If you need to show '''dependencies''', OnePager provides a means for you to '''link''' one task or milestone with others.   
+
If you need to show '''dependencies''' in your project views, OnePager 6.1 provides a means for you to '''link''' one task or milestone shape with others using '''predecessor''' data from your '''source plan'''.   
  
In OnePager Pro/Express version 6.1 you can now import '''Task Link''' data from your '''source plans'''.  You can manipulate '''Task Link''' representations in your project views; exercise controls by defining '''Task Link''' '''show/hide''' filter rules; and use enhanced graphics  to alter '''Task Link''' colors, arrow heads, and line styles. 
+
1) Using OnePager Pro/Express version 6.1 you can now:
  
As with previous versions of OnePager you can manually create and edit '''Task Links'''.
+
:(1) Import '''Task Link''' data from your '''source plans'''.
  
Please use the Wiki article links below which provide detailed  information on the new  '''data-driven Task Links'''  feature and the enhancements made to  '''manually created Task Links'''  in OnePager 6.1.  The top two articles in the set of links below provide you with an overview to the new '''Data-Driven Task Link''' feature and the enhancements made to the existing '''Manual Task Link''' capabilities.
+
:(2) Manipulate '''Task Link''' representations in your project views.
 +
 
 +
:(3) Use controls to define '''Task Link''' '''show/hide''' filtering rules.
 +
 
 +
:(4) And use enhanced editing techniques  to alter '''Task Link colors, arrow heads, line styles, and other properties'''. 
 +
 
 +
2) As with previous versions of OnePager you can manually create and edit '''Task Links'''.
 +
 
 +
3) Finally, you are provided with tools so you can manage all '''Task Links''' in your project view and all its various snapshots.
 +
 
 +
4) Please use the Wiki article links below which provide detailed  information on the new  '''data-driven Task Links'''  feature and the enhancements made to  '''manually created Task Links'''  in OnePager 6.1.  The top row's two articles in the table of links below provide you with an overview to the new '''Data-Driven Task Link''' feature and the enhancements made to the existing '''Manual Task Link''' capabilities.
  
 
<center>
 
<center>
Line 32: Line 42:
 
|}
 
|}
 
</center>
 
</center>
 
<!--
 
{| class="wikitable"
 
| [[Manually Creating and Editing Task Links for OnePager Pro and Express Version 6.1 | Manually Creating and Editing Task Links for OnePager Pro and Express]] 19.1.1-61
 
|}
 
-->
 
  
 
(19.0.1-61)
 
(19.0.1-61)
Line 43: Line 47:
 
[[Category:Version 6.1]]
 
[[Category:Version 6.1]]
 
[[Category:Editing a Project View]]
 
[[Category:Editing a Project View]]
[[Category:Event Links/Dependencies]]
+
[[Category:Task Links]]
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Editing]]
 
[[Category:Ribbon]]
 
[[Category:Ribbon]]

Revision as of 16:27, 17 November 2017

About Links and Linking Tasks/Milestones

Introduction

If you need to show dependencies in your project views, OnePager 6.1 provides a means for you to link one task or milestone shape with others using predecessor data from your source plan.

1) Using OnePager Pro/Express version 6.1 you can now:

(1) Import Task Link data from your source plans.
(2) Manipulate Task Link representations in your project views.
(3) Use controls to define Task Link show/hide filtering rules.
(4) And use enhanced editing techniques to alter Task Link colors, arrow heads, line styles, and other properties.

2) As with previous versions of OnePager you can manually create and edit Task Links.

3) Finally, you are provided with tools so you can manage all Task Links in your project view and all its various snapshots.

4) Please use the Wiki article links below which provide detailed information on the new data-driven Task Links feature and the enhancements made to manually created Task Links in OnePager 6.1. The top row's two articles in the table of links below provide you with an overview to the new Data-Driven Task Link feature and the enhancements made to the existing Manual Task Link capabilities.

Using OnePager Pro 6.1 Task Links – An Overview 19.1.1-61 Using OnePager Express 6.1 Task Links – An Overview 19.2.1-61
Data-Driven Task Links for OnePager Pro 6.1 P61-19.1.2-61 Data-Driven Task Links for OnePager Express 6.1 P61-19.2.2-61
Using Task Link Filtering Rules with OnePager Pro 6.1 19.1.3-61 Using Task Link Filtering Rules with OnePager Express 6.1 19.2.3-61
Project-View Properties Form Editing of Task Links for OnePager Pro 6.1 19.1.4-61 Project-View Properties Form Editing Task Links for OnePager Express 6.1 19.2.4-61
Manual Editing of Task Links for OnePager Pro 6.1 19.1.5-61 Manual Editing of Task Links for OnePager Express 6.1 19.2.5-61
Notes on Data-Driven Task Links for OnePager Pro 6.1 19.1.6-61 Notes on Data-Driven Task Links for OnePager Express 6.1 19.2.6-61

(19.0.1-61)