Difference between revisions of "Order of Tasks/Milestones Decorations for Version 7.0"

From OnePager Documentation
Jump to: navigation, search
(Example)
(Ordering Sub-Commands)
Line 30: Line 30:
 
===Ordering Sub-Commands===
 
===Ordering Sub-Commands===
  
6) The sub-menu for the '''Order''' command allows you to select any of these four sub-commands.
+
6) The '''sub-menu''' for the '''Order''' command allows you to select any of these four sub-commands.
  
7) '''Bring to front'''.  This option puts the task/milestone shape '''decorations''' in front of all other shapes in the chart area.
+
7) '''Bring to front'''.  This option puts the task bar/milestone symbol '''decorations in front''' of all other shapes in the chart area.
  
8) '''Send to back'''.  This option puts the task/milestone shape '''decorations''' behind all other foreground shapes in the chart area (but not behind background shapes).
+
8) '''Send to back'''.  This option puts the task BAR/milestone sYMBOL '''decorations behind all other foreground''' shapes in the chart area (but not behind background shapes).
  
9) '''Bring forward'''.  Selecting the '''Bring forward''' option steps the task/milestone shape '''decorations''' forward by one increment of '''Z-level'''.  This is not very useful.
+
9) '''Bring forward'''.  Selecting the '''Bring forward''' option steps the task bar/milestone symbol '''decorations forward by one increment''' of '''Z-level'''.  This is not very useful.
  
10) '''Send backward'''.  This option steps the task/milestone shape '''decorations''' backward by one '''Z-level'''.  This also is not very useful.
+
10) '''Send backward'''.  This option steps the task bar/milestone symbol '''decorations backward by one increment''' of '''Z-level'''.  This also is not very useful.
  
11) The action of the '''Order''' command applies to the task/milestone shape itself and all '''decorations''' associated with it including '''Task Links'''.
+
11) The action of the '''Order''' command applies to the task bar/milestone symbol itself and all '''decorations''' associated with it including '''Task Links'''.
  
 
==Example==
 
==Example==

Revision as of 14:53, 4 June 2020

About Ordering Task/Milestones With Decorations

1) Editing the z-ordering for specific task bar/milestone symbol decorations is useful when these decorations are overlaid in the chart by other graphics.

2) Decorations on task bars/milestone symbols are always drawn in the same z-order from back to front.

Standard Ordering of Decorations

3) This fixed ordering from back to front is given here:

a) Connectors in back (e.g., baseline connectors to task bars/milestone symbols, endpoint shapes, and deadline connectors to task bars/milestone symbols)
b) Task Bars/Milestone Symbols
c) Baseline Shapes
d) Endpoints/Deadline Shapes
e) All text for task bars/milestone symbols, deadline shapes and endpoint shapes in front.

Editing the Ordering of Task Bars/Milestone Symbols with Decorations

4) Editing the z-order for a task bar/milestone symbol with decorations is done on an individual task bar/milestone symbol basis.

5) That is, you must first select the task bar/milestone symbol with a right-click to access the task bar right-click context menu as shown below:

P70-10 13 1-(1)-06042020.png
P70-10_13_1-(1)-06042020.png

Ordering Sub-Commands

6) The sub-menu for the Order command allows you to select any of these four sub-commands.

7) Bring to front. This option puts the task bar/milestone symbol decorations in front of all other shapes in the chart area.

8) Send to back. This option puts the task BAR/milestone sYMBOL decorations behind all other foreground shapes in the chart area (but not behind background shapes).

9) Bring forward. Selecting the Bring forward option steps the task bar/milestone symbol decorations forward by one increment of Z-level. This is not very useful.

10) Send backward. This option steps the task bar/milestone symbol decorations backward by one increment of Z-level. This also is not very useful.

11) The action of the Order command applies to the task bar/milestone symbol itself and all decorations associated with it including Task Links.

Example

1) Suppose we have a chart with Percent Complete decorations shown on some task/milestone shapes as shown below:

P70-10 13 1-(2)-06042020.png
P70-10_13_1-(2)-06042020.png
File:P70-10 13 1-70-(2)-09202019.png
P70-10_13_1-70-(2)-09202019.png

2) If the Engineering Team 2 Development task is moved up to overlay the ADONIS Subcontractor Selection Task the chart then looks like this:

File:P70-10 13 1-(3)-06042020.png
P70-10_13_1-(3)-06042020.png
File:P70-10 13 1-70-(3)-09202019.png
P70-10_13_1-70-(3)-09202019.png

3) If our goal, for the sake of this example, is to show the ADONIS Subcontractor Selection task with its Percent Complete decoration showing on top, we need to us the Order command's Send to back sub-command to do this as shown here:

P70-10 13 1-(4)-06042020.png
P70-10_13_1-(4)-06042020.png
File:P70-10 13 1-70-(3-1)-09202019.png
P70-10_13_1-70-(3-1)-09202019.png

4) When the operation above is complete, the chart looks like this:

P70-10 13 1-(5)-06042020.png
P70-10_13_1-(5)-06042020.png
File:P70-10 13 1-70-(5)-09202019.png
P70-10_13_1-70-(5)-09202019.png

5) The Order command is useful when it is necessary to orient task/milestone shapes with decorations when these task/milestone shapes overlay other graphics such as Comment Boxes or Curtains.

(10.13.1-70)