(Created page with "==Overview== One of OnePager's strengths is its ability to create compact visual representations of multiple projects. These can be several projects that belong to one progra...")
 
(Overview)
Line 1: Line 1:
 
==Overview==
 
==Overview==
  
One of OnePager's strengths is its ability to create compact visual representations of multiple projects. These can be several projects that belong to one program, or they can be several projects and programs in an organization’s portfolio.
+
1) One of OnePager's strengths is its ability to create compact visual representations of multiple projects.  
  
Microsoft Project supports the management of multiple projects through the creation of a Microsoft Project Master Project or Integrated Master Schedule ('''IMS''').  
+
2) These can be several projects that belong to one program or they can be several projects and programs in an organization’s portfolio.
  
1) To create an '''IMS''' of related projects, open Microsoft Project and go to the '''Insert Projects''' button to insert sub-projects into a '''Master Project'''. Save the '''Master Project''' with an appropriate '''Master Project file name''' for future reference.
+
3) Microsoft Project supports the management of '''multiple projects''' through the creation of a Microsoft Project '''Master Project''' or '''Integrated Master Schedule''' ('''IMS''').  
  
2) Creating a One Pager multi-project chart is a matter of opening the Microsoft Project '''Master Project''' and using a different OnePager Pro '''Template''' to import data and create a new chart.  
+
4) To create an '''IMS''' of related projects, open Microsoft Project and go to the '''Insert Projects''' button to insert sub-projects into a '''Master Project'''. '''Save''' the '''Master Project''' with an appropriate '''Master Project file name''' for future reference.
  
:a) To change '''Templates''' click the '''Template...''' button on the Microsoft Project tool bar to bring up the '''Template Properties''' form shown below.  Then, click the '''File''' button as shown:
+
5) Creating a One Pager '''multi-project''' chart is a matter of opening the Microsoft Project '''Master Project''' and using a different OnePager Pro '''Template''' to '''import''' data and '''create''' a new chart.
 +
 
 +
:a) To change '''Templates''' click the '''Template...''' button on the Microsoft Project tool bar to access the '''Template Properties''' form.   
 +
 
 +
:b) Then, click the '''File''' button as shown below:
 +
 
 +
<center[[File:P70-8_1_1-70-(1)-08272019.png]]</center>
 +
<center>P70-8_1_1-70-(1)-08272019.png</center>
  
 
<center>[[File:P60-8_1_1-60-(1)-02082017.png]]</center>
 
<center>[[File:P60-8_1_1-60-(1)-02082017.png]]</center>
 
<center>P60-8_1_1-60-(1)-02082017.png</center>
 
<center>P60-8_1_1-60-(1)-02082017.png</center>
  
:b) Clicking the '''BROWSE''' option takes you to where OnePager stores your '''Templates''' as shown below:
+
:c) Clicking the '''BROWSE''' option takes you to where OnePager stores your '''Templates''' as shown below:
 +
 
 +
<center[[File:P70-8_1_1-70-(2)-08272019.png]]</center>
 +
<center>P70-8_1_1-70-(2)-08272019.png</center>
  
 
<center>[[File:P60-8_1_1-60-(2)-10072016.png]]</center>
 
<center>[[File:P60-8_1_1-60-(2)-10072016.png]]</center>
  
3) The default OnePager Pro out-of-the-box '''Template''' is '''Single Project Gantt View – Detailed'''. Instead, choose the '''Template''' named '''Multi-Project Gantt Chart - Detailed''' as shown above.  
+
6) The default OnePager Pro out-of-the-box '''Template''' is '''Single Project Gantt View – Detailed'''.  
  
:a) OnePager assumes that when the '''Multi-Project Gantt Chart - Detailed Template''' is in use, that you are using a Microsoft Project '''Master Project''' as the '''source plan'''.
+
:a) Instead, choose the '''Template''' named '''Multi-Project Gantt Chart - Detailed''' as shown above.  
  
:b) Making this choice changes the '''Template Properties''' form to have the multi-project '''Template''' name in the title bar, as is shown below:
+
:b) OnePager assumes that when the '''Multi-Project Gantt Chart - Detailed Template''' is in use, that you are using a Microsoft Project '''Master Project''' as the '''source plan'''.
 +
 
 +
:c) Making this choice changes the '''Template Properties''' form to have the multi-project '''Template''' name in the title bar, as is shown below:
 +
 
 +
<center[[File:P70-8_1_1-70-(3)-08272019.png]]</center>
 +
<center>P70-8_1_1-70-(3)-08272019.png</center>
  
 
<center>[[File:P60-8_1_1-60-(3)-10072016.png]]</center>
 
<center>[[File:P60-8_1_1-60-(3)-10072016.png]]</center>
  
:c) You now have OnePager Pro ready to use the multi-project '''Template'''.
+
:d) You now have OnePager Pro ready to use the '''multi-project Template'''.
  
4) The actions required from this point are just like those described elsewhere (See:  [[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] 7.0.1-70) to create a new chart.
+
7) The actions required from this point are just like those described elsewhere (See:  [[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] 7.0.1-70) to create a new chart.
  
:a) Launch Microsoft Project with your multi-project '''source plan'''.
+
:a) Launch Microsoft Project with your '''multi-project source plan'''.
  
 
:b) Launch OnePager Pro and select the '''NEW''' button.
 
:b) Launch OnePager Pro and select the '''NEW''' button.
  
:c) OnePager uses the loaded Microsoft Project multi-project '''source plan''' under control of the '''Multi-Project Gantt Chart – Detailed Template''' to create your new chart as shown below:
+
:c) OnePager uses the loaded Microsoft Project '''multi-project source plan''' under control of the '''Multi-Project Gantt Chart – Detailed Template''' to create your '''new''' chart as shown below:
 +
 
 +
<center[[File:P70-8_1_1-70-(4)-08272019.png]]</center>
 +
<center>P70-8_1_1-70-(4)-08272019.png</center>
  
 
<center>[[File:P60-8_1_1-60-(4)-10072016.png]]</center>
 
<center>[[File:P60-8_1_1-60-(4)-10072016.png]]</center>
  
5) In the example above, the chart is organized with swimlanes representing various projects at Level 4. Rows are used to represent resources.  
+
8) In the example above, the chart is organized with swimlanes representing various projects at '''Level 4'''. Rows are used to represent '''Resource Names'''.  
  
6) We now can change the representation of some of the tasks from Gantt bars to milestone symbols by right-clicking them and clicking the '''As milestone at finish''' option as shown below:
+
9) We now can change the representation of some of the tasks from task bar shapes to milestone symbols by right-clicking them and clicking the '''As milestone at finish''' option as shown below:
 +
 
 +
<center[[File:P70-8_1_1-70-(5)-08272019.png]]</center>
 +
<center>P70-8_1_1-70-(5)-08272019.png</center>
  
 
<center>[[File:P60-8_1_1-60-(5)-10072016.png]]</center>
 
<center>[[File:P60-8_1_1-60-(5)-10072016.png]]</center>
  
7) The chart below was produced by representing the project level tasks as Gantt bars and the remaining tasks as milestones:
+
10) The chart below was produced by representing the project level tasks as task bar shapes and the remaining tasks as milestones:
 +
 
 +
<center[[File:P70-8_1_1-70-(6)-08272019.png]]</center>
 +
<center>P70-8_1_1-70-(6)-08272019.png</center>
  
 
<center>[[File:P60-8_1_1-60-(6)-10072016.png]]</center>
 
<center>[[File:P60-8_1_1-60-(6)-10072016.png]]</center>
  
8) It is also possible to represent the tasks below the project level as milestone symbols positioned at the start of the task period as shown below:
+
11) It is also possible to represent the tasks below the project level as milestone symbols positioned at the '''start of the task period''' as shown below:
 +
 
 +
<center[[File:P70-8_1_1-70-(7)-08272019.png]]</center>
 +
<center>P70-8_1_1-70-(7)-08272019.png</center>
  
 
<center>[[File:P60-8_1_1-60-(7)-10072016.png]]</center>
 
<center>[[File:P60-8_1_1-60-(7)-10072016.png]]</center>
  
9) These charts can now be copied and pasted into Microsoft PowerPoint for delivery to your audience.
+
12) These charts can now be '''copied''' into Microsoft PowerPoint for delivery to your audience.
  
 
(8.1.1-70)
 
(8.1.1-70)

Revision as of 21:26, 26 August 2019

Overview

1) One of OnePager's strengths is its ability to create compact visual representations of multiple projects.

2) These can be several projects that belong to one program or they can be several projects and programs in an organization’s portfolio.

3) Microsoft Project supports the management of multiple projects through the creation of a Microsoft Project Master Project or Integrated Master Schedule (IMS).

4) To create an IMS of related projects, open Microsoft Project and go to the Insert Projects button to insert sub-projects into a Master Project. Save the Master Project with an appropriate Master Project file name for future reference.

5) Creating a One Pager multi-project chart is a matter of opening the Microsoft Project Master Project and using a different OnePager Pro Template to import data and create a new chart.

a) To change Templates click the Template... button on the Microsoft Project tool bar to access the Template Properties form.
b) Then, click the File button as shown below:

<centerFile:P70-8 1 1-70-(1)-08272019.png</center>

P70-8_1_1-70-(1)-08272019.png
P60-8 1 1-60-(1)-02082017.png
P60-8_1_1-60-(1)-02082017.png
c) Clicking the BROWSE option takes you to where OnePager stores your Templates as shown below:

<centerFile:P70-8 1 1-70-(2)-08272019.png</center>

P70-8_1_1-70-(2)-08272019.png
P60-8 1 1-60-(2)-10072016.png

6) The default OnePager Pro out-of-the-box Template is Single Project Gantt View – Detailed.

a) Instead, choose the Template named Multi-Project Gantt Chart - Detailed as shown above.
b) OnePager assumes that when the Multi-Project Gantt Chart - Detailed Template is in use, that you are using a Microsoft Project Master Project as the source plan.
c) Making this choice changes the Template Properties form to have the multi-project Template name in the title bar, as is shown below:

<centerFile:P70-8 1 1-70-(3)-08272019.png</center>

P70-8_1_1-70-(3)-08272019.png
P60-8 1 1-60-(3)-10072016.png
d) You now have OnePager Pro ready to use the multi-project Template.

7) The actions required from this point are just like those described elsewhere (See: Basic Workflows (Portal) 7.0.1-70) to create a new chart.

a) Launch Microsoft Project with your multi-project source plan.
b) Launch OnePager Pro and select the NEW button.
c) OnePager uses the loaded Microsoft Project multi-project source plan under control of the Multi-Project Gantt Chart – Detailed Template to create your new chart as shown below:

<centerFile:P70-8 1 1-70-(4)-08272019.png</center>

P70-8_1_1-70-(4)-08272019.png
P60-8 1 1-60-(4)-10072016.png

8) In the example above, the chart is organized with swimlanes representing various projects at Level 4. Rows are used to represent Resource Names.

9) We now can change the representation of some of the tasks from task bar shapes to milestone symbols by right-clicking them and clicking the As milestone at finish option as shown below:

<centerFile:P70-8 1 1-70-(5)-08272019.png</center>

P70-8_1_1-70-(5)-08272019.png
P60-8 1 1-60-(5)-10072016.png

10) The chart below was produced by representing the project level tasks as task bar shapes and the remaining tasks as milestones:

<centerFile:P70-8 1 1-70-(6)-08272019.png</center>

P70-8_1_1-70-(6)-08272019.png
P60-8 1 1-60-(6)-10072016.png

11) It is also possible to represent the tasks below the project level as milestone symbols positioned at the start of the task period as shown below:

<centerFile:P70-8 1 1-70-(7)-08272019.png</center>

P70-8_1_1-70-(7)-08272019.png
P60-8 1 1-60-(7)-10072016.png

12) These charts can now be copied into Microsoft PowerPoint for delivery to your audience.

(8.1.1-70)