Difference between revisions of "Making Multi-Project Charts from MS Project Integrated Master Schedules for Version 7.0"

From OnePager Documentation
Jump to: navigation, search
(Creating the Multi-Project Chart)
(Creating the Multi-Project Chart)
Line 50: Line 50:
 
8) The actions required to create a new chart from this point are as described elsewhere depending on whether you are creating a '''NEW''' chart, '''UPDATING''' an existing chart, or '''OPENING''' an existing chart.  Please see the articles in this section of the Wiki for details on '''workflow options''':  [[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] 7.0.1-70
 
8) The actions required to create a new chart from this point are as described elsewhere depending on whether you are creating a '''NEW''' chart, '''UPDATING''' an existing chart, or '''OPENING''' an existing chart.  Please see the articles in this section of the Wiki for details on '''workflow options''':  [[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] 7.0.1-70
  
8) Creating a '''NEW multi-project''' chart follows these steps
+
9) Creating a '''NEW multi-project''' chart follows these steps
  
 
:a) Launch Microsoft Project with your '''multi-project source plan'''.
 
:a) Launch Microsoft Project with your '''multi-project source plan'''.
Line 61: Line 61:
 
<center>P70-8_1_1-70-(4)-08272019.png</center>
 
<center>P70-8_1_1-70-(4)-08272019.png</center>
  
9) In the example above, the chart is organized with swimlanes representing various projects at '''Level 4'''. Rows are used to represent '''Resource Names'''.  '''Colors''' are assigned randomly in a '''round -robin'' fashion based on '''Resource Names''' as well.
+
10) In the example above, the chart is organized with swimlanes representing various projects at '''Level 4'''. Rows are used to represent '''Resource Names'''.  '''Colors''' are assigned randomly in a '''round -robin'' fashion based on '''Resource Names''' as well.
  
 
===Changing Task Bar Shape Representation===
 
===Changing Task Bar Shape Representation===

Revision as of 14:21, 27 August 2019

Overview

1) One of OnePager's strength is its ability to create compact visual representations of multiple projects.

2) These can be several projects that belong to one program or they can be several projects and programs in an organization’s portfolio.

3) Microsoft Project supports the management of multiple projects through the creation of a Microsoft Project Master Project or Integrated Master Schedule (IMS).

Creating an IMS of Related Projects

4) To create an IMS from related projects, open Microsoft Project and go to the Insert Projects button to insert sub-projects into a Master Project. Save the Master Project with an appropriate Master Project file name for future reference.

5) These reference links to our Blog are useful:

a) How to Use Master MS Project Files and OnePager to Create Visuals of Separate MS Project Files
b) Making Multi-Project Graphs from Separate Microsoft project Plans

The OnePager Multi-Project Template

6) Creating a One Pager multi-project chart is a matter of opening the Microsoft Project Master Project and using a different OnePager Pro Template to import data and create a new chart.

a) To change Templates, click the Template... button on the Microsoft Project Add-in tool bar to access the Template Properties form.
b) Then, click the File button as shown below:
File:P70-8 1 1-70-(1)-08272019.png
P70-8_1_1-70-(1)-08272019.png
c) Clicking the BROWSE option takes you to where OnePager stores your Templates as shown below:
File:P70-8 1 1-70-(2)-08272019.png
P70-8_1_1-70-(2)-08272019.png

7) The default OnePager Pro out-of-the-box Template is Single Project Gantt View – Detailed.

a) Instead, choose the Template named Multi-Project Gantt Chart - Detailed as shown above.
b) OnePager assumes that when the Multi-Project Gantt Chart - Detailed Template is in use, that you are using a Microsoft Project Master Project as the source plan.
c) Making this choice changes the Template Properties form to have the multi-project Template name in the title bar, as is shown below:
File:P70-8 1 1-70-(3)-08272019.png
P70-8_1_1-70-(3)-08272019.png
d) You now have OnePager Pro ready to use the multi-project Template.

Creating the Multi-Project Chart

8) The actions required to create a new chart from this point are as described elsewhere depending on whether you are creating a NEW chart, UPDATING an existing chart, or OPENING an existing chart. Please see the articles in this section of the Wiki for details on workflow options: Basic Workflows (Portal) 7.0.1-70

9) Creating a NEW multi-project chart follows these steps

a) Launch Microsoft Project with your multi-project source plan.
b) Launch OnePager Pro and select the NEW button.
c) OnePager uses the loaded Microsoft Project multi-project source plan under control of the Multi-Project Gantt Chart – Detailed Template to create your new chart as shown below:
File:P70-8 1 1-70-(4)-08272019.png
P70-8_1_1-70-(4)-08272019.png

10) In the example above, the chart is organized with swimlanes representing various projects at Level 4'. Rows are used to represent Resource Names. Colors are assigned randomly in a round -robin fashion based on Resource Names as well.

Changing Task Bar Shape Representation

9) We now can change the representation of some of the tasks from task bar shapes to milestone symbols by right-clicking them and clicking the As milestone at finish option as shown below:

File:P70-8 1 1-70-(5)-08272019.png
P70-8_1_1-70-(5)-08272019.png

10) The chart below was produced by representing the project level tasks as task bar shapes and the remaining tasks as milestones:

File:P70-8 1 1-70-(6)-08272019.png
P70-8_1_1-70-(6)-08272019.png
P60-8 1 1-60-(6)-10072016.png

11) It is also possible to represent the tasks below the project level as milestone symbols positioned at the start of the task period as shown below:

File:P70-8 1 1-70-(7)-08272019.png
P70-8_1_1-70-(7)-08272019.png
P60-8 1 1-60-(7)-10072016.png

12) These charts can now be copied into Microsoft PowerPoint for delivery to your audience.

Related Links

How to Use Master MS Project Files and OnePager to Create Visuals of Separate MS Project Files

Making Multi-Project Graphs from Separate Microsoft project Plans

Creating a NEW Chart via Pull Operation - OnePager Pro 7.13.1-70

REPLACING a Snapshot via Pull Operation - OnePager Pro 7.14.1-70

ADDING a Snapshot via Pull Operation - OnePager Pro 7.15.1-70

Creating a NEW Chart via Pull Operation - OnePager Express 7.13.2-70

REPLACING a Snapshot via Push Update - OnePager Express Desktop 7.14.2-70

ADDING a Snapshot via Pull Operation - OnePager Express 7.15.2-70

(8.1.1-70)