Difference between revisions of "TEMPxx1"

From OnePager Documentation
Jump to: navigation, search
(Blanked the page)
Line 1: Line 1:
==Overview==
 
  
This article is meant to clarify how '''snapshots''' apply to OnePager charts.  Two cases are explained.  The first is where a single '''source plan''' is used to represent changes through the project which updated to the single '''source plan''' file.  The second case is where multiple '''source plans''' are produced for each update of the project as it proceeds through time toward completion.
 
 
The concepts described and used in this article apply equally to OnePager Pro, OnePager Express and OnePager Bundle.
 
 
==About Charts and Snapshots for OnePager==
 
 
OnePager charts and snapshots let you create schedule '''charts''' for specific audiences and show them how the project is changing over time. Each chart is a subset of the tasks in a '''source plan''' (e.g., Microsoft Project, Microsoft Excel, Smartsheet, or Oracle Primavera P6) that you specified with a '''Flag''' field.
 
 
For each chart, you can import different versions of its schedule to keep track of how those tasks and milestones change over time. You can store each '''version''' of the schedule as a separate '''snapshot''' and give it a unique '''snapshot date''' in the past, present, or future. Each chart '''saves''' your presentation '''colors, row and swimlane assignments, font sizes, titles, and legends''' so that you don't need to '''re-edit''' the graphics every time the project changes.
 
 
A simple relationship between a '''source plan''' (Project A), charts created from that Microsoft Project '''source plan''', for example, using different '''Flag''' settings, and '''snapshots''' is shown below:
 
 
<!--<center>[[File:P70-4_0_1_1-(1A)-04292020.png]]</center>-->
 
<!--<center>P70-4_0_1_1-(1A)-04292020.png</center>-->
 
<center>[[File:P71-4_0_1_1-71-(1A-1)-11012021.png]]</center>
 
<center>P71-4_0_1_1-71-(1A-1)-11012021.png</center>
 
 
===Using a Single Source Plan throughout a Project Period===
 
 
The following discussion, based on the figure above, assumes that you have one '''source plan''', with a single plan name (Project A), that is used to manage the project. This one '''source plan''' is updated periodically, say, from week to week, and '''re-saved''' using the same '''source plan''' name (Project A) from the beginning to the project's end. This being the first example scenario, the figure above shows the single '''source plan''' from which three charts were created using different '''Flag''' fields, '''Flag20''' for executive views, '''Flag10''' for project team view, and '''Flag5''' for customer views.
 
 
Further, for the '''Flag20''' chart, there exist three '''snapshots''' taken from the '''source plan''' on '''June 1st''', '''July 1st''', and '''August 1st'''. Each '''snapshot''' represents the chart (under the control of '''Flag20''' in this case) at each of these three dates during the course of the project. The same dates or different dates are used to create '''snapshots''', in the example, for all three charts associated with Project A. This doesn’t need to be the case because '''snapshots''' can be taken at any time for any '''Flag''' field available and OnePager remembers them, makes them available for subsequent viewing, and allows updates as needed.
 
 
A chart is a set of task bars and milestone symbols for an intended audience. Usually a chart is associated with a specific '''Flag''' or '''Number''' field in a specifically named '''source plan'''. The chart also '''saves''' the '''task bar names, task bar label positions, and row and swimlane assignments, plus the title, legend, header/footer elements, and background colors'''.  This means you never have to re-enter this graphical information when dates change. Making and updating charts is the primary activity that OnePager users do!
 
 
A '''snapshot''' is a how the task bars and milestone symbols in a chart look as task bars and milestone symbols on a specific '''snapshot date''' (a.k.a. '''status date''' or '''version date'''). When you '''import''' updated schedules from a  '''source plan''', you must specify a unique '''snapshot date''' for the '''imported''' data unless you want to replace the data for an existing '''snapshot'''. What changes '''snapshot''' to '''snapshot''' depends on what changed in the '''source plan'''.  Typically '''snapshots''' vary because of changes to '''start''' and '''finish dates''', '''baseline start''' and '''finish dates''', '''percent complete''' and '''milestone completions'''.
 
 
===Using Multiple Source Plans throughout a Project Period===
 
 
Another typical project schedule '''source plan''' management scenario is to create a '''source plan''' at the beginning of a project and '''save''' the updated '''source plan''' with a unique '''source plan name''' after each update/status recording period. Under this scenario, charts and '''snapshots''' can still be created and maintained as with the first scenario above.
 
 
The following steps correspond with the example in the figure below:
 
 
:1) Create the '''source plan''' named '''Project A-June 1st''' with populated '''Flag''' fields '''Flag20''', '''Flag10''' and '''Flag5''' and '''save''' it.
 
 
:2) Launch OnePager using each of the '''Flag''' fields to control the task selection and ''''save''' the corresponding charts. In the first launch on '''June 1st''', the '''snapshot dates''' is set to '''June 1st'''.
 
 
:3) On the next update of the '''source plan''', save the update '''source plan''' as '''Project A-July 20th'''.
 
 
:4) Launch OnePager in '''UPDATE existing Chart''' mode selecting the appropriate chart name. Set the '''snapshot date''' for the date of the snapshot (e.g., '''July 20th''') and create the '''snapshot'''.
 
 
:5) OnePager stores the '''snapshot''' for '''July 20th''' with the named chart.
 
 
:6) Repeat this process for each of the two remaining '''Flag''' field instances.
 
 
After three iterations, there are three charts and nine synchronized '''snapshots''' available for use in presentations. There are three corresponding '''source plans''' for the status dates, 6/1/2018 through 8/2/2018.
 
 
<!--<center>[[File:P70-4_0_1_1-(2)-04292020.png]]</center>-->
 
<!--<center>P70-4_0_1_1-(2)-04292020.png</center>-->
 
<center>[[File:P71-4_0_1_1-71-(2-1)-11012021.png]]</center>
 
<center>P71-4_0_1_1-71-(2-1)-11012021.png</center>
 
 
 
==Related Links==
 
 
[[Basic Workflows for Version 7.1 (Portal) | Basic Workflows (Portal)]] 7.0.1-71
 
 
[[Creating Various Multi-Project Charts with OnePager Pro and Express for Version 7.1 (Portal) | Creating Various Multi-Project Charts with OnePager Pro and Express (Portal)]] 8.0.1-71
 
 
(4.0.1.1-71)
 

Revision as of 14:53, 23 November 2021