(Created page with "==About Modifying Date Labels== 1) '''Date label''' displays are driven by the '''start and finish date''' data imported from the Microsoft Excel '''source plan'''. 2) Ever...")
 
 
(21 intermediate revisions by 2 users not shown)
Line 1: Line 1:
==About Modifying Date Labels==
+
==About Date Labels==
  
1) '''Date label''' displays are driven by the '''start and finish date''' data imported from the Microsoft Excel '''source plan'''.  
+
'''Date label''' displays are driven by the '''start and finish date''' data imported from the Microsoft Excel '''source plan'''.  Every task in a Microsoft Excel '''source plan''' has a designated '''start and finish date'''.  A milestone's '''start and finish dates''' are usually the same. You can choose to use '''date labels''' for tasks, milestones, or both.
  
2) Every task in a Microsoft Excel '''source plan''' has a designated '''start and finish date'''.
+
==Using the Chart Properties Form to Edit Date Labels== 
  
3) A milestones’ '''start and finish dates''' are usually the same. You can choose to use date labels for tasks, milestones, or both.
+
''All''' task and milestone shape '''date labels''' cab be '''edited''' without changing the settings in the current '''Template''' by clicking the '''Chart Properties''' button on the '''Home''' ribbon in the '''Settings''' group as shown here:
  
==Modifying All Date Labels in a Project View== 
+
<center>[[File:X70-10_2_1-70-(1)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(1)-09142019.png</center>-->
  
All task and milestone date labels can be modified in a project view without changing the settings in the current '''Template''' by using the following steps:
+
Clicking the '''Chart Properties''' button accesses the '''Chart Properties''' form. Next, navigate to either the '''Task Bars''' or '''Milestones''' tab as appropriate.  On the '''Task Bars''' tab, as shown below, ensure that the '''Date Labels''' checkbox is checked '''On''':
  
1) Click the Project-View Properties ('''PVP''') button on the '''Home''' ribbon in the '''Settings''' group.
+
<center>[[File:X70-10_2_1-70-(2-1)-09252020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(2-1)-09252020.png</center>-->
  
2)  Then, navigate to either the '''Task Bars''' or '''Milestones'''tab as appropriate.
+
Clicking the '''Date Label Properties...''' button to the right of the '''Date Labels''' checkbox accesses the '''Set Date Label Properties''' form as shown here:
  
3) Ensure that the '''Date Labels''' checkbox is checked as shown below:
+
<center>[[File:X70-10_2_1-70-(3-1)-09252020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(3-1)-09252020.png</center>-->
  
<center>[[File:X60-10_2_1-60-(1)-02092017.png]]</center>
+
There are eight (8) controls in the form above.   All actions are consistent with identical controls found elsewhere in OnePager Express ('''OPX''').
<center>X60-10_2_1-60-(1)-02092017.png</center>
+
  
4)  Clicking the '''Date Label Properties...''' button to the right of the '''Date Labels''' checkbox accesses the '''Set Date Label Properties''' form as shown here:
+
===Date Label Font===
  
<center>[[File:X60-10_2_1-60-(2)-02092017.png]]</center>
+
This control causes the '''Font properties''' form shown below to appear when the dropdown button is clicked.  
<center>X60-10_2_1-60-(2)-02092017.png</center>
+
  
5) There are eight controls in the form above.   All actions are consistent with identical controls found elsewhere in OnePager Express ('''OPX''').
+
<center>[[File:X70-10_2_1-70-(3A)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(3A)-09142019.png</center>-->
  
:a) '''Date label font'''. This control causes the '''Font properties''' form shown below to appear when the dropdown button is clicked. Within this form are controls for date text '''font style''', '''color''' and '''size'''. Additionally, you can set the date text to '''Bold''', ''Italic'', or [[Underline]].
+
Within this form are controls for date text '''font style''', '''color''' and '''size'''. Additionally, you can set the date text to '''Bold''', ''Italic'', or [[Underline]].
  
<center>[[File:X52-10_2-(3)-06082015.png]]</center>
+
===Show (start/finish) and Position Date Label Text===
  
:b) '''Show (start/finish) and Position Date Label Text'''.  The two checkboxes, '''Show start date''' and '''Show finish date''', control the display of these two dates, respectively. When checked, you have the option of selecting the position of the dates individually or together:
+
The two checkboxes, '''Show start date''' and '''Show finish date''', control the display of these two dates, respectively. When checked, you have the option of selecting the position of the dates individually or together:
  
<center>[[File:X52-10_2-(4)-06082015.png]]</center>
+
<center>[[File:X70-10_2_1-70-(4)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(4)-09142019.png</center>-->
  
===Note===
+
The '''Start field''' and '''Finish field''' are dropdown lists of all '''date type fields imported''' from your '''source plan''' giving you the options to select a different '''start date field''' or '''finish date field''' for use in the chart.  A '''Start field''' dropdown list example is shown below:
  
::The combination of '''task label''' display and '''date label''' display for all task/milestones can cause a crowded appearance. Use the '''date label''' positioning controls to achieve the appearance desired in combination with '''task labels'''.
+
<center>[[File:X70-10_2_1-70-(5)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(5)-09142019.png</center>-->
  
:c) '''Date Format'''. OnePager provides a great deal of variety for the selection of '''date formats''' for task/milestones.  For consistency, the available formats for task/milestone '''date formats''' are the same as for '''date formats''' used for the '''time axis''' at the top/bottom of the project view. A sample of '''date formats''' are shown below:
+
The combination of '''task label''' display and '''date label''' display for '''all''' task/milestone shapes can cause a crowded appearance around the task/milestone shape.  Use the '''date label''' positioning controls to achieve the appearance desired in combination with '''task labels'''.
  
<center>[[File:X52-10_2-(5)-06082015.png]]</center>
+
===Date Format===
  
:d) '''Separator'''.  The '''separators''' are pairs of symbols that help differentiate the '''date label''' from other nearby text (e.g., '''task labels''' or '''percent complete'''). There are several '''separator''' options to select from as shown below:
+
OnePager provides a great deal of variety for the selection of '''date formats''' for task/milestonesFor consistency, the available formats for task/milestone shape's '''date formats''' are the same as for '''date formats''' used for the '''time axis''' at the top/bottom of the chart. A sample of '''date formats''' are shown below:
  
<center>[[File:X52-10_2-(6)-06082015.png]]</center>
+
<center>[[File:X70-10_2_1-70-(6)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(6)-09142019.png</center>-->
  
:e) '''Use Fiscal Year'''. The '''Use fiscal year''' checkbox is an instruction, if checked, to OnePager to show the displayed date in the '''fiscal year''' format for the project view’s '''time axis'''. OnePager takes the action only if the '''time axis''' for the project view is, indeed, displaying the '''time axis''' in a '''fiscal year''' format.
+
===Separator===
  
6)  When the '''Date Labels''' checkbox is checked and both the '''Show start date''' and '''Show finish date''' checkboxes are checked in the '''Set date label properties''' form, the '''date labels''' in the project view looks like this:
+
The '''separators''' are pairs of symbols that help differentiate the '''date label''' from other nearby text (e.g., '''task labels''' or '''percent complete''').  There are several '''separator''' options to select from as shown below:
  
<center>[[File:X52-10_2-(7)-06082015.png]]</center>
+
<center>[[File:X70-10_2_1-70-(7)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(7)-09142019.png</center>-->
  
:a) '''Date Label''' fonts are overridden by '''Task Label''' fonts when the '''Date Label''' and '''Task Label''' are in the '''same position'''.
+
===Use Fiscal Year===
  
:b) If the '''Date Label''' is put in a '''different''' position than the '''Task Label''', the '''Date Label''' font's properties are honored as expected.
+
The '''Use fiscal year''' checkbox is an instruction, if checked '''On''', to OnePager to show the displayed '''date''' in the '''fiscal year''' format for the chart’s '''time axis'''.  OnePager takes the action only if the '''time axis''' for the chart is, indeed, displaying the '''time axis''' in a '''fiscal year''' format.  Make sure that the '''time axis''' is in '''fiscal''' mode to assure that '''date labels''' displayed are consistent.
  
==Modifying Individual Date Labels in the Project View==
+
===Sample Start and Finish Date Labels in the Chart===
  
1) The default settings for '''date labels''' on individual task/milestones can be modified by using the following steps:
+
When the '''Date Labels''' checkbox is checked '''On''' and both the '''Show start date''' and '''Show finish date''' checkboxes are checked '''On''' in the '''Set date label properties''' form, the '''date labels''' looks like this:
  
2) You can select the task/milestone and right-click it to reveal the context menu with the '''Format…''' command or click the '''Format…''' button on the '''Home''' ribbon after selecting the desired tasks/milestones.
+
<center>[[File:X70-10_2_1-70-(8)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8)-09142019.png</center>-->
  
<center>[[File:P53-10_0_1-53-(2)-03142016.png]]</center>
+
'''Date Label fonts''' are overridden by '''Task Label fonts''' when the '''Date Label''' and '''Task Label''' are in the '''same position'''. If the '''Date Label''' is put in a '''different''' position than the '''Task Label''', the '''Date Label font's''' properties are honored.
  
 +
==Editing Individual Date Labels in the Chart==
  
<center>[[File:P52-10_-(2)-06012015.png]]</center>
+
There are three (3) methods for accessing the controls for '''editing''' individual '''date labels''' on individual tasks and milestones:
  
3) Either way, select the '''Date''' tab in the '''Change Marker Properties''' form which looks like this:
+
:*  You can right-click on the selected task/milestone shape to access the context menu followed by clicking the '''Format...''' command in the menu.
 +
:* You can right-click on the selected '''date label''' itself to access the '''one command''' context menu followed by clicking the '''Format...''' command.
 +
:* You can click the '''Format...''' button on the '''Home''' ribbon tab.
  
<center>[[File:X52-10_2-(8)-06082015.png]]</center>
+
Each of these methods is discussed below.
  
4) When the '''Show Dates''' checkbox is checked as shown above, you can decide if you want to '''Show Start Date''', '''Show Finish Dates''' or both by checking the appropriate checkbox also shown above.
+
===Right-Clicking a Task/Milestone===
 +
 
 +
Accessing the '''Change Task/Milestone Properties''' form with this method requires you to right-click on the task or milestone shape.  This action accesses the available commands in the '''context menu''' shown below:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8A-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8A-1)-09092020.png</center>-->
 +
 
 +
Clicking the '''Format…''' command accesses the '''Change Task/Milestone Properties''' form at the '''Format''' tab as shown here:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8B-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8B-1)-09092020.png</center>-->
 +
 
 +
The '''Format''' tab is shown above where you can '''edit''' the task/milestone shape's properties shown. Navigate to the '''Dates''' tab on the '''Change Task/Milestones Properties''' form to make your '''edits''' to the selected '''dates'''. The controls in the '''Change Task/Milestone Properties''' form's '''Date''' tab are discussed below.
 +
 
 +
===Right-Clicking the Date Label===
 +
 
 +
The '''Date Label''' when displayed can also be right-clicked to access the one command context menu as shown below:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8C-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8C-1)-09092020.png</center>-->
 +
 
 +
Clicking the '''Format…''' command accesses the '''Change Task/Milestone Properties''' form at the '''Dates''' tab as shown here:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8D-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8D-1)-09092020.png</center>-->
 +
 
 +
===Format button on the OnePager Express Home Ribbon===
 +
 
 +
The '''Change Task/Milestone Properties''' form can also be accessed by clicking the '''Format…''' button after you selected one or more task/milestone shapes to '''edit'''.  The '''Format...'''button on the ribbon is shown below:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8E)-09142019.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8E)-09142019.png</center>-->
 +
 
 +
After clicking the '''Format...''' button as shown above, the '''Change Task/Milestone Properties''' form is accessed at the '''Format''' tab as shown here:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8B-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8B-1)-09092020.png</center>-->
 +
 
 +
Navigate to the '''Dates''' tab on the '''Change Task/Milestones Properties''' form to make your '''edits''' to the selected '''dates'''. The controls in the '''Change Task/Milestone Properties''' form's '''Date''' tab are discussed below.
 +
 
 +
===Using the Change Task/Milestone Properties Form's Date Tab===
 +
 
 +
Any method you use the '''Date''' tab in the '''Change Task/Milestone Properties''' form looks like this:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8G-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8G-1)-09092020.png</center>-->
 +
 
 +
====Show Dates====
 +
 
 +
When the '''Show Dates''' checkbox is checked '''On''' as shown above, you can decide if you want to '''Show Start Date''', '''Show Finish Dates''' or both by checking the appropriate checkbox '''On''' also shown above.
 +
 
 +
====Date Position Options====
 
   
 
   
4) '''Date Label Position'''.  You have the option to change the either the '''Start Date Position''' or the '''Finish Date Position''' or both by clicking the dropdown menu buttons to the immediate right of the checkboxes as shown here:
+
You have the option to change either the '''Start Date Position''' or the '''Finish Date Position''' or both by clicking the dropdown menu buttons to the immediate right of the checkboxes as shown here:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8H-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8H-1)-09092020.png</center>-->
 +
 
 +
====Date Font Properties====
 +
 
 +
Clicking the '''Date Font''' dropdown menu button accesses the '''Font properties''' form shown below:
 +
 
 +
<center>[[File:X70-10_2_1-70-(8I-1)-09092020.png]]</center>
 +
<!--<center>X70-10_2_1-70-(8I-1)-09092020.png</center>-->
  
<center>[[File:X52-10_2-(9)-06082015.png]]</center>
+
Within the '''Font properties''' form are controls for date text '''font style''', '''color''' and '''size'''. Additionally, you can set the date text to '''Bold''', ''Italic'', or [[Underline]].
  
5) '''Date Font'''. Clicking the '''Date Font''' dropdown menu button brings up the '''Font properties''' form shown below:
+
==Related Link==
  
<center>[[File:X52-10_2-(10)-06082015.png]]</center>
+
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!--9.0.1-70-->
  
:a) Within the '''Font properties''' form are controls for date text '''font style''', '''color''' and '''size'''.
+
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] <!--21.0.1-70-->
  
:b) Additionally, you can set the date text to '''Bold''', ''Italic'', or [[Underline]].
+
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
  
 
(10.2.1-70)
 
(10.2.1-70)
  
 
[[Category:Version 7.0]]
 
[[Category:Version 7.0]]
[[Category:Project Views]]
+
[[Category:Charts]]
[[Category:Project-View Properties Form]]
+
[[Category:Chart Properties Form]]
[[Category:Editing a Project View]]
+
[[Category:Editing the Chart]]
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Decorations]]
 
[[Category:Task/Milestone Decorations]]
 +
[[Category:Labels]]
 
[[Category:Mavericks]]
 
[[Category:Mavericks]]
 
[[Category:OnePager Express]]
 
[[Category:OnePager Express]]

Latest revision as of 21:04, 12 January 2021

About Date Labels

Date label displays are driven by the start and finish date data imported from the Microsoft Excel source plan. Every task in a Microsoft Excel source plan has a designated start and finish date. A milestone's start and finish dates are usually the same. You can choose to use date labels for tasks, milestones, or both.

Using the Chart Properties Form to Edit Date Labels

All' task and milestone shape date labels cab be edited without changing the settings in the current Template by clicking the Chart Properties button on the Home ribbon in the Settings group as shown here:

X70-10 2 1-70-(1)-09142019.png

Clicking the Chart Properties button accesses the Chart Properties form. Next, navigate to either the Task Bars or Milestones tab as appropriate. On the Task Bars tab, as shown below, ensure that the Date Labels checkbox is checked On:

X70-10 2 1-70-(2-1)-09252020.png

Clicking the Date Label Properties... button to the right of the Date Labels checkbox accesses the Set Date Label Properties form as shown here:

X70-10 2 1-70-(3-1)-09252020.png

There are eight (8) controls in the form above. All actions are consistent with identical controls found elsewhere in OnePager Express (OPX).

Date Label Font

This control causes the Font properties form shown below to appear when the dropdown button is clicked.

X70-10 2 1-70-(3A)-09142019.png

Within this form are controls for date text font style, color and size. Additionally, you can set the date text to Bold, Italic, or Underline.

Show (start/finish) and Position Date Label Text

The two checkboxes, Show start date and Show finish date, control the display of these two dates, respectively. When checked, you have the option of selecting the position of the dates individually or together:

X70-10 2 1-70-(4)-09142019.png

The Start field and Finish field are dropdown lists of all date type fields imported from your source plan giving you the options to select a different start date field or finish date field for use in the chart. A Start field dropdown list example is shown below:

X70-10 2 1-70-(5)-09142019.png

The combination of task label display and date label display for all task/milestone shapes can cause a crowded appearance around the task/milestone shape. Use the date label positioning controls to achieve the appearance desired in combination with task labels.

Date Format

OnePager provides a great deal of variety for the selection of date formats for task/milestones. For consistency, the available formats for task/milestone shape's date formats are the same as for date formats used for the time axis at the top/bottom of the chart. A sample of date formats are shown below:

X70-10 2 1-70-(6)-09142019.png

Separator

The separators are pairs of symbols that help differentiate the date label from other nearby text (e.g., task labels or percent complete). There are several separator options to select from as shown below:

X70-10 2 1-70-(7)-09142019.png

Use Fiscal Year

The Use fiscal year checkbox is an instruction, if checked On, to OnePager to show the displayed date in the fiscal year format for the chart’s time axis. OnePager takes the action only if the time axis for the chart is, indeed, displaying the time axis in a fiscal year format. Make sure that the time axis is in fiscal mode to assure that date labels displayed are consistent.

Sample Start and Finish Date Labels in the Chart

When the Date Labels checkbox is checked On and both the Show start date and Show finish date checkboxes are checked On in the Set date label properties form, the date labels looks like this:

X70-10 2 1-70-(8)-09142019.png

Date Label fonts are overridden by Task Label fonts when the Date Label and Task Label are in the same position. If the Date Label is put in a different position than the Task Label, the Date Label font's properties are honored.

Editing Individual Date Labels in the Chart

There are three (3) methods for accessing the controls for editing individual date labels on individual tasks and milestones:

  • You can right-click on the selected task/milestone shape to access the context menu followed by clicking the Format... command in the menu.
  • You can right-click on the selected date label itself to access the one command context menu followed by clicking the Format... command.
  • You can click the Format... button on the Home ribbon tab.

Each of these methods is discussed below.

Right-Clicking a Task/Milestone

Accessing the Change Task/Milestone Properties form with this method requires you to right-click on the task or milestone shape. This action accesses the available commands in the context menu shown below:

X70-10 2 1-70-(8A-1)-09092020.png

Clicking the Format… command accesses the Change Task/Milestone Properties form at the Format tab as shown here:

X70-10 2 1-70-(8B-1)-09092020.png

The Format tab is shown above where you can edit the task/milestone shape's properties shown. Navigate to the Dates tab on the Change Task/Milestones Properties form to make your edits to the selected dates. The controls in the Change Task/Milestone Properties form's Date tab are discussed below.

Right-Clicking the Date Label

The Date Label when displayed can also be right-clicked to access the one command context menu as shown below:

X70-10 2 1-70-(8C-1)-09092020.png

Clicking the Format… command accesses the Change Task/Milestone Properties form at the Dates tab as shown here:

X70-10 2 1-70-(8D-1)-09092020.png

Format button on the OnePager Express Home Ribbon

The Change Task/Milestone Properties form can also be accessed by clicking the Format… button after you selected one or more task/milestone shapes to edit. The Format...button on the ribbon is shown below:

X70-10 2 1-70-(8E)-09142019.png

After clicking the Format... button as shown above, the Change Task/Milestone Properties form is accessed at the Format tab as shown here:

X70-10 2 1-70-(8B-1)-09092020.png

Navigate to the Dates tab on the Change Task/Milestones Properties form to make your edits to the selected dates. The controls in the Change Task/Milestone Properties form's Date tab are discussed below.

Using the Change Task/Milestone Properties Form's Date Tab

Any method you use the Date tab in the Change Task/Milestone Properties form looks like this:

X70-10 2 1-70-(8G-1)-09092020.png

Show Dates

When the Show Dates checkbox is checked On as shown above, you can decide if you want to Show Start Date, Show Finish Dates or both by checking the appropriate checkbox On also shown above.

Date Position Options

You have the option to change either the Start Date Position or the Finish Date Position or both by clicking the dropdown menu buttons to the immediate right of the checkboxes as shown here:

X70-10 2 1-70-(8H-1)-09092020.png

Date Font Properties

Clicking the Date Font dropdown menu button accesses the Font properties form shown below:

X70-10 2 1-70-(8I-1)-09092020.png

Within the Font properties form are controls for date text font style, color and size. Additionally, you can set the date text to Bold, Italic, or Underline.

Related Link

Manual Editing Task/Milestone Shapes and Text Labels (Portal)

Editing with the Chart Properties form (Portal)

Managing Templates (Portal)

(10.2.1-70)