' command in the '''context menu''' as shown below:
  
 +
<center>[[File:P70-10_11_1-(8)-06042020.png]]</center>
 +
<center>P70-10_11_1-(8)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(8)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(8)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(8)-09192019.png</center>
 
<center>P70-10_11_1-70-(8)-09192019.png</center>
  
5) Before you can do so, you must confirm that the '''Endpoints''' checkbox in either the '''Template''' or '''Chart Properties''' form's '''Task Bars''' and/or '''Milestones''' tab is checked '''On'''.
+
5) Before you can do so, you must confirm that the '''Endpoints''' checkbox in either the '''Template Properties''' or '''Chart Properties''' form's '''Task Bars''' tab is checked '''ON'''.
  
 
===Accessing the Change Task/Milestone Properties Form===
 
===Accessing the Change Task/Milestone Properties Form===
  
6) Select the '''Format…''' command accesses the '''Change Task/Milestone Properties''' form.  
+
6) Selecting the '''Format…''' command accesses the '''Change Task/Milestone Properties''' form.  
  
 
7) Next, navigate to the '''Endpoints''' tab, which displays the '''endpoint''' control options shown below:
 
7) Next, navigate to the '''Endpoints''' tab, which displays the '''endpoint''' control options shown below:
  
 +
<center>[[File:P70-10_11_1-(9)-06042020.png]]</center>
 +
<center>P70-10_11_1-(9)-06042020.png</center>
 
<center>[[File:P70-10_11_1-70-(9)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(9)-09192019.png]]</center>
 
<center>P70-10_11_1-70-(9)-09192019.png</center>
 
<center>P70-10_11_1-70-(9)-09192019.png</center>
  
8) From the '''Endpoints''' tab of the form above, you are able to turn the selected '''endpoint''' '''On''' or '''Off''', show the '''endpoint connector''' to the task shape, and show or hide the '''endpoint date label text'''.
+
8) From the '''Endpoints''' tab of the form above, you are able to turn the selected '''endpoint''' '''ON''' or '''OFF''', show the '''endpoint connector''' to the task bar, and show or hide the '''endpoint date label text'''.
 +
 
 +
9) Recall that selecting a milestone symbol in the manner described above to access its '''Change Task/Milestone Properties''' form accesses the version of the form without either the '''Critical Path''' or the '''Endpoints''' tab as shown here:
 +
 
 +
<center>[[File:P70-10_11_1-(10)-06042020.png]]</center>
 +
<center>P70-10_11_1-(10)-06042020.png</center>
  
 
===Example===
 
===Example===
  
9) For example, using the '''Deadlines-Endpoints Example''' previously illustrated above, suppose we want to make the following '''edits''':
+
10) For example, using the '''Deadlines-Endpoints Example''' previously illustrated above, suppose we want to make the following '''edits''':
  
:* Turn '''Off''' the display of Endpoint 1 for Task B
+
:* Turn '''OFF''' the display of Endpoint 1 for Task B
 
:* Hide the '''Endpoint connector''' for Endpoint 1 to Task C
 
:* Hide the '''Endpoint connector''' for Endpoint 1 to Task C
 
:* Hide the '''Date Label''' for Endpoint 4 for Task C under the task
 
:* Hide the '''Date Label''' for Endpoint 4 for Task C under the task
  
10) For each task shape we select the task shape with a left-click, then right-click to get to the '''context menu''', select the '''Format…''' command to get to the '''Change Task/Milestone Properties''' form and finally accessed the '''Endpoints''' tab.  
+
11) For each task bar we select the task bar with a right-click to access the task bar right-click '''context menu''', select the '''Format…''' command to get to the '''Change Task/Milestone Properties''' form, and finally accessed the '''Endpoints''' tab.  
  
11) These steps are performed for each of the task shapes involved starting with Task B where one '''edit''' to '''Endpoint 1''' was made and then to Task C where an '''edit''' was made to '''Endpoints 1 and 4'''.  
+
12) These steps are performed for each of the task bars involved starting with Task B where one '''edit''' to '''Endpoint 1''' was made and then to Task C where an '''edit''' was made to '''Endpoints 1 and 4'''.  
  
12) After making these '''edits''' the chart looks like this:
+
13) After making these '''edits''' the chart looks like this:
  
 
<center>[[File:P70-10_11_1-70-(10)-09192019.png]]</center>
 
<center>[[File:P70-10_11_1-70-(10)-09192019.png]]</center>

Revision as of 20:16, 3 June 2020

About Editing Endpoints

1) There are four (4) endpoints definable in OnePager for each task bar.

2) By definition, milestone symbols in OnePager do not have multiple endpoints.

3) Accordingly, endpoints for milestone symbols are not supported and there is no decoration controls for endpoints in the Template Properties or Chart Properties form's Milestones tab.

4) For all practical purposes, the four possible endpoints (Endpoint1, Endpoint2, Endpoint3, and Endpoint4) can be thought of as additional deadlines dates for task bars that can be defined to communicate related dates associated with the task bar.

5) As an additional thought, you can consider the four endpoints as task-oriented milestones as they occupy the same row as their parent task shape.

6) The control and the behavior of all four endpoints are identical to that discussed for deadlines.

7) For more information on Deadlines, please see the article at: Deadlines for OnePager Pro 10.9.1-70.

8) By convention and as a default, the initial association of Endpoints 1 through 4 are to Microsoft Project source plan fields is as follows:

  • Endpoint 1: Start Date.
  • Endpoint 2: Finish Date.
  • Endpoint 3: Baseline Start Date.
  • Endpoint 4: Baseline Finish Date.

9) These default settings are contained in all distributed OnePager Pro Template Properties forms.

10) Since controls are provided as described below whereby you can edit the endpoint association with Microsoft Project source plan fields, it is recommended that you establish your endpoint relationships to specific Microsoft Project date fields before creating the first chart.

11) This recommendation can be done by editing the Template Properties form you plan to use before launching OnePager Pro or after launching OnePager Pro by editing the Template Properties form using the access point in the OnePager choices (OPC) form described in the following section.

Displaying Endpoints

1) For OnePager to properly display your endpoints, you must first define the endpoint field in Microsoft Project and map them to OnePager through the OnePager choices (OPC) form.

2) A sample, Microsoft Project source plan is shown below with both deadline and endpoint definitions:

P70-10 11 1-(1)-06042020.png
P70-10_11_1-(1)-06042020.png
File:P70-10 11 1-70-(1-1)-09192019.png
P70-10_11_1-70-(1-1)-09192019.png

3) In the sample above, we see the typical task information with Flag20 used to signal OnePager which rows to import, the Microsoft Project Deadline field and four Date fields (Date1, Date2, Date3, and Date4) which are used to import information to OnePager representing Endpoints 1 through 4 respectively.

4) When the OnePager button is clicked on the Microsoft Project Add-ins tool bar tab and you click the NEW button on the OnePager Pro Start form, OnePager displays the first page of the OPC form as shown below:

P70-10 11 1-(2)-06042020.png
P70-10_11_1-(2)-06042020.png
File:P70-10 11 1-70-(2)-09192019.png
P70-10_11_1-70-(2)-09192019.png

5) Clicking the Next> button with the Show field mappings checkbox checked ON accesses the second page of the OPC form shown below:

P70-10 11 1-(3)-06042020.png
P70-10_11_1-(3)-06042020.png
File:P70-10 11 1-70-(3)-09192019.png
P70-10_11_1-70-(3)-09192019.png

6) Clicking the Edit current template… button takes you to the Template Properties form.

7) Navigate to the Task Bars tab and the Endpoints checkbox in the Task Bar Decorations control group of the form as shown below:

P70-10 11 1-(4)-06042020.png
P70-10_11_1-(4)-06042020.png
File:P70-10 11 1-70-(4)-09192019.png
P70-10_11_1-70-(4)-09192019.png

8) Check the checkbox to ON and Clickthe Endpoint Properties..." button to access the Set endpoint properties form shown below where you can set and edit the properties of any one endpoint or all four.

Editing All Endpoint Properties

1) The Set endpoint properties form is a multi-endpoint form in that using this one form allows you to edit the properties of all four endpoint shapes available for display in the chart.

Set Endpoint Properties Form

2) Clicking the Endpoint Properties... button accesses the Set endpoint properties form where the Choose endpoint dropdown is shown below allowing you the option to select to edit one of the four available endpoints:

P70-10 11 1-(5)-06042020.png
P70-10_11_1-(5)-06042020.png
File:P70-10 11 1-70-(5)-09192019.png
P70-10_11_1-70-(5)-09192019.png

3) In the illustration above, Endpoint 1 is shown edited with all its available elements turned ON.

4) The above form is almost identical to the Set deadline properties form.

5) The difference is the Show this endpoint checkbox which refers to the dropdown menu shown above whereby you can select which endpoint to control.

6) In effect, this form is four (4) forms in one allowing you to turn ON and OFF each individual endpoint and configure the properties of each endpoint separately.

7) The illustration above covers up two important controls that need to be addressed.

8) The Show this endpoint checkbox and the Field dropdown menu by which you tell OnePager which Microsoft Project source plan field is used for each particular endpoint.

9) These controls are shown here:

P70-10 11 1-(6)-06042020.png
P70-10_11_1-(6)-06042020.png
File:P70-10 11 1-70-(6)-09192019.png
P70-10_11_1-70-(6)-09192019.png

10) As necessary, repeat the above editing steps for Endpoint 2 through 4 as required such that when the endpoint data are imported into OnePager the endpoint shapes and other properties are unique.

Saving the Current Template Properties Form

11) Now that the endpoints are defined with distinct properties for all task bars in our example, go back to the Template Properties form, click the Save and use button to get back to the second page of the OPC form

12) Then, click the Create new chart button and OnePager produces the following chart:

File:P70-10 11 1-(7)-06042020.png
P70-10_11_1-(7)-06042020.png
File:P70-10 11 1-70-(7)-09192019.png
P70-10_11_1-70-(7)-09192019.png

13) For the illustration above, Endpoints 1 through 4 are lined up from left to right in each row.

Editing Endpoint Properties

14) The above section's discussion covered the set up and initial display of endpoints.

15) Recall that endpoint controls are exactly identical to the controls for deadlines.

16) For more information on Deadlines, please see the article at: Deadlines for OnePager Pro 10.9.1-70.

17) The exception is only for the necessity to turn ON and OFF the individual endpoints through their respective Show this endpoint checkbox and to enter the Microsoft Project source plan field you need to use for the respective endpoints in the Field dropdown menu of the Set endpoint properties form.

Editing Individual Task Endpoint Properties

1) Endpoint properties can be set or edited for individual task bars.

2) In addition to the capabilities for editing all Endpoint properties using the Template Properties and/or Chart Properties forms, you can select and individually edit Endpoint properties showing in the chart.

3) A prerequisite for editing individual endpoint properties is the necessity for endpoint data to be imported from the Microsoft Project source plan.

Selecting Individual Task Bar or Bars

4) Individual task bar endpoint properties can be edited by selecting the desired task bar or task bars with a right-click operation to access the task bar right-click context menu and then clicking on the Format... command in the context menu as shown below:

P70-10 11 1-(8)-06042020.png
P70-10_11_1-(8)-06042020.png
File:P70-10 11 1-70-(8)-09192019.png
P70-10_11_1-70-(8)-09192019.png

5) Before you can do so, you must confirm that the Endpoints checkbox in either the Template Properties or Chart Properties form's Task Bars tab is checked ON.

Accessing the Change Task/Milestone Properties Form

6) Selecting the Format… command accesses the Change Task/Milestone Properties form.

7) Next, navigate to the Endpoints tab, which displays the endpoint control options shown below:

P70-10 11 1-(9)-06042020.png
P70-10_11_1-(9)-06042020.png
File:P70-10 11 1-70-(9)-09192019.png
P70-10_11_1-70-(9)-09192019.png

8) From the Endpoints tab of the form above, you are able to turn the selected endpoint ON or OFF, show the endpoint connector to the task bar, and show or hide the endpoint date label text.

9) Recall that selecting a milestone symbol in the manner described above to access its Change Task/Milestone Properties form accesses the version of the form without either the Critical Path or the Endpoints tab as shown here:

P70-10 11 1-(10)-06042020.png
P70-10_11_1-(10)-06042020.png

Example

10) For example, using the Deadlines-Endpoints Example previously illustrated above, suppose we want to make the following edits:

  • Turn OFF the display of Endpoint 1 for Task B
  • Hide the Endpoint connector for Endpoint 1 to Task C
  • Hide the Date Label for Endpoint 4 for Task C under the task

11) For each task bar we select the task bar with a right-click to access the task bar right-click context menu, select the Format… command to get to the Change Task/Milestone Properties form, and finally accessed the Endpoints tab.

12) These steps are performed for each of the task bars involved starting with Task B where one edit to Endpoint 1 was made and then to Task C where an edit was made to Endpoints 1 and 4.

13) After making these edits the chart looks like this:

File:P70-10 11 1-70-(10)-09192019.png
P70-10_11_1-70-(10)-09192019.png

Related Links

Manual Editing Task/Milestone Shapes and Text Labels (Portal) 9.0.1-70

Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.) 9.2.1-70

Labeling Task/Milestone Dates for OnePager Pro 10.1.1-70

Percent complete for OnePager Pro 10.3.1-70

Baselines for OnePager Pro 10.5.1-70

Deadlines for OnePager Pro 10.9.1-70

Editing with the Chart Properties form (Portal) 21.0.1-70

Managing Templates (Portal) 24.0.1-70

(10.11.1-70)