==Overview==
 
==Overview==
  
1) In the article at [[Making Multi-Project Charts from MS Project Integrated Master Schedules for Version 7.0 | Making Multi-Project Charts from MS Project Integrated Master Schedules]] 8.1.1-61 the Microsoft Project '''Integrated Master Schedule''' feature is used to construct a '''multi-project source plan''' from which OnePager Pro ('''OPP''') created a '''multi-project''' chart.
+
1) OnePager Pro is capable of '''importing''' separate '''source plans''' to create a '''multi-project''' chart from individual '''source plans'''.
  
2) OnePager Pro is capable of '''importing''' separate '''source plans''' to also create a '''multi-project''' chart from these individual '''source plans'''.
+
2) In the article at: [[Making Multi-Project Charts from MS Project Integrated Master Schedules for Version 7.0 | Making Multi-Project Charts from MS Project Integrated Master Schedules]], <!--8.1.1-70--> the Microsoft Project '''Integrated Master Schedule''' feature is used to construct a '''multi-project source plan''' from which OnePager Pro ('''OPP''') created a '''multi-project''' chart.
  
3) Suppose you want to build a ''''multi-project''' chart without first creating a Microsoft Project '''Integrated Master Schedule''' ('''IMS''').   
+
3) Suppose you want to build a '''multi-project''' chart without first creating a Microsoft Project '''Integrated Master Schedule''' ('''IMS''').   
  
 
4) To illustrate an approach to do this, we’ll use the OnePager Pro ('''OPP''') '''Add-in''' application following the steps described in the remainder of this article.
 
4) To illustrate an approach to do this, we’ll use the OnePager Pro ('''OPP''') '''Add-in''' application following the steps described in the remainder of this article.
Line 13: Line 13:
 
===Settings for Microsoft Project===
 
===Settings for Microsoft Project===
  
1) OnePager Pro ('''OPP''') always uses the '''labels''' of the '''project-summary task''' to identify each project in a '''multi-project''' chart.  
+
1) OnePager Pro ('''OPP''') uses the '''labels''' of the '''project-summary task''' to identify each project in a '''multi-project''' chart.  
  
:a) OnePager does not use the Microsoft Project '''source plan''' file name to identify projects.  
+
2) OnePager does not use the Microsoft Project '''source plan file name''' to identify projects.  
  
:b) If you want to display the '''project summary task''' at the top of a Microsoft Project file, go to the '''File''' tab on Microsoft Project’s tool bar.  
+
3) If you want to display the '''project summary task''' at the top of a Microsoft Project file, go to the '''File''' tab on Microsoft Project’s ribbon tool bar.  
  
:c)Then navigate to '''Options''' tab and once there, to the '''Advanced''' tab and check the checkbox that is shown below:
+
4)Then navigate to '''Options''' tab and once there, to the '''Advanced''' tab and check the checkbox '''ON''' that is shown below:
  
 
<center>[[File:P70-8_2_1-70-(0)-08282019.png]]</center>
 
<center>[[File:P70-8_2_1-70-(0)-08282019.png]]</center>
<center>P70-8_2_1-70-(0)-08282019.png</center>
+
<!--<center>P70-8_2_1-70-(0)-08282019.png</center>-->
  
2) When you are using the '''Pull''' operation workflow to create a '''multi-project''' chart, the setting above on the Microsoft Project’s '''Project Options''' page must be set '''before''' the first designated Microsoft Project '''source plan''' is '''pulled in''' and must stay set for all subsequent '''source plan Pull''' operations.  
+
5) When you are using the '''Pull''' operation workflow to create a '''multi-project''' chart, the setting above on the Microsoft Project’s '''Project Options''' page must be set '''before''' the first designated Microsoft Project '''source plan''' is '''pulled in''' and must stay set for all subsequent '''source plan Pull''' operations.  
  
3) This is because, although Microsoft Project as an application does not appear on your screen anytime during the '''Pull''' operation, nevertheless, it is launched by '''OPP''' and operates on the designated files before '''OPP''' processes them.
+
6) This is because, although Microsoft Project, as an application, does not appear on your screen anytime during the '''Pull''' operation, nevertheless, it is launched by '''OPP''' and operates on the designated files before '''OPP''' processes them.
  
4) The setting for Microsoft Project discussed above does not need to be switched '''On''' when '''Push''' operational workflows are being used.
+
7) The setting for Microsoft Project discussed above does not need to be switched '''ON''' when '''Push''' operational workflows are being used.
  
 
===Predatory Steps===
 
===Predatory Steps===
  
5) Before proceeding with the construction of a OnePager Pro '''multi-project''' chart, the first step is to assure that the '''Template''' used is for '''Single Project Gantt Chart - Detailed'''.  This is because OnePager Pro is going to '''import''' two or more '''source plans''' and use them to construct the desired chart.
+
8) Before proceeding with the construction of a OnePager Pro '''multi-project''' chart, the first step is to assure that the '''Template Properties''' form used is for '''Single Project Gantt Chart - Detailed'''.   
  
6) Further, since each Microsoft Project '''source plan''' contains its own '''UniqueID''' sequence and since these '''UniqueID''' values may be duplicates from one '''source plan''' to the next, we need to make OnePager Pro aware that it must '''safely combine tasks from different source plans'''.
+
9) This is because OnePager Pro is going to '''import''' two or more '''source plans''' and use them to construct the desired chart.
  
7) These steps are described below:
+
10) Further, since each Microsoft Project '''source plan''' contains its own '''UniqueID''' sequence and since these '''UniqueID''' values may be duplicates from one '''source plan''' to the next, we need to make OnePager Pro aware that it must '''safely combine tasks from different source plans'''.
  
===Modifying the OnePager Pro Template for Creating Multi-Project Charts===
+
11) These steps are described below:
  
4) Launch Microsoft Project and navigate to the '''Add-ins''' tab on the Microsoft Project ribbon tabs.
+
===Modifying the OnePager Pro Template Properties Form for Creating Multi-Project Charts===
  
5) Click the '''Template''' button which accesses the current '''Template'''.
+
12) Launch Microsoft Project and navigate to the '''Add-ins''' tab on the Microsoft Project ribbon tool bar.
  
6) Assure that the '''Template''' type is '''Single Project Gantt Chart - Detailed''' or a '''Template''' of your own that is '''equivalent''' as used in this example shown below:
+
13) Click the '''Template''' button which accesses the current '''Template Properties''' form.
  
<center>[[File:P70-8_2_1-70-(1)-08282019.png]]</center>
+
14) Assure that the '''Template Properties''' form type is '''Single Project Gantt Chart - Detailed''' or a '''Template Properties''' form of your own that is '''equivalent''' as used in this example shown below:
<center>P70-8_2_1-70-(1)-08282019.png</center>
+
  
7) At the '''Advanced''' tab, check the '''Safely combine tasks from different files''' checkbox '''On''' as shown above.
+
<center>[[File:P70-8_2_1-(1)-05132020.png]]</center>
 +
<!--<center>P70-8_2_1-(1)-05132020.png</center>-->
  
:a) This setting allows you to '''import multiple''' standalone Microsoft Project '''source plans'''.  
+
15) At the '''Advanced''' tab, check the '''Safely combine tasks from different files''' checkbox '''ON''' as shown above.
  
:b) If you do not check this checkbox, OnePager may confuse tasks from one Microsoft Project '''source plan''' with tasks from another when the tasks have the same '''UniqueID'''.
+
16) This setting allows you to '''import multiple''' standalone Microsoft Project '''source plans'''. 
 +
 
 +
17) If you do not check this checkbox '''ON''', OnePager may confuse tasks from one Microsoft Project '''source plan''' with tasks from another when the tasks have the same '''UniqueID'''.
  
 
===Making Adjustments to Rows and Swimlanes===
 
===Making Adjustments to Rows and Swimlanes===
  
8) With the '''Template''' form used previously, go to the '''Template Properties''' form’s '''Rows/Swimlanes''' tab shown below.  
+
18) With the '''Template Properties''' form used previously, go to the '''Template Properties''' form’s '''Rows/Swimlanes''' tab shown below.  
  
:a) Ensure that you are '''grouping''' and '''labeling''' swimlanes by the '''Project Name'''.  
+
19) Ensure that you are '''grouping''' and '''labeling''' the '''swimlane level''' by the '''Project Name'''.  
  
:b) This step is optional, it is strongly recommended.
+
20) This step is optional, it is strongly recommended.
  
<center>[[File:P70-8_2_1-70-(2)-08282019.png]]</center>
+
<center>[[File:P70-8_2_1-(2)-05132020.png]]</center>
<center>P70-8_2_1-70-(2)-08282019.png</center>
+
<!--<center>P70-8_2_1-(2)-05132020.png</center>-->
  
9) Now click the '''Save and use''' or '''Use''' button to make this '''Template''' the current '''Template''' to support creating a '''multi-project''' chart.
+
21) Now click the '''Save and use''' or '''Use''' button to make this '''Template Properties''' form the current '''Template Properties''' form to support creating a '''multi-project''' chart.
  
10) Once you’ve '''saved''' the '''Template Properties''' form, the next series of steps below involve accessing the separate Microsoft Project '''source plans''' that we intend to use for our '''multi-project''' chart.
+
22) Once you’ve '''saved''' the '''Template Properties''' form, the next series of steps below involve accessing the separate Microsoft Project '''source plans''' that we intend to use for our '''multi-project''' chart.
  
 
===Load the First Microsoft Project Source Plan===
 
===Load the First Microsoft Project Source Plan===
  
11) With Microsoft Project already launched, use the '''Files''' controls in Microsoft Project to load the first Microsoft Project '''source plan''' as shown here:
+
23) With Microsoft Project already launched, use the '''Files''' controls in Microsoft Project to load the first Microsoft Project '''source plan''' as shown here:
  
<center>[[File:P70-8_2_1-70-(3)-08282019.png]]</center>
+
<center>[[File:P70-8_2_1-(3)-05132020.png]]</center>
<center>P70-8_2_1-70-(3)-08282019.png</center>
+
<!--<center>P70-8_2_1-(3)-05132020.png</center>-->
  
12) When you click the '''Open''' button on the form above, Microsoft Project loads the '''source plan''' in the normal manner.
+
24) When you click the '''Open''' button on the form above, Microsoft Project loads the '''source plan''' in the normal manner.
  
13)  With the '''first source plan''' loaded, navigate to the Microsoft Project '''Add-ins''' tab and click the '''OnePager Pro''' button to launch OnePager and access the '''OnePager Start''' form.
+
25)  With the '''first source plan''' loaded, navigate to the Microsoft Project '''Add-ins''' tab and click the '''OnePager Pro''' button to launch OnePager and access the '''OnePager Start''' form.
  
14) Now click the '''NEW''' button on the '''OnePager Start''' form to access the OnePager choices ('''OPC''') form as shown here:   
+
26) Now click the '''NEW''' button on the '''OnePager Start''' form to access the OnePager choices ('''OPC''') form as shown here:   
  
 
<center>[[File:P70-8_2_1-70-(4)-08282019.png]]</center>
 
<center>[[File:P70-8_2_1-70-(4)-08282019.png]]</center>
<center>P70-8_2_1-70-(4)-08282019.png</center>
+
<!--<center>P70-8_2_1-70-(4)-08282019.png</center>-->
  
:a) In the illustration above, OnePager Pro already knows the name of the '''first source plan'''.
+
27) In the illustration above, OnePager Pro already knows the '''name''' of the '''first source plan'''.
  
:b) Complete the remainder of the fields in the '''OPC''' form such as the '''Title of New Chart''' and the '''Snapshot Date''' if applicable.
+
28) Complete the remainder of the fields in the '''OPC''' form such as the '''Title of New Chart''' and the '''Snapshot Date''' if applicable.
  
15) To add the remaining two (2) '''source plans''' used in this example it is necessary to create a '''source package''' assuring that all three '''source plans''' are included.
+
29) To add the remaining two (2) '''source plans''' used in this example, it is necessary to create a '''source package''' assuring that all three '''source plans''' are included.
  
16) To do this click on the '''Add/Remove''' button near the top of the '''OPC''' form.  This action accesses the '''Data source selection''' form where the '''first source plan''' is already present in the grid as shown below:
+
30) To do this click on the '''Add/Remove''' button near the top of the '''OPC''' form.   
 +
 
 +
31) This action accesses the '''Data source selection''' form where the '''first source plan''' is already present in the grid as shown below:
  
 
<center>[[File:P70-8_2_1-70-(5)-08282019.png]]</center>
 
<center>[[File:P70-8_2_1-70-(5)-08282019.png]]</center>
<center>P70-8_2_1-70-(5)-08282019.png</center>
+
<!--<center>P70-8_2_1-70-(5)-08282019.png</center>-->
  
 
===Add the Second Microsoft Project Source Plan to the Source Packet===
 
===Add the Second Microsoft Project Source Plan to the Source Packet===
  
17) Using the '''Data source selection''' form, click the '''Add''' button in the form which gives you the option to select a '''recently used source plan''' or to '''BROWSE...'''.
+
32) Using the '''Data source selection''' form, click the '''Add''' button in the form which gives you the option to select a '''recently used source plan''' or to '''BROWSE...'''.
  
:a) Select the '''BROWSE...''' option so that you can select the '''second source plan''' for the multi-project''' chart being created.
+
33) Select the '''BROWSE...''' option so that you can select the '''second source plan''' for the multi-project''' chart being created.
  
:b) Click on the desired '''second source plan''' as shown below and click the '''Open''' button on the form.  
+
34) Click on the desired '''second source plan''' as shown below and click the '''Open''' button on the form.  
  
<center>[[File:P70-8_2_1-70-(6)-08282019.png]]</center>
+
<center>[[File:P70-8_2_1-(6)-05132020.png]]</center>
<center>P70-8_2_1-70-(6)-08282019.png</center>
+
<!--<center>P70-8_2_1-(6)-05132020.png</center>-->
  
18) This action '''adds''' the '''second source plan''' to the '''source packet''' as shown below in the '''Data source selection''' form after the operation is complete.
+
35) This action '''adds''' the '''second source plan''' to the '''source packet''' as shown below in the '''Data source selection''' form after the operation is complete.
  
 
<center>[[File:P70-8_2_1-70-(7)-08282019.png]]</center>
 
<center>[[File:P70-8_2_1-70-(7)-08282019.png]]</center>
<center>P70-8_2_1-70-(7)-08282019.png</center>
+
<!--<center>P70-8_2_1-70-(7)-08282019.png</center>-->
  
 
===Add the Third Microsoft Project Source Plan to the Source Packet===
 
===Add the Third Microsoft Project Source Plan to the Source Packet===
  
20) Repeat this exact same process to '''add''' the '''third source plan''' to the '''source packet'''.
+
36) Repeat this exact same process to '''add''' the '''third source plan''' to the '''source packet'''.
  
21) At the completion of that step the '''Data source selection''' form looks like this:
+
37) At the completion of that step the '''Data source selection''' form looks like this:
  
 
<center>[[File:P70-8_2_1-70-(8)-08282019.png]]</center>
 
<center>[[File:P70-8_2_1-70-(8)-08282019.png]]</center>
<center>P70-8_2_1-70-(8)-08282019.png</center>
+
<!--<center>P70-8_2_1-70-(8)-08282019.png</center>-->
  
21) When the '''OK''' button on the '''Data source selection''' form is clicked, the '''OPC''' form is '''updated''' to show that three '''source plans''' are included in the '''source packet''' as shown below:
+
38) When the '''OK''' button on the '''Data source selection''' form is clicked, the '''OPC''' form is '''updated''' to show that three '''source plans''' are included in the '''source packet''' as shown below:
  
 
<center>[[File:P70-8_2_1-70-(9)-08282019.png]]</center>
 
<center>[[File:P70-8_2_1-70-(9)-08282019.png]]</center>
<center>P70-8_2_1-70-(9)-08282019.png</center>
+
<!--<center>P70-8_2_1-70-(9)-08282019.png</center>-->
  
==Create the Multi-Project Chart==
+
===Create the Multi-Project Chart===
  
1) Now, go ahead and click the '''Create the new chart''' button on the '''OPC''' form and the resulting chart will look like this:
+
39) Now, go ahead and click the '''Create the new chart''' button on the '''OPC''' form and the resulting chart looks like this:
  
 
<center>[[File:P70-8_2_1-70-(10)-08282019.png]]</center>
 
<center>[[File:P70-8_2_1-70-(10)-08282019.png]]</center>
<center>P70-8_2_1-70-(10)-08282019.png</center>
+
<!--<center>P70-8_2_1-70-(10)-08282019.png</center>-->
  
==Settings for Microsoft Project ==
+
==Updating Charts Created from Separate Microsoft Project Plans==
  
12) '''OPP''' always uses the label (name) of the project-summary task to identify each project in a multi-project situation.  
+
1) Eventually there is a need to '''update''' your '''multi-project''' chart by either '''adding''' a snapshot or '''replacing''' a snapshot with '''updated''' data.
  
:a) OnePager does not use the Microsoft Project '''source plan''' name to identify projects.  
+
2) To perform either the '''add''' or the '''replace''' snapshot operation, the processes described in the article at: [[REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 7.0 | REPLACING a Snapshot via Pull Operation - OnePager Pro]] <!--7.14.1-70-->
  
:b) If you want to display the project summary task (Task 0) at the top of a project file, go to the '''File''' tab on Microsoft Project’s tool bar. Then navigate to '''Options''' tab and once there, to the '''Advanced''' tab and check the checkbox that is shown below:
+
3) The key to '''updating multi-project''' charts is the proper management of the '''source packet'''
  
<center>[[File:P60-8_2_1-60-(9)-10072016.png]]</center>
+
4) Recall that the '''source packet''' contains the file or files that are to be used to either create or '''update''' a chart.  
  
13) Since we are using the '''pull''' operation workflow to create this multi-project chart, the setting above on the Microsoft Project’s '''Project Options''' page must be set '''before''' the first designated Microsoft Project '''source plan''' is pulled in and must stay set for all subsequent '''source plan pull''' operations. This is because, although Microsoft Project as an application will not appear on your screen anytime during the '''pull''' operation, nevertheless, it will be launched by '''OPP''' and will operate on the designated files before '''OPP''' processes them.
+
5) They are stored as '''file names''' and '''path names''' in the chart’s '''.TAM''' file and can be accessed from the OnePager '''Data''' ribbon tool bar tab’s '''Selected file(s)''' button as shown below:
  
==Updating Charts Created from Separate Microsoft Project Plans==
+
<center>[[File:P70-8_2_1-70-(11)-08282019.png]]</center>
 +
<!--<center>P70-8_2_1-70-(11)-08282019.png</center>-->
  
14) Eventually you will want to update your multi-project chart by either adding a snapshot or replacing a snapshot with updated data.  To perform either the add or the replace snapshot, the processes described in the '''Related Links''' section below can be used.
+
6) Validating the contents of the '''source packet''' and assuring that these are the Microsoft Project '''source plans''' to '''update''' is an essential step before proceeding to perform a '''multi-project'''chart '''update'''.
  
15) The key to updating multi-project charts is the proper management of the '''source packet'''.  Recall that the '''source packet''' contains the file or files that are to be used to either create or update a chart.  They are stored as file names and path names in the chart’s '''.TAM''' file and can be accessed from the '''Data''' tab’s '''Selected file(s)''' button on the ribbon as shown below:
+
==Related Links==
  
<center>[[File:P60-8_2_1-60-(10)-10072016.png]]</center>
+
[[Creating a NEW Chart via Pull Operation - OnePager Pro for Version 7.0 | Creating a NEW Chart via Pull Operation - OnePager Pro]] <!--7.13.1-70-->
 
+
16) Validating the contents of the '''source packet''' and assuring that these are the Microsoft Project '''source plans''' that were updated is an essential step before proceeding to perform a chart update.
+
 
+
==Related Links==
+
  
[[Creating a NEW Chart via Pull Operation - OnePager Pro for Version 7.0 | Creating a NEW Chart via Pull Operation - OnePager Pro]] 7.13.1-70
+
[[REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 7.0 | REPLACING a Snapshot via Pull Operation - OnePager Pro]] <!--7.14.1-70-->
  
[[REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 7.0 | REPLACING a Snapshot via Pull Operation - OnePager Pro]] 7.14.1-70
+
[[ADDING a Snapshot via Pull Operation - OnePager Pro for Version 7.0 | ADDING a Snapshot via Pull Operation - OnePager Pro]] <!--7.15.1-70-->
  
[[ADDING a Snapshot via Pull Operation - OnePager Pro for Version 7.0 | ADDING a Snapshot via Pull Operation - OnePager Pro]] 7.15.1-70
+
[[Making Multi-Project Charts from MS Project Integrated Master Schedules for Version 7.0 | Making Multi-Project Charts from MS Project Integrated Master Schedules]] <!--8.1.1-70-->
  
 
(8.2.1-70)
 
(8.2.1-70)

Latest revision as of 15:12, 12 January 2021

Overview

1) OnePager Pro is capable of importing separate source plans to create a multi-project chart from individual source plans.

2) In the article at: Making Multi-Project Charts from MS Project Integrated Master Schedules, the Microsoft Project Integrated Master Schedule feature is used to construct a multi-project source plan from which OnePager Pro (OPP) created a multi-project chart.

3) Suppose you want to build a multi-project chart without first creating a Microsoft Project Integrated Master Schedule (IMS).

4) To illustrate an approach to do this, we’ll use the OnePager Pro (OPP) Add-in application following the steps described in the remainder of this article.

Setting Up Steps

Settings for Microsoft Project

1) OnePager Pro (OPP) uses the labels of the project-summary task to identify each project in a multi-project chart.

2) OnePager does not use the Microsoft Project source plan file name to identify projects.

3) If you want to display the project summary task at the top of a Microsoft Project file, go to the File tab on Microsoft Project’s ribbon tool bar.

4)Then navigate to Options tab and once there, to the Advanced tab and check the checkbox ON that is shown below:

P70-8 2 1-70-(0)-08282019.png

5) When you are using the Pull operation workflow to create a multi-project chart, the setting above on the Microsoft Project’s Project Options page must be set before the first designated Microsoft Project source plan is pulled in and must stay set for all subsequent source plan Pull operations.

6) This is because, although Microsoft Project, as an application, does not appear on your screen anytime during the Pull operation, nevertheless, it is launched by OPP and operates on the designated files before OPP processes them.

7) The setting for Microsoft Project discussed above does not need to be switched ON when Push operational workflows are being used.

Predatory Steps

8) Before proceeding with the construction of a OnePager Pro multi-project chart, the first step is to assure that the Template Properties form used is for Single Project Gantt Chart - Detailed.

9) This is because OnePager Pro is going to import two or more source plans and use them to construct the desired chart.

10) Further, since each Microsoft Project source plan contains its own UniqueID sequence and since these UniqueID values may be duplicates from one source plan to the next, we need to make OnePager Pro aware that it must safely combine tasks from different source plans.

11) These steps are described below:

Modifying the OnePager Pro Template Properties Form for Creating Multi-Project Charts

12) Launch Microsoft Project and navigate to the Add-ins tab on the Microsoft Project ribbon tool bar.

13) Click the Template button which accesses the current Template Properties form.

14) Assure that the Template Properties form type is Single Project Gantt Chart - Detailed or a Template Properties form of your own that is equivalent as used in this example shown below:

P70-8 2 1-(1)-05132020.png

15) At the Advanced tab, check the Safely combine tasks from different files checkbox ON as shown above.

16) This setting allows you to import multiple standalone Microsoft Project source plans.

17) If you do not check this checkbox ON, OnePager may confuse tasks from one Microsoft Project source plan with tasks from another when the tasks have the same UniqueID.

Making Adjustments to Rows and Swimlanes

18) With the Template Properties form used previously, go to the Template Properties form’s Rows/Swimlanes tab shown below.

19) Ensure that you are grouping and labeling the swimlane level by the Project Name.

20) This step is optional, it is strongly recommended.

P70-8 2 1-(2)-05132020.png

21) Now click the Save and use or Use button to make this Template Properties form the current Template Properties form to support creating a multi-project chart.

22) Once you’ve saved the Template Properties form, the next series of steps below involve accessing the separate Microsoft Project source plans that we intend to use for our multi-project chart.

Load the First Microsoft Project Source Plan

23) With Microsoft Project already launched, use the Files controls in Microsoft Project to load the first Microsoft Project source plan as shown here:

P70-8 2 1-(3)-05132020.png

24) When you click the Open button on the form above, Microsoft Project loads the source plan in the normal manner.

25) With the first source plan loaded, navigate to the Microsoft Project Add-ins tab and click the OnePager Pro button to launch OnePager and access the OnePager Start form.

26) Now click the NEW button on the OnePager Start form to access the OnePager choices (OPC) form as shown here:

P70-8 2 1-70-(4)-08282019.png

27) In the illustration above, OnePager Pro already knows the name of the first source plan.

28) Complete the remainder of the fields in the OPC form such as the Title of New Chart and the Snapshot Date if applicable.

29) To add the remaining two (2) source plans used in this example, it is necessary to create a source package assuring that all three source plans are included.

30) To do this click on the Add/Remove button near the top of the OPC form.

31) This action accesses the Data source selection form where the first source plan is already present in the grid as shown below:

P70-8 2 1-70-(5)-08282019.png

Add the Second Microsoft Project Source Plan to the Source Packet

32) Using the Data source selection form, click the Add button in the form which gives you the option to select a recently used source plan or to BROWSE....

33) Select the BROWSE... option so that you can select the second source plan for the multi-project chart being created.

34) Click on the desired second source plan as shown below and click the Open button on the form.

P70-8 2 1-(6)-05132020.png

35) This action adds the second source plan to the source packet as shown below in the Data source selection form after the operation is complete.

P70-8 2 1-70-(7)-08282019.png

Add the Third Microsoft Project Source Plan to the Source Packet

36) Repeat this exact same process to add the third source plan to the source packet.

37) At the completion of that step the Data source selection form looks like this:

P70-8 2 1-70-(8)-08282019.png

38) When the OK button on the Data source selection form is clicked, the OPC form is updated to show that three source plans are included in the source packet as shown below:

P70-8 2 1-70-(9)-08282019.png

Create the Multi-Project Chart

39) Now, go ahead and click the Create the new chart button on the OPC form and the resulting chart looks like this:

P70-8 2 1-70-(10)-08282019.png

Updating Charts Created from Separate Microsoft Project Plans

1) Eventually there is a need to update your multi-project chart by either adding a snapshot or replacing a snapshot with updated data.

2) To perform either the add or the replace snapshot operation, the processes described in the article at: REPLACING a Snapshot via Pull Operation - OnePager Pro

3) The key to updating multi-project charts is the proper management of the source packet.

4) Recall that the source packet contains the file or files that are to be used to either create or update a chart.

5) They are stored as file names and path names in the chart’s .TAM file and can be accessed from the OnePager Data ribbon tool bar tab’s Selected file(s) button as shown below:

P70-8 2 1-70-(11)-08282019.png

6) Validating the contents of the source packet and assuring that these are the Microsoft Project source plans to update is an essential step before proceeding to perform a multi-projectchart update.

Related Links

Creating a NEW Chart via Pull Operation - OnePager Pro

REPLACING a Snapshot via Pull Operation - OnePager Pro

ADDING a Snapshot via Pull Operation - OnePager Pro

Making Multi-Project Charts from MS Project Integrated Master Schedules

(8.2.1-70)