Difference between revisions of "Order of Tasks/Milestones Decorations for Version 7.0"

From OnePager Documentation
Jump to: navigation, search
(Example)
(Ordering Sub-Command)
Line 28: Line 28:
 
<center>P70-10_13_1-70-(1)-09202019.png</center>
 
<center>P70-10_13_1-70-(1)-09202019.png</center>
  
===Ordering Sub-Command===
+
===Ordering Sub-Commands===
  
 
6) The sub-menu for the '''Order''' command allows you to select any of the four sub-commands as follows:
 
6) The sub-menu for the '''Order''' command allows you to select any of the four sub-commands as follows:

Revision as of 20:14, 20 September 2019

About Ordering Task/Milestones With Decorations

1) Editing the z-ordering for specific task/milestone decorations is useful when these decorations are overlaid in the chart by other graphics.

2) Decorations on tasks/milestones are always drawn in the same z-order from back to front.

Standard Ordering of Decorations

3) This fixed ordering from back to front is given below:

a) Connectors in back (e.g., baseline to task/milestone, endpoints, and deadline connectors to task/milestone)
b) Task/Milestone
c) Baseline
d) Endpoints/Deadline
e) All text for task/milestone, deadline and endpoints in front.

Editing the Ordering of Task/Milestones with Decorations

4) Editing the z-order for a task/milestone shape with decorations is done on an individual task/milestone basis.

5) That is, you must first select the task/milestone shape with a right-click to access the context menu as shown below:

File:P70-10 13 1-70-(1)-09202019.png
P70-10_13_1-70-(1)-09202019.png

Ordering Sub-Commands

6) The sub-menu for the Order command allows you to select any of the four sub-commands as follows:

a) Bring to front. This option puts the task/milestone decorations in front of all other shapes in the chart area.
b) Send to back. This option puts the task/milestone decorations behind all other foreground shapes in the chart area (but not behind background shapes).
c) Bring forward. Selecting the Bring forward option steps the task/milestone decorations forward by one increment of Z-level. This is not very useful.
d) Send backward. This option steps the task/milestone decorations backward by one Z-level. This also is not very useful.

6) The action of the Order command applies to the task/milestone itself and all decorations associated with it including Task Links.

Example

1) Suppose we have a chart with Percent Complete decorations shown on some task/milestone shapes as shown below:

File:P70-10 13 1-70-(2)-09202019.png
P70-10_13_1-70-(2)-09202019.png

2) If the Engineering Team 2 Development task is moved up to overlay the ADONIS Subcontractor Selection Task the chart then looks like this:

File:P70-10 13 1-70-(3)-09202019.png
P70-10_13_1-70-(3)-09202019.png

3) If our goal, for the sake of this example, is to show the ADONIS Subcontractor Selection task with its Percent Complete decoration showing on top, we need to us the Order command's Send to back sub-command to do this as shown here:

File:P70-10 13 1-70-(3-1)-09202019.png
P70-10_13_1-70-(3-1)-09202019.png

4) When the operation above is complete, the chart looks like this:

File:P70-10 13 1-70-(5)-09202019.png
P70-10_13_1-70-(5)-09202019.png

5) The Order command is useful when it is necessary to orient task/milestone shapes with decorations when these task/milestone shapes overlay other graphics such as Comment Boxes or Curtains.