1) Decorations on tasks/milestones are always drawn in the same z-order from back to front.

2) This fixed ordering from back to front is given below:

a) Connectors in back (e.g., baseline to task/milestone, endpoints, and deadline connectors to task/milestone)
b) Task/Milestone
c) Baseline
d) Endpoints/Deadline
e) All text for task/milestone, deadline and endpoints/deadline in front.

3) Editing the z-order for a task/milestone shape with decorations is done on an individual task/milestone basis.

4) That is, you must first select the task/milestone shape with a right-click to access the context menu as shown below:

File:P70-10 13 1-70-(1)-09202019.png
P70-10_13_1-70-(1)-09202019.png

5) The sub-menu for the Order command allows you to select any of the four sub-commands as follows:

a) Bring to front. This option puts the task/milestone decorations in front of all other shapes in the chart area.
b) Send to back. This option puts the task/milestone decorations behind all other foreground shapes in the chart area (but not behind background shapes).
c) Bring forward. Selecting the Bring forward option steps the task/milestone decorations forward by one increment of Z-level. This is not very useful.
d) Send backward. This option steps the task/milestone decorations backward by one Z-level. This also is not very useful.


6) The action of the Order command applies to the task/milestone itself and all decorations associated with it including Task Links.