=Placeholder for Task/Milestone Link Tab for OnePager Express - 21.12.2-61=
+
This tab controls the '''global editing''' of '''data-driven''' and manual '''Task Links''' in the project view. The tab is shown below:
  
This tab controls the '''font''' characteristics of links. The tab is shown below:
+
<center>[[File:X61-0_4_1_7-61-(4)-08072018.png]]</center>
 +
<center>X61-0_4_1_7-61-(4)-08072018</center>
  
<center>[[File:P60-21_1_12-60-(1)-02212017.png]]</center>
+
The control groups and individual settings in the '''PVP''' form's '''Task Links''' tab are described in detail at: [[Editing Task Links with the Project-View Properties Form for OnePager Express for Version 6.1 | Editing Task Links with the Project-View Properties Form for OnePager Express]] 19.3.2-61
<!--<center>P60-21_1_12-60-(1)-02212017.png</center>-->
+
 
+
1) '''Font'''. This one control in the '''Event Links''' tab of the Project-View Properties ('''PVP''') form provides access to the standard '''Font properties''' form. 
+
 
+
2) The '''Font properties''' form, shown below, allows you to change the '''font type, size''' and other related properties of the '''event link text''':
+
 
+
<center>[[File:P53-21_1_12-53-(2)-05062016.png]]</center>
+
 
+
3) This tab does not provide any controls for changing the properties of the '''link connector line''' itself. To do this you must right click the link in the project view and select the '''Properties...''' command from the '''context menu'''.  Doing this will bring up the '''Specify Event Links''' form shown below:
+
 
+
<center>[[File:P53-21_1_12-53-(3)-05062016.png]]</center>
+
  
 
==Related Link==
 
==Related Link==

Revision as of 17:58, 30 August 2018

This tab controls the global editing of data-driven and manual Task Links in the project view. The tab is shown below:

X61-0 4 1 7-61-(4)-08072018.png
X61-0_4_1_7-61-(4)-08072018

The control groups and individual settings in the PVP form's Task Links tab are described in detail at: Editing Task Links with the Project-View Properties Form for OnePager Express 19.3.2-61