Snapshot-Dependent Text Columns for OnePager Pro for Version 6.0

From OnePager Documentation
Revision as of 17:19, 17 November 2016 by Rfeingold (Talk | contribs) (Created page with "==Overview (PE60-12_4_1-60-11152016)== Certain fields (columns) from Microsoft Project typically change from snapshot to snapshot and will automatically be updated if they ar...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Overview (PE60-12_4_1-60-11152016)

Certain fields (columns) from Microsoft Project typically change from snapshot to snapshot and will automatically be updated if they are selected to drive the text column cell contents. These fields include:

  • Percent Complete (% complete)
  • Duration
  • Start Date
  • Finish Date
  • Baseline Start Date
  • Baseline Finish Date
  • Deadline Date
  • Any column used for round-robin color assignment
  • Any column used for conditional-formatting
  • Any column used for endpoints

Often it is important in presentations to emphasize the above data items by collecting tasks/milestones into rows and to label rows using one of the above fields from the Microsoft Project source plan.

When this is done, the project view will show that row text column contents and the rows continue to be associated with one of the above data fields and the snapshots will change to show the most current data in the view and in the text column contents as successive snapshots are taken over time.

Example

The following example illustrates the feature:

1) The following example Microsoft Project source plan shows all the column field names mentioned above and the Task Name, Resource Names, and Flag20:

P52-10 4-(1)-06022015.png
P52-10_4-(1)-06022015.png

2) Note the % Done column with the specific %Complete data for each task.

3) When the OnePager Pro (OPP) button is clicked, you have an opportunity to select the functions of the various Microsoft Project source plan data columns as described elsewhere by examining and modifying the OnePager Choices (OPC) form. The example is such that the row text column contents, row ordering, and collection are set to use the % Done column to organize the project view.

4) When these controls are set in the template through the Row and Swimlanes tab, the following snapshot will be created:

File:P60-10 4 1-60-(2)-11172016.png
P60-10_4_1-60-(2)-11172016.png

5) In the first snapshot, the text column cells are created with the % Done data in ascending order so that the tasks with the lowest % Done task will be at the top of the swimlane set of rows. The tasks/milestones will not be reordered in subsequent snapshots as this would violate a basic principle of OnePager to maintain consistency of look and feel between snapshots.

6) If the project’s Microsoft Project plan is updated, say on 11/11/2015, with the latest % Done data, that Microsoft Project plan might look like this:

P52-10 4-(3)-06022015.png
P52-10_4-(3)-06022015.png

7) The updates to the % DONE data, shown above, as compared to the Microsoft Project plan captured on 4/21/2015, shows that the project is progressing but the tasks of interest, those with a Flag20 flag of Yes indicate that these tasks of interest are behind schedule.

8) If we create the snapshot on 11/11/2015, it will look like this:

File:P60-10 4 1-60-(4)-11172016.png
P60-10_4_1-60-(4)-11172016.png

9) The tasks/milestones are updated with the latest % DONE data and the new percent complete information from the Microsoft Project plan is shown in the text column for each row. OPP does not reorder rows between snapshots but retains the row ordering originally established for the project view. The Microsoft Project plan did not change the Finish Dates of any of the tasks to reflect their current % DONE.

(12.4-1-60)