(Created page with "==Overview== Suppose you need to build a multi-project project view without first creating a Microsoft Project Integrated Master Schedule ('''IMS'''). To illustrate an appro...")
 
 
Line 1: Line 1:
 
==Overview==
 
==Overview==
  
Suppose you need to build a multi-project project view without first creating a Microsoft Project Integrated Master Schedule ('''IMS''').  To illustrate an approach to do this, we’ll use the OnePager Pro ('''OPP''') '''desktop''' application.   
+
Suppose you need to build a multi-project chart without first creating a Microsoft Project Integrated Master Schedule ('''IMS''').  To illustrate an approach to do this, we’ll use the OnePager Pro ('''OPP''') '''desktop''' application.  Just follow the steps listed below:
 
+
Just follow the steps listed below:
+
  
 
==Setting up the Template for a Multi-Project Graph==
 
==Setting up the Template for a Multi-Project Graph==
  
1) Launch '''OPP''' from the '''desktop''' icon and navigate to the '''File''' tab on the ribbon.
+
Launch '''OPP''' from the '''desktop''' icon and navigate to the '''File''' tab on the ribbon. Then, click on the '''Options''' button on the left margin.  On the '''Options''' form, go to the '''Template''' button on the right side and click it.  This action will bring up the '''Template Properties''' form.  Finally, navigate to the '''Advanced''' tab on the '''Template Properties''' form as shown below:
 
+
2) Then, click on the '''Options''' button on the left margin.  On the '''Options''' form, go to the '''Template''' button on the right side and click it.  This action will bring up the '''Template Properties''' form.  Finally, navigate to the '''Advanced''' tab on the '''Template Properties''' form as shown below:
+
  
 
<center>[[File:P60-8_2_1-60-(1)-02082017.png]]</center>
 
<center>[[File:P60-8_2_1-60-(1)-02082017.png]]</center>
 
<center>P60-8_2_1-60-(1)-02082017.png</center>
 
<center>P60-8_2_1-60-(1)-02082017.png</center>
  
3) At the '''Advanced''' tab, check the '''Safely combine tasks from different files''' checkbox.
+
At the '''Advanced''' tab, check the '''Safely combine tasks from different files''' checkbox.   This setting allows you to import multiple standalone Microsoft Project '''source plans'''.  If you do not check this checkbox, OnePager may confuse tasks from one Microsoft Project '''source plan''' with tasks from another when the tasks have the same '''UniqueID''' in Microsoft Project Professional.
 
+
:a) This setting allows you to import multiple standalone Microsoft Project '''source plans'''.   
+
 
+
:b) If you do not check this checkbox, OnePager may confuse tasks from one Microsoft Project '''source plan''' with tasks from another when the tasks have the same '''UniqueID''' in Microsoft Project Professional.
+
  
 
<center>[[File:P60-8_2_1-60-(2)-02082017.png]]</center>
 
<center>[[File:P60-8_2_1-60-(2)-02082017.png]]</center>
Line 25: Line 17:
 
==Adjustments to Rows and Swimlanes==
 
==Adjustments to Rows and Swimlanes==
  
4) Go to the '''Template Properties''' form’s '''Rows/Swimlanes''' tab shown below. Ensure that you are grouping and labeling swimlanes by the '''Project Name'''. Though this step is optional, it is strongly recommended.
+
Go to the '''Template Properties''' form’s '''Rows/Swimlanes''' tab shown below. Ensure that you are grouping and labeling swimlanes by the '''Project Name'''. Though this step is optional, it is strongly recommended.
  
 
<center>[[File:P60-8_2_1-60-(3)-02082017.png]]</center>
 
<center>[[File:P60-8_2_1-60-(3)-02082017.png]]</center>
 
<center>P60-8_2_1-60-(3)-02082017.png</center>
 
<center>P60-8_2_1-60-(3)-02082017.png</center>
  
5) Now click the '''Save and use''' or '''Use''' button to make this '''Template''' the current '''Template''' to support creating a multi-project project view.
+
Now click the '''Save and use''' or '''Use''' button to make this '''Template''' the current '''Template''' to support creating a multi-project chart. Once you’ve saved the '''Template Properties''' form, now click the '''New…''' button on the left margin of the '''File''' tab.  You should still be on the '''File''' tab at this point.
 
+
6) Once you’ve saved the '''Template Properties''' form, now click the '''New…''' button on the left margin of the '''File''' tab.  You should still be on the '''File''' tab at this point.
+
  
 
==Use the First Microsoft Project Source Plan==
 
==Use the First Microsoft Project Source Plan==
  
7) When you click the '''New…''' button, OnePager will take you back to the '''Home''' tab and display the OnePager choices ('''OPC''') form.  Click the '''Select''' button in in the upper right corner and select the '''BROWSE FILES…''' option from the dropdown menu.  A Windows '''Open''' form will appear as shown below:
+
When you click the '''New…''' button, OnePager will take you back to the '''Home''' tab and display the OnePager choices ('''OPC''') form.  Click the '''Select''' button in in the upper right corner and select the '''BROWSE FILES…''' option from the dropdown menu.  A Windows '''Open''' form will appear as shown below:
  
 
<center>[[File:P60-8_2_1-60-(4)-10072016.png]]</center>
 
<center>[[File:P60-8_2_1-60-(4)-10072016.png]]</center>
  
8) Select the first Microsoft Project '''source plan''' in the set of three and then click the '''Open''' button.  When you do this, the '''OPC''' form expands as shown here:
+
Select the first Microsoft Project '''source plan''' in the set of three and then click the '''Open''' button.  When you do this, the '''OPC''' form expands as shown here:
  
 
<center>[[File:P60-8_2_1-60-(5)-02082017.png]]</center>
 
<center>[[File:P60-8_2_1-60-(5)-02082017.png]]</center>
Line 47: Line 37:
 
==Use the Remaining Microsoft Project Source Plans==
 
==Use the Remaining Microsoft Project Source Plans==
  
9) We are now going to confirm the name of the Microsoft Project '''source plan'''.
+
We are now going to confirm the name of the Microsoft Project '''source plan'''.   Type in a new chart title and confirm the snapshot date.   Once that is done, we are going to click on the '''Add/Remove''' button.  '''Data source selection''' form will appear and you can use the '''Add''' button to add the two remaining Microsoft Project '''source plans''' to the '''source packet''' as show below:
 
+
:a) Type in a new project view title and confirm the snapshot date.
+
 
+
:b)  Once that is done, we are going to click on the '''Add/Remove''' button.   
+
 
+
:c) '''Data source selection''' form will appear and you can use the '''Add''' button to add the two remaining Microsoft Project '''source plans''' to the '''source packet''' as show below:
+
  
 
<center>[[File:P60-8_2_1-60-(6)-02082017.png]]</center>
 
<center>[[File:P60-8_2_1-60-(6)-02082017.png]]</center>
 
<center>P60-8_2_1-60-(6)-02082017.png</center>
 
<center>P60-8_2_1-60-(6)-02082017.png</center>
  
10) Click the '''OK''' button and OnePager will update the '''Selected File(s)''' group of the '''OPC''' form indicating that all three Microsoft Project '''source plans''' were found as shown below:
+
Click the '''OK''' button and OnePager will update the '''Selected File(s)''' group of the '''OPC''' form indicating that all three Microsoft Project '''source plans''' were found as shown below:
  
 
<center>[[File:P60-8_2_1-60-(7)-02082017.png]]</center>
 
<center>[[File:P60-8_2_1-60-(7)-02082017.png]]</center>
 
<center>P60-8_2_1-60-(7)-02082017.png</center>
 
<center>P60-8_2_1-60-(7)-02082017.png</center>
  
==Create the Multi-Project Project View==
+
==Create the Multi-Project Chart==
  
11) Now, go ahead and click the '''Create the new project view''' button on the '''OPC''' form and the resulting project view will look like this:
+
Now, go ahead and click the '''Create the new chart''' button on the '''OPC''' form and the resulting chart will look like this:
  
 
<center>[[File:P60-8_2_1-60-(8)-10072016.png]]</center>
 
<center>[[File:P60-8_2_1-60-(8)-10072016.png]]</center>
Line 71: Line 55:
 
==Settings for Microsoft Project ==
 
==Settings for Microsoft Project ==
  
12) '''OPP''' always uses the label (name) of the project-summary task to identify each project in a multi-project situation.  
+
'''OPP''' always uses the label (name) of the project-summary task to identify each project in a multi-project situation. OnePager does not use the Microsoft Project '''source plan''' name to identify projects. If you want to display the project summary task (Task 0) at the top of a project file, go to the '''File''' tab on Microsoft Project’s tool bar. Then navigate to '''Options''' tab and once there, to the '''Advanced''' tab and check the checkbox that is shown below:
 
+
:a) OnePager does not use the Microsoft Project '''source plan''' name to identify projects.  
+
 
+
:b) If you want to display the project summary task (Task 0) at the top of a project file, go to the '''File''' tab on Microsoft Project’s tool bar. Then navigate to '''Options''' tab and once there, to the '''Advanced''' tab and check the checkbox that is shown below:
+
  
 
<center>[[File:P60-8_2_1-60-(9)-10072016.png]]</center>
 
<center>[[File:P60-8_2_1-60-(9)-10072016.png]]</center>
  
13) Since we are using the '''pull''' operation workflow to create this multi-project project view, the setting above on the Microsoft Project’s '''Project Options''' page must be set '''before''' the first designated Microsoft Project '''source plan''' is pulled in and must stay set for all subsequent '''source plan pull''' operations. This is because, although Microsoft Project as an application will not appear on your screen anytime during the '''pull''' operation, nevertheless, it will be launched by '''OPP''' and will operate on the designated files before '''OPP''' processes them.
+
Since we are using the '''pull''' operation workflow to create this multi-project chart, the setting above on the Microsoft Project’s '''Project Options''' page must be set '''before''' the first designated Microsoft Project '''source plan''' is pulled in and must stay set for all subsequent '''source plan pull''' operations. This is because, although Microsoft Project as an application will not appear on your screen anytime during the '''pull''' operation, nevertheless, it will be launched by '''OPP''' and will operate on the designated files before '''OPP''' processes them.
 
+
==Updating Project Views Created from Separate Microsoft Project Plans==
+
  
14) Eventually you will want to update your multi-project project view by either adding a snapshot or replacing a snapshot with updated data.  To perform either the add or the replace snapshot, the processes described in the '''Related Links''' section below can be used.
+
==Updating Charts Created from Separate Microsoft Project Plans==
  
15) The key to updating multi-project project views is the proper management of the '''source packet'''.  Recall that the '''source packet''' contains the file or files that are to be used to either create or update a project view.  They are stored as file names and path names in the project view’s '''.TAM''' file and can be accessed from the '''Data''' tab’s '''Selected file(s)''' button on the ribbon as shown below:
+
Eventually you will want to update your multi-project chart by either adding a snapshot or replacing a snapshot with updated data.  To perform either the add or the replace snapshot, the processes described in the '''Related Links''' section below can be used. The key to updating multi-project charts is the proper management of the '''source packet'''.  Recall that the '''source packet''' contains the file or files that are to be used to either create or update a chart.  They are stored as file names and path names in the chart’s '''.TAM''' file and can be accessed from the '''Data''' tab’s '''Selected file(s)''' button on the ribbon as shown below:
  
 
<center>[[File:P60-8_2_1-60-(10)-10072016.png]]</center>
 
<center>[[File:P60-8_2_1-60-(10)-10072016.png]]</center>
  
16) Validating the contents of the '''source packet''' and assuring that these are the Microsoft Project '''source plans''' that were updated is an essential step before proceeding to perform a project view update.
+
Validating the contents of the '''source packet''' and assuring that these are the Microsoft Project '''source plans''' that were updated is an essential step before proceeding to perform a chart update.
  
 
==Related Links==
 
==Related Links==

Latest revision as of 20:45, 5 January 2021

Overview

Suppose you need to build a multi-project chart without first creating a Microsoft Project Integrated Master Schedule (IMS). To illustrate an approach to do this, we’ll use the OnePager Pro (OPP) desktop application. Just follow the steps listed below:

Setting up the Template for a Multi-Project Graph

Launch OPP from the desktop icon and navigate to the File tab on the ribbon. Then, click on the Options button on the left margin. On the Options form, go to the Template button on the right side and click it. This action will bring up the Template Properties form. Finally, navigate to the Advanced tab on the Template Properties form as shown below:

P60-8 2 1-60-(1)-02082017.png
P60-8_2_1-60-(1)-02082017.png

At the Advanced tab, check the Safely combine tasks from different files checkbox. This setting allows you to import multiple standalone Microsoft Project source plans. If you do not check this checkbox, OnePager may confuse tasks from one Microsoft Project source plan with tasks from another when the tasks have the same UniqueID in Microsoft Project Professional.

P60-8 2 1-60-(2)-02082017.png
P60-8_2_1-60-(2)-02082017.png

Adjustments to Rows and Swimlanes

Go to the Template Properties form’s Rows/Swimlanes tab shown below. Ensure that you are grouping and labeling swimlanes by the Project Name. Though this step is optional, it is strongly recommended.

P60-8 2 1-60-(3)-02082017.png
P60-8_2_1-60-(3)-02082017.png

Now click the Save and use or Use button to make this Template the current Template to support creating a multi-project chart. Once you’ve saved the Template Properties form, now click the New… button on the left margin of the File tab. You should still be on the File tab at this point.

Use the First Microsoft Project Source Plan

When you click the New… button, OnePager will take you back to the Home tab and display the OnePager choices (OPC) form. Click the Select button in in the upper right corner and select the BROWSE FILES… option from the dropdown menu. A Windows Open form will appear as shown below:

P60-8 2 1-60-(4)-10072016.png

Select the first Microsoft Project source plan in the set of three and then click the Open button. When you do this, the OPC form expands as shown here:

P60-8 2 1-60-(5)-02082017.png
P60-8_2_1-60-(5)-02082017.png

Use the Remaining Microsoft Project Source Plans

We are now going to confirm the name of the Microsoft Project source plan. Type in a new chart title and confirm the snapshot date. Once that is done, we are going to click on the Add/Remove button. Data source selection form will appear and you can use the Add button to add the two remaining Microsoft Project source plans to the source packet as show below:

P60-8 2 1-60-(6)-02082017.png
P60-8_2_1-60-(6)-02082017.png

Click the OK button and OnePager will update the Selected File(s) group of the OPC form indicating that all three Microsoft Project source plans were found as shown below:

P60-8 2 1-60-(7)-02082017.png
P60-8_2_1-60-(7)-02082017.png

Create the Multi-Project Chart

Now, go ahead and click the Create the new chart button on the OPC form and the resulting chart will look like this:

P60-8 2 1-60-(8)-10072016.png

Settings for Microsoft Project

OPP always uses the label (name) of the project-summary task to identify each project in a multi-project situation. OnePager does not use the Microsoft Project source plan name to identify projects. If you want to display the project summary task (Task 0) at the top of a project file, go to the File tab on Microsoft Project’s tool bar. Then navigate to Options tab and once there, to the Advanced tab and check the checkbox that is shown below:

P60-8 2 1-60-(9)-10072016.png

Since we are using the pull operation workflow to create this multi-project chart, the setting above on the Microsoft Project’s Project Options page must be set before the first designated Microsoft Project source plan is pulled in and must stay set for all subsequent source plan pull operations. This is because, although Microsoft Project as an application will not appear on your screen anytime during the pull operation, nevertheless, it will be launched by OPP and will operate on the designated files before OPP processes them.

Updating Charts Created from Separate Microsoft Project Plans

Eventually you will want to update your multi-project chart by either adding a snapshot or replacing a snapshot with updated data. To perform either the add or the replace snapshot, the processes described in the Related Links section below can be used. The key to updating multi-project charts is the proper management of the source packet. Recall that the source packet contains the file or files that are to be used to either create or update a chart. They are stored as file names and path names in the chart’s .TAM file and can be accessed from the Data tab’s Selected file(s) button on the ribbon as shown below:

P60-8 2 1-60-(10)-10072016.png

Validating the contents of the source packet and assuring that these are the Microsoft Project source plans that were updated is an essential step before proceeding to perform a chart update.

Related Links

Creating a NEW Project View via Pull Operation - OnePager Pro 7.13.1-70

REPLACING a Snapshot via Pull Operation - OnePager Pro 7.14.1-70

ADDING a Snapshot via Pull Operation - OnePager Pro 7.15.1-70