(Created page with "==About Modifying Percent Complete)== '''Percent complete''' displays are driven by the '''percent complete''' data imported from the Microsoft Excel '''source plan'''. Not e...")
 
 
(3 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
==About Modifying Percent Complete)==
 
==About Modifying Percent Complete)==
  
'''Percent complete''' displays are driven by the '''percent complete''' data imported from the Microsoft Excel '''source plan'''. Not every task in a Microsoft Project '''source plan''' has '''percent complete''' data associated with it.  '''Percent complete''' data for milestones are usually either zero (0%) or totally (100%) complete.  When you desire to display '''percent complete''' information, it is essential that these data be properly represented in the associated Microsoft Excel plan before the data are imported to OnePager Express ('''OPX''').
+
'''Percent complete''' displays are driven by the '''percent complete''' field data imported from the Microsoft Excel '''source plan'''. Not every task in a Microsoft Excel '''source plan''' has '''percent complete''' data associated with it.  '''Percent complete''' data for milestones are usually either zero (0%) or totally (100%) complete.  When you desire to display '''percent complete''' information, it is essential that these data be properly represented in the associated Microsoft Excel '''source plan''' before the data are imported to OnePager Express ('''OPX''').
  
 
==Modifying All Task Percent Complete Displays==   
 
==Modifying All Task Percent Complete Displays==   
  
All task '''percent complete''' displays may be modified without changing the settings in the current '''template''' by using the following steps:
+
All task '''percent complete''' displays may be modified without changing the settings in the current '''Template''' by using the following steps:
  
 
1) Click the Project-View Properties ('''PVP''') button on the '''Home''' ribbon in the '''Settings''' group.
 
1) Click the Project-View Properties ('''PVP''') button on the '''Home''' ribbon in the '''Settings''' group.
  
2) Then, navigate to either the '''Task Bars''' tab.
+
2) Next, navigate to either the '''Task Bars''' tab.
  
 
3) Ensure that the '''%Complete''' checkbox is checked and then click the '''%Complete Properties''' button as shown below:
 
3) Ensure that the '''%Complete''' checkbox is checked and then click the '''%Complete Properties''' button as shown below:
  
<center>[[File:X53-10_4_1-53-(1)-12242015.png]]</center>
+
<center>[[File:X60-10_4_1-60-(1)-02092917.png]]</center>
 +
<!--<center>X60-10_4_1-60-(1)-02092917.png</center>-->
  
 
4) There are two sets of controls in the '''Set percent-complete properties''' form:  
 
4) There are two sets of controls in the '''Set percent-complete properties''' form:  
Line 19: Line 20:
 
:(1) For changing the properties of the '''percent complete bar''' and  
 
:(1) For changing the properties of the '''percent complete bar''' and  
  
:(2) for changing the properties of the '''percent complete''' related text.
+
:(2) To change the properties of the '''percent complete''' related text.
  
:a) Checking the '''Show percent-complete bars''' checkbox activates controls over the '''color''' of the '''percent complete bar''' displayed in the task and the '''height''' of the '''percent complete bar''' within the task bar as a percent of the total task (Gantt bar) height.
+
:a) Checking the '''Show percent-complete bars''' checkbox activates controls over the '''color''' of the '''percent complete bar''' displayed in the task and the '''height''' of the '''percent complete bar''' within the task bar as a percent of the total task (Gantt bar) '''height'''.
  
 
::i) Clicking the '''%Complete color''' dropdown menu will bring up the standard '''Color Chooser'''  which allows you to set the specific '''color''' for the '''percent complete bar''' represented in the task.
 
::i) Clicking the '''%Complete color''' dropdown menu will bring up the standard '''Color Chooser'''  which allows you to set the specific '''color''' for the '''percent complete bar''' represented in the task.
::ii) You can also use the '''%Complete height''' control to set the relative height of the '''percent complete bar''' as a percentage of the total task bar height.
+
::ii) You can also use the '''%Complete height''' control to set the relative '''height''' of the '''percent complete bar''' as a percentage of the total task bar '''height'''.
::iii) When selecting a percentage for the '''percent complete bar height''', recall that task bars can vary in height through manual editing.  Therefore, applying this control to all task bars will result in varying heights for the '''percent complete bar''' as well.
+
::iii) When selecting a percentage for the '''percent complete bar height''', recall that task bars can vary in '''height''' through manual editing.  Therefore, applying this control to all task bars will result in varying '''heights''' for the '''percent complete bar''' as well.
  
:b) Checking the '''Show percent-complete text''' checkbox will activate control for the '''percent complete text''' (numerical) associated with the task.  You may choose to display the '''percent complete bar''' only, the '''percent complete text''' only, or both using these two checkboxes.  When activated, you have the following controls to modify the appearance of the '''percent complete''' information for all task bars:
+
:b) Checking the '''Show percent-complete text''' checkbox will activate control for the '''percent complete text''' (numerical) associated with the task.  You can choose to display the '''percent complete bar''' only, the '''percent complete text''' only, or both using these two checkboxes.  When activated, you have the following controls to modify the appearance of the '''percent complete''' information for all task bars:
  
 
::i) The '''%Complete font''' controls respond exactly as other '''text font''' controls found elsewhere in OnePager.  Clicking the '''%Complete font''' dropdown menu button will bring up the standard '''Set font properties''' form that was explained above.
 
::i) The '''%Complete font''' controls respond exactly as other '''text font''' controls found elsewhere in OnePager.  Clicking the '''%Complete font''' dropdown menu button will bring up the standard '''Set font properties''' form that was explained above.
 
::ii) Similarly, the '''Label position''' dropdown menu button gives you access to the '''eight available positions''' to place the '''percent complete text'''.
 
::ii) Similarly, the '''Label position''' dropdown menu button gives you access to the '''eight available positions''' to place the '''percent complete text'''.
::iii) Finally, the '''Separator''' dropdown menu button provides you with eight options for separating the '''percent complete text''' from the task bar '''label'''.
+
::iii) Finally, the '''Separator''' dropdown menu button provides you with '''eight''' options for separating the '''percent complete text''' from the task bar '''label'''.
  
 
5) When the '''%Complete''' checkbox is checked and both the '''Show percent-complete bars''' and '''Show percent-complete text''' checkboxes are checked in the '''Set percent-complete properties''' form, the '''percent complete''' information for tasks will look like this:
 
5) When the '''%Complete''' checkbox is checked and both the '''Show percent-complete bars''' and '''Show percent-complete text''' checkboxes are checked in the '''Set percent-complete properties''' form, the '''percent complete''' information for tasks will look like this:
Line 41: Line 42:
 
The default settings for displaying '''percent complete''' information for individual task can be modified by using the following steps:
 
The default settings for displaying '''percent complete''' information for individual task can be modified by using the following steps:
  
1) You can select the task by right-clicking on it to reveal the context menu with the '''Format…''' command or click the '''Format…''' button on the '''Home''' ribbon.
+
1) You can select the task by right-clicking on it to reveal the context menu with the '''Format…''' command or click the '''Format…''' button on the '''Home''' ribbon after selecting the desired tasks/milestones.
  
 
2) Either way, click the '''Format..." command to bring up the '''Change Marker Properties''' form.  Then, select the '''Percent Complete''' tab in the '''Change Marker Properties''' form which looks like this:
 
2) Either way, click the '''Format..." command to bring up the '''Change Marker Properties''' form.  Then, select the '''Percent Complete''' tab in the '''Change Marker Properties''' form which looks like this:
Line 61: Line 62:
 
:d) Clicking the '''%Complete Font''' dropdown button will bring up the standard '''Font properties''' form which can be used to change the '''font properties''' of the '''%Complete label''' and numeric text.
 
:d) Clicking the '''%Complete Font''' dropdown button will bring up the standard '''Font properties''' form which can be used to change the '''font properties''' of the '''%Complete label''' and numeric text.
  
:e) The '''Use %Complete Defaults''' button bar, when clicked, will change the task’s '''%Complete properties''' to those currently specified as global in the current '''template''' form.
+
:e) The '''Use %Complete Defaults''' button bar, when clicked, will change the task’s '''%Complete properties''' to those currently specified as global in the current '''Template''' form.
  
 
(10.4.1-60)
 
(10.4.1-60)

Latest revision as of 15:06, 5 April 2017

About Modifying Percent Complete)

Percent complete displays are driven by the percent complete field data imported from the Microsoft Excel source plan. Not every task in a Microsoft Excel source plan has percent complete data associated with it. Percent complete data for milestones are usually either zero (0%) or totally (100%) complete. When you desire to display percent complete information, it is essential that these data be properly represented in the associated Microsoft Excel source plan before the data are imported to OnePager Express (OPX).

Modifying All Task Percent Complete Displays

All task percent complete displays may be modified without changing the settings in the current Template by using the following steps:

1) Click the Project-View Properties (PVP) button on the Home ribbon in the Settings group.

2) Next, navigate to either the Task Bars tab.

3) Ensure that the %Complete checkbox is checked and then click the %Complete Properties button as shown below:

X60-10 4 1-60-(1)-02092917.png

4) There are two sets of controls in the Set percent-complete properties form:

(1) For changing the properties of the percent complete bar and
(2) To change the properties of the percent complete related text.
a) Checking the Show percent-complete bars checkbox activates controls over the color of the percent complete bar displayed in the task and the height of the percent complete bar within the task bar as a percent of the total task (Gantt bar) height.
i) Clicking the %Complete color dropdown menu will bring up the standard Color Chooser which allows you to set the specific color for the percent complete bar represented in the task.
ii) You can also use the %Complete height control to set the relative height of the percent complete bar as a percentage of the total task bar height.
iii) When selecting a percentage for the percent complete bar height, recall that task bars can vary in height through manual editing. Therefore, applying this control to all task bars will result in varying heights for the percent complete bar as well.
b) Checking the Show percent-complete text checkbox will activate control for the percent complete text (numerical) associated with the task. You can choose to display the percent complete bar only, the percent complete text only, or both using these two checkboxes. When activated, you have the following controls to modify the appearance of the percent complete information for all task bars:
i) The %Complete font controls respond exactly as other text font controls found elsewhere in OnePager. Clicking the %Complete font dropdown menu button will bring up the standard Set font properties form that was explained above.
ii) Similarly, the Label position dropdown menu button gives you access to the eight available positions to place the percent complete text.
iii) Finally, the Separator dropdown menu button provides you with eight options for separating the percent complete text from the task bar label.

5) When the %Complete checkbox is checked and both the Show percent-complete bars and Show percent-complete text checkboxes are checked in the Set percent-complete properties form, the percent complete information for tasks will look like this:

X52-10 4-(2)-06082015.png

Modifying Individual Task Percent Complete Displays

The default settings for displaying percent complete information for individual task can be modified by using the following steps:

1) You can select the task by right-clicking on it to reveal the context menu with the Format… command or click the Format… button on the Home ribbon after selecting the desired tasks/milestones.

2) Either way, click the Format..." command to bring up the Change Marker Properties form. Then, select the Percent Complete tab in the Change Marker Properties form which looks like this:

P52-10 3-(3)-06012015.png

3) Go to the Percent Complete tab as shown above which controls the display of the percent complete (%) bar on the selected task and the placement of the numeric text for percent complete information:

a) The Show Percent Complete checkbox allows you to turn on and off the display of percent complete information for the selected task.
b) When the Show Percent Complete checkbox is checked, you have the option to display either the Percent Complete bar within the selected task or the Percent Complete numeric text or both by checking the appropriate checkboxes as illustrated below:
X52-10 4-(4)-06082015.png
c) If you check the Show %Complete Label checkbox, OnePager will display the numeric value of the percent complete in a position you determine by selecting an option from the dropdown menu to the right of the Show %Complete Label checkbox as illustrated here:
X52-10 4-(5)-06082015.png
d) Clicking the %Complete Font dropdown button will bring up the standard Font properties form which can be used to change the font properties of the %Complete label and numeric text.
e) The Use %Complete Defaults button bar, when clicked, will change the task’s %Complete properties to those currently specified as global in the current Template form.

(10.4.1-60)