Difference between revisions of "Testing Article1"

From OnePager Documentation
Jump to: navigation, search
(Results from Installing OnePager Pro and/or OnePager Express with OnePager Bundle)
Line 1: Line 1:
==Introduction==
+
==Creating and Managing Summary Tasks in Oracle Primavera P6 for Version 7.1==
  
Most OnePager users install either OnePager Pro and/or OnePager Express into a '''user account''' for use with Microsoft Project or Microsoft Excel, respectively.  OnePager Pro and Express operate in two modes: (1) The '''Add-in''' mode where OnePager is launched from “inside” Microsoft Project or Microsoft Excel, or (2) The '''Standalone''' mode where either OnePager Pro or OnePager Express is launched from a '''desktop icon''', the '''Windows task-bar''', or '''Start-Menu shortcuts'''.
+
OnePager supports the representation of '''Project Summary Tasks''' for Oracle Primavera P6 '''source plans''' by providing a '''virtual task''' which spans the duration and computes the percent complete for the entire project. These '''Project Summary Tasks''' can be found by looking at a OnePager field called '''Project Summary''', which will be set to '''True/Yes''' for any tasks that summarize at the project level.
  
Our new OnePager Bundle offers capabilities of OnePager Pro and OnePager Express in both the '''Add-in''' and '''Standalone '''modes.  With the capabilities of OnePager Bundle installed in a '''user account''' there is generally no need to have OnePager Pro and/or OnePager Express also installed in the same '''user account'''.  Our recommendation to OnePager Bundle users, therefore, is to avoid having OnePager Pro and/or OnePager Express installed in the same '''user account''' along with OnePager Bundle.
+
If the '''Outline Level''' for an '''imported activity '''is equal to zero (0), the corresponding '''Project Summary '''value is set to '''True/Yes''' indicating that the '''imported activity''' is a '''Project Summary '''type '''activity'''.  If the '''Outline Level '''for an '''imported activity''' is greater than zero (0), the corresponding '''Project Summary '''value is set to '''False/No''', meaning that the activity is either a lower-level summary task, or simply an individual activity.
  
There are, however, possible situation where a '''user account''' needs to retain OnePager Pro and/or OnePager Express but also needs the capabilities of OnePager BundleFor example, suppose the '''user account''' is operating with an '''older version''' of OnePager Pro and/or OnePager Express but needs the latest editions of OnePager products available in OnePager Bundle.  It is possible to operate within a '''user account''' with all three OnePager products if steps are taken to manage which of the products are '''enabled''' in the '''Add-in '''mode.
+
The '''Project Summary '''field is also available to use when making '''task selections''' when creating a '''NEW''' chart or when performing an '''UPDATE''' of an existing chartUsed this way, the '''Project Summary '''field can be used to control the '''import '''of just '''Outline Level zero (0) activity''' or '''activities''' whose '''Outline Level '''is greater than '''zero (0)'''.
  
This article explains how to manage the '''Add-in''' modes of OnePager Pro, OnePager Express, and OnePager Bundle within the same '''user account'''.
+
This sub-section provides an example of how the '''Project Summary '''field in OnePager can be used to create and manage OnePager charts that represent the highest summary level for multi-project '''source plans''' managed by Oracle Primavera P6.
  
==Installing OnePager Bundle in a User Account with OnePager Pro and/or OnePager Express==
+
===Multi-Project Oracle Primavera P6 Example ===
  
Suppose a '''user account''' has both OnePager Pro and OnePager Express installed in both the '''Add-in''' and '''Standalone '''modes and the need exists to install OnePager Bundle in this same '''user account'''.  This can be done by simply following the installation process for OnePager Bundle as directed by the normal installation process for OnePager products.
+
Consider the Oracle Primavera P6 '''source plan '''shown below as a '''multi-project source plan''' which is used as the example '''source plan''' in this article:
  
For more detailed information on '''installing''' OnePager Bundle, please see the article at:  [[Installing and Activating OnePager Bundle for Version 7.1 (Portal) | Installing and Activating OnePager Bundle (Portal)]] 2.0.3-71.
+
<center>[[File:P71-8_5_2-71-(21)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(21)-03082022.png</center>
  
===Installation Process for OnePager Bundle===
+
The illustration shown above is a '''multi-project source plan''' made up of '''Project A '''and '''Project B '''each with '''multiple phases''' and '''activities'''.  Creating a detailed OnePager chart from this '''source plan''' is described elsewhere.  For our purpose here, the requirement is to create a chart that has a '''task bar '''for each of the two projects represented above.
  
During the OnePager Bundle installation process you are asked to '''enable''' OnePager Bundle as an '''Add-in''' by clicking the '''Launch from my desktop or from MS Project/Excel '''radio button on the '''Installation options''' form shown below:
+
===Selecting Activities to Represent Project Summaries===
  
<center>[[File:P71-2_0_4-71-(1)-02162022.png]]</center>
+
Creating a '''NEW''' chart in OnePager requires launching OnePager Bundle '''Standalone''' from your desktop and selecting the '''NEW '''option from the '''OnePager Bundle Start''' form shown below:''' '''
<center>P71-2_0_4-71-(1)-02162022.png</center>
+
  
===Results from Installing OnePager Bundle with OnePager Pro and/or Express===
+
<center>[[File:P71-8_5_2-71-(22)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(22)-03082022.png</center>
  
Making the selection to launch OnePager Bundle in both the '''Add-in''' and '''Standalone '''modes as shown above produces the following results:
+
Clicking the '''NEW''' button accesses the abbreviated '''OnePager choices '''form where you select the '''source plan '''for '''import''' to OnePager and other selections and options as discussed further below.  The abbreviated '''OnePager choices''' form is shown below:
  
:1) OnePager Bundle '''disables '''OnePager Pro and/or OnePager Express as '''Add-ins''' to Microsoft Project and/or Microsoft Excel.
+
<center>[[File:P71-8_5_2-71-(23)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(23)-03082022.png</center>
  
:2) OnePager Bundle '''enables '''itself as an '''Add-in option''' to both Microsoft Project and/or Microsoft Excel.
+
====Selecting the Oracle Primavera P6 Source Plan====
  
:3) OnePager Pro, OnePager Express, and OnePager Bundle remain '''enabled''' and available to be individually launched in '''Standalone''' mode and the '''desktop icons, task-bar''', and '''Start-Menu shortcuts''' are all available for use.
+
Going forward and selecting the Oracle Primavera P6 '''multi-project source plan''' using the '''Select…''' button shown above, expands the '''OnePager Choices '''form to look like this:
  
:4) Using the '''double-left-click''' method on a '''.TAM''' or '''.TAT''' file launches OnePager Bundle in the '''Standalone '''mode since the OnePager Bundle product is the last product installed.
+
<center>[[File:P71-8_5_2-71-(24)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(24)-03082022.png</center>
  
:5) If you select the '''Launch from my desktop only''' option in the '''Installation options''' form shown above, OnePager Pro and/or OnePager Express are '''NOT disabled''' and remain available in '''Add-in '''mode for future use.  In other words, the actions described in items 1) and 2) above are '''NOT''' taken by OnePager Bundle.
+
====Selecting the Multi-Project Template Properties Form====
  
The resulting configuration of the '''user account''' based upon the actions taken in items 1) through 3) above are that OnePager Bundle is available in the '''Add-in '''and '''Standalone '''modes and OnePager Pro and/or OnePager Express is available '''only''' in the '''Standalone '''mode.
+
As shown above, we need to access a '''multi-project Template Properties''' form since our intent is to produce a '''multi-project Summary '''chart.  To do this, click on the '''Change… '''button in the '''Starting Template '''sub-control group which accesses a list of '''Template Properties '''form as shown below:
  
The '''Add-in''' tabs for OnePager Pro and OnePager Express are available when you launch Microsoft Project and/or Microsoft Excel but clicking the '''Add-in '''tab from either Microsoft Project or Microsoft Excel launches OnePager Bundle. Launching OnePager Pro or OnePager Express from their respective '''desktop icons''' launches OnePager Pro and/or OnePager Express in their '''Standalone '''modes.
+
<center>[[File:P71-8_5_2-71-(25)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(25)-03082022.png</center>
  
===Re-Enabling OnePager Pro and/or Express in Add-in Mode===
+
====Naming the Multi-Project Chart====
  
If required in the future, it is possible to '''enable''' OnePager Pro and/or Express in the '''Add-in '''mode as long as you '''disable '''OnePager Bundle in the '''Add-in '''mode in Microsoft Project and/or Microsoft Excel. 
+
Upon completing the '''Template Properties''' form selection, continue on and enter the chart’s '''title''' in the '''Title of New Chart '''sub-control group’s text window.  When that is done, the '''OnePager choices '''form looks like this:
  
Doing this requires that you access the '''COM Add-ins''' form for Microsoft Project and/or Microsoft Excel, '''disable''' OnePager Pro and/or OnePager Express, and assure that OnePager Bundle is '''enabled'''.
+
<center>[[File:P71-8_5_2-71-(26)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(26)-03082022.png</center>
  
For information on '''disabling''' and '''re-enabling '''OnePager Pro and OnePager Express, please see the article sections given in the table below:
+
====Selecting Project Summary Tasks Using the Project Summary Field====
  
<center>
+
At this point you are ready to make '''task selections''' using the one of the three options in the '''Task Selection '''sub-control group. The easiest way to do this is to click the '''Select task with ‘YES’ in field:''' radio button and click in the window to access the '''dropdown list''' as shown here:
{| class="wikitable"
+
| [[Temporarily Disabling & Re-enabling OnePager for Version 7.1#About Temporarily Disabling & Re-Enabling OnePager Pro for Microsoft Project | Temporarily Disabling & Re-Enabling OnePager Pro for Microsoft Project]] 1.5.2-71
+
|-
+
| [[Temporarily Disabling & Re-enabling OnePager for Version 7.1#About Temporarily Disabling & Re-Enabling OnePager Express for Microsoft Excel | Temporarily Disabling & Re-Enabling OnePager Express for Microsoft Excel]] 1.5.2-71
+
|}
+
</center>
+
  
The following sub-sections demonstrate how to '''re-enable '''OnePager Pro and OnePager Express in '''Add-in '''mode.
+
<center>[[File:P71-8_5_2-71-(27)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(27)-03082022.png</center>
  
===Re-Enabling OnePager Pro Example for Microsoft Project’s Add-in Mode===
+
====Creating the Chart====
  
As an example, suppose that you need to '''enable '''OnePager Pro in '''Add-in '''mode and must '''disable''' OnePager Bundle from '''Add-in '''modeAt the start of this procedure the '''COM Add-ins '''form for Microsoft Project looks like this:
+
Once you’ve selected the '''Project Summary '''option, you may change the snapshot date, if desired, and go ahead and click the '''Create new chart''' buttonWhen this button is clicked, OnePager creates the '''multi-project '''chart that looks like this:
  
<center>[[File:P71-2_0_4-71-(2)-02162022.png]]</center>
+
<center>[[File:P71-8_5_2-71-(28-1)-03092022.png]]</center>
<center>P71-2_0_4-71-(2)-02162022.png</center>
+
<center>P71-8_5_2-71-(28-1)-03092022.png</center>
  
To '''enable '''OnePager Pro, check the OnePager Pro V7.1.2 checkbox '''ON''' and uncheck the OnePager Bundle V7.1.2 checkbox '''OFF''' so that it looks like this:
+
In the chart shown above, created from an '''XML formatted import '''from Oracle Primavera P6, OnePager has used the '''Project Summary '''field to create a task bar shape that covers the '''start''' to '''finish dates''' for '''Project A''' and '''Project B'''. OnePager also made the color selections based on the different project names. Additionally, using the '''XML formatted import’s''' data, OnePager calculated the '''Percent Complete''' value for each project.
  
<center>[[File:P71-2_0_4-71-(3)-02162022.png]]</center>
+
To see this information in text form, adding '''text columns''' for '''Start Date''', '''Finish Date, Percent Complete''', provides visual conformation of this information in the chart as shown below:
<center>P71-2_0_4-71-(3)-02162022.png</center>
+
  
It is important that only one of the OnePager entries be '''enabled''' as '''enabling''' both entries my produce unexpected results.
+
<center>[[File:P71-8_5_2-71-(29-1)-03092022.png]]</center>
 +
<center>P71-8_5_2-71-(29-1)-03092022.png</center>
  
===Re-Enabling OnePager Express Example for Microsoft Excel’s Add-in Mode===
+
====Alternative Method for Selecting Project Summary Tasks====
  
For another example, suppose you need to '''enable '''OnePager Express in '''Add-in '''mode and must '''disable''' OnePager Bundle from '''Add-in '''mode.  At the start of this procedure the '''COM Add-ins '''form for Microsoft Excel looks like this:
+
As an alternative means of selecting '''Project''' '''Summary Tasks''' for display in your OnePager chart, you can use the '''Conditional Import Rules '''feature.  This can be done by using the '''Select task by custom filter''' radio button to access the '''Conditional Import Rules''' form as shown below:
  
<center>[[File:P71-2_0_4-71-(4)-02162022.png]]</center>
 
<center>P71-2_0_4-71-(4)-02162022.png</center>
 
  
To '''enable '''OnePager Express, check the OnePager Express V7.1.2 checkbox '''ON''' and uncheck the OnePager Bundle V7.1.2 checkbox '''OFF''' so that it looks like this:
+
<center>[[File:P71-8_5_2-71-(30)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(30)-03082022.png</center>
  
<center>[[File:P71-2_0_4-71-(5)-02162022.png]]</center>
+
Using the '''Conditional Import Rules''' form, create a rule using the '''Project Summary '''field in the '''Field '''column of the form and '''True/Yes''' in the '''Operator '''field as shown below:
<center>P71-2_0_4-71-(5)-02162022.png</center>
+
  
It is important that only one of the OnePager entries be '''enabled''' as '''enabling''' both entries my produce unexpected results.
+
<center>[[File:P71-8_5_2-71-(31)-03082022.png]]</center>
 +
<center>P71-8_5_2-71-(31)-03082022.png</center>
  
===Launching OnePager from Microsoft Project with OnePager Bundle in Add-in Mode===
+
Clicking the '''OK '''button on the '''Conditional Import Rules '''form and the '''Create new chart''' on the '''OnePager choices''' form creates the same chart as shown above.
  
Assuming that the configuration is such that OnePager Bundle is in '''Add-in '''mode, meaning that OnePager Pro can only be launched in '''Standalone '''mode, the sequence for using the '''Add-in '''tab on Microsoft Project, for example, looks like the following sequence:
+
For more detailed information on '''conditional import rules''', please see the article at: [[Conditional Import for Version 7.1 (Portal) | Conditional Import Filters (Portal)]] 7.18.1-71.
 
+
:1) Launching Microsoft Project and navigating to the '''ADD-INS''' tab looks like this:
+
 
+
<center>[[File:P71-2_0_4-71-(6)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(6)-02162022.png</center>
+
 
+
:2) Clicking the '''OnePager Bundle''' button launches OnePager Bundle as shown below:
+
 
+
<center>[[File:P71-2_0_4-71-(7)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(7)-02162022.png</center>
+
 
+
:3) OnePager Bundle is now available to use to create a '''NEW''' chart, '''UPDATE''' an existing chart, or '''OPEN''' an existing chart.
+
 
+
===Launching OnePager from Microsoft Excel with OnePager Bundle in Add-in Mode===
+
 
+
For Microsoft Excel, assume the configuration is such that OnePager Bundle is in '''Add-in '''mode, meaning that OnePager Express can only be launched in '''Standalone '''mode, the sequence for using the '''Add-in '''tab on Microsoft Excel, for example, looks like the following sequence:
+
 
+
:1) Launching Microsoft Excel and navigating to the '''Add-ins''' tab looks like this:
+
 
+
<center>[[File:P71-2_0_4-71-(8)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(8)-02162022.png</center>
+
 
+
:2) Clicking the '''OnePager Bundle''' button launches OnePager Bundle as shown below:
+
 
+
<center>[[File:P71-2_0_4-71-(9)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(9)-02162022.png</center>
+
 
+
:3) OnePager Bundle is now available to use to create a '''NEW''' chart, '''UPDATE''' an existing chart, or '''OPEN''' an existing chart
+
 
+
==Installing OnePager Pro and/or OnePager Express in a User Account with OnePager Bundle==
+
 
+
Suppose a '''user account''' has OnePager Bundle installed in the both the '''Add-in''' and '''Standalone '''mode and the need exists to install OnePager Pro and/or OnePager Express in this same '''user account'''.  This can be done by simply following the installation processes for OnePager Pro and/or OnePager Express as directed by the normal installation process for OnePager products.
+
 
+
For more detailed information on installing OnePager Pro and OnePager Express, please see the articles at:
+
 
+
<center>
+
{| class="wikitable"
+
| [[Installing and Activating OnePager Pro for Version 7.1 (Portal) | Installing and Activating OnePager Pro (Portal)]] 1.0.1-71
+
|-
+
| [[Installing and Activating OnePager Express for Version 7.1 (Portal) | Installing and Activating OnePager Express (Portal)]] 2.0.2-71
+
|}
+
</center>
+
 
+
===Installation Process for OnePager Pro - Example===
+
 
+
During the OnePager Pro installation process you are asked to '''enable''' OnePager Pro as an '''Add-in''' by clicking the '''Launch from my desktop or from Microsoft Project''' radio button on the '''Installation options''' form shown below:
+
 
+
<center>[[File:P71-2_0_4-71-(10)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(10)-02162022.png</center>
+
 
+
===Results from Installing OnePager Pro and/or OnePager Express with OnePager Bundle===
+
 
+
Making the selection to launch OnePager Pro and/or OnePager Express in both the '''Add-in''' and '''Standalone '''modes as shown above produces the following results:
+
 
+
:1) OnePager Pro and/or OnePager Express '''disables '''OnePager Bundle as '''Add-ins''' to Microsoft Project and/or Microsoft Excel.
+
 
+
:2) OnePager Pro and/or OnePager Express '''enables '''themselves as '''Add-in options''' to both Microsoft Project and/or Microsoft Excel.
+
 
+
:3) OnePager Pro, OnePager Express, and OnePager Bundle remain '''enabled''' and available to be individually launched in '''Standalone''' mode and the '''desktop icons, task-bar''', and '''Start-Menu shortcuts''' are all available for use.
+
 
+
:4) Using the '''double-left-click''' method on a '''.TAM''' or '''.TAT''' file launches OnePager Pro or OnePager Express in the '''Standalone '''mode since these products are the last product installed.
+
 
+
:5) If you select the '''Launch from my desktop only''' option in the '''Installation options''' shown above, OnePager Pro and/or OnePager Express are '''NOT disabled''' and remain available in '''Add-in '''mode for future use.  In other words, the actions described in items 1) and 2) above are not taken by OnePager Pro and/or OnePager Express.
+
 
+
The resulting configuration of the '''user account''' based upon the actions taken in items 1) through 3) above are that OnePager Pro and/or OnePager Express are available in the '''Add-in '''and '''Standalone '''modes and OnePager Bundle is available only in the '''Standalone '''mode.
+
 
+
The '''Add-in''' tabs for OnePager Pro and OnePager Express are available when you launch Microsoft Project and/or Microsoft Excel and clicking the '''Add-in '''tab from either Microsoft Project or Microsoft Excel launches OnePager Pro or OnePager Express respectively.  Launching OnePager Pro or OnePager Express from their respective '''desktop icons''' launches OnePager Pro and/or OnePager Express in their '''Standalone '''modes.
+
 
+
===Re-Enabling OnePager Bundle in Add-in Mode===
+
 
+
If required in the future, it is possible to '''enable''' Bundle in the '''Add-in '''mode as long as you '''disable '''OnePager Pro and/or OnePager Express in the '''Add-in '''mode for Microsoft Project and/or Microsoft Excel. 
+
 
+
Doing this requires that you access the '''COM Add-ins''' form for Microsoft Project and/or Microsoft Excel, '''disable''' OnePager Pro and/or OnePager Express, and assure that OnePager Bundle is '''enabled'''.
+
 
+
For information on '''disabling''' and '''re-enabling '''OnePager Pro and OnePager Express, please see the article sections given in the table below:
+
 
+
<center>
+
{| class="wikitable"
+
| [[Temporarily Disabling & Re-enabling OnePager for Version 7.1#About Temporarily Disabling & Re-Enabling OnePager Pro for Microsoft Project | Temporarily Disabling & Re-Enabling OnePager Pro for Microsoft Project]] 1.5.2-71
+
|-
+
| [[Temporarily Disabling & Re-enabling OnePager for Version 7.1#About Temporarily Disabling & Re-Enabling OnePager Express for Microsoft Excel | Temporarily Disabling & Re-Enabling OnePager Express for Microsoft Excel]] 1.5.2-71
+
|}
+
</center>
+
 
+
===Re-Enabling OnePager Bundle Example for Microsoft Project’s Add-in Mode===
+
 
+
As an example, suppose that you need to '''enable '''OnePager Bundle in '''Add-in '''mode and must '''disable''' OnePager Pro from '''Add-in '''mode.  At the start of this procedure the '''COM Add-ins '''form for Microsoft Project looks like this:
+
 
+
<center>[[File:P71-2_0_4-71-(11)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(11)-02162022.png</center>
+
 
+
To '''enable '''OnePager Bundle, check the OnePager BundleV7.1.2 checkbox '''ON''' and uncheck the OnePager Pro V7.1.2 checkbox '''OFF''' so that it looks like this:
+
 
+
<center>[[File:P71-2_0_4-71-(12)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(12)-02162022.png</center>
+
 
+
It is important that only one of the OnePager entries be '''enabled''' as '''enabling''' both entries my produce unexpected results.
+
 
+
===Re-Enabling OnePager Bundle Example for Microsoft Excel’s Add-in Mode===
+
 
+
For another example, suppose you need to '''enable '''OnePager Bundle in '''Add-in '''mode and must '''disable''' OnePager Express from '''Add-in '''mode.  At the start of this procedure the '''COM Add-ins '''form for Microsoft Excel looks like this:
+
 
+
<center>[[File:P71-2_0_4-71-(13)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(13)-02162022.png</center>
+
 
+
 
+
To '''enable '''OnePager Bundle check the OnePager Pro V7.1.2 checkbox '''ON''' and uncheck the OnePager Express V7.1.2 checkbox '''OFF''' so that it looks like this:
+
 
+
<center>[[File:P71-2_0_4-71-(14)-02162022.png]]</center>
+
<center>P71-2_0_4-71-(14)-02162022.png</center>
+
 
+
It is important that only one of the OnePager entries be '''enabled''' as '''enabling''' both entries my produce unexpected results.
+
 
+
==Un-Installing OnePager Bundle in a User Account with OnePager Pro and/or OnePager Express==
+
 
+
'''Un-installing''' OnePager Bundle in a '''user account''' is accomplished in the same way as '''un-installing''' most other Windows applications.  However, in this case OnePager Pro and/or OnePager Express are also '''installed''' in the '''user account''' as shown below:
+
 
+
<center>[[File:P71-2_0_4-71-(15)-02282022.png]]</center>
+
<center>P71-2_0_4-71-(15)-02282022.png</center>
+
 
+
As shown in the illustration above, OnePager Bundle is installed with OnePager Pro and OnePager Express.  To '''un-install''' OnePager Bundle where OnePager Bundle is in '''Add-in''' mode and OnePager Pro and OnePager Express, are both in the Standalone mode, select OnePager Bundle in the above form and click the '''Uninstall''' button.  This action '''un-installs''' OnePager Bundle in the '''Add-in '''and '''Standalone '''modes and the '''Program and Features''' form looks like this:
+
 
+
<center>[[File:P71-2_0_4-71-(15A)-02282022.png]]</center>
+
<center>P71-2_0_4-71-(15A)-02282022.png</center>
+
 
+
As a result, OnePager Pro and/or OnePager Express are '''un-attached''' from their respective OnePager products after the operation complete.  Additionally, the OnePager Bundle entry in the '''COM Add-Ins '''forms for OnePager Pro and/or OnePager Express is '''removed''' as shown here:
+
 
+
 
+
<center>'''COM Add-Ins Form for Microsoft Project'''</center>
+
<center>[[File:P71-2_0_4-71-(16)-02282022.png]]</center>
+
<center>P71-2_0_4-71-(16)-02282022.png</center>
+
 
+
<center>'''COM Add-Ins Form for Microsoft Excel'''</center>
+
<center>[[File:P71-2_0_4-71-(17)-02282022.png]]</center>
+
<center>P71-2_0_4-71-(17)-02282022.png</center>
+
 
+
To '''restore''' OnePager Pro and/or OnePager Express in both the '''Add-in '''and '''Standalone '''modes, check the respective OnePager Pro and/or OnePager Express V7.1.2 checkboxes '''ON''' and click the '''OK '''buttons on the respective '''COM Add-ins '''forms.
+
 
+
==Un-Installing OnePager Pro and/or OnePager Express in a User Account with OnePager Bundle==
+
 
+
Where a '''user account''' has OnePager Pro, OnePager Express, and OnePager Bundle '''installed''' with OnePager Pro and/or OnePager Express '''installed '''in the '''Add-in''' mode, it is possible to un-install either OnePager Pro or OnePager Express, retain both in the '''Standalone '''mode and OnePager Bundle in the '''Add-in '''mode.
+
 
+
In this configuration, to '''un-install''' either OnePager Pro and/or OnePager Express, follow the procedures described in the article links below:
+
 
+
<center>
+
{| class="wikitable"
+
| [[Uninstalling OnePager (Version 7.1)#Uninstalling OnePager Pro | Uninstalling OnePager Pro]] 1.4.2-71
+
|-
+
| [[Uninstalling OnePager (Version 7.1)#Uninstalling OnePager Express | Uninstalling OnePager Express]] 1.4.2-71
+
|}
+
</center>
+
 
+
When both OnePager Pro and OnePager Express are '''un-installed''' OnePager Bundle remains the only entry in the Microsoft Project and/or Microsoft Express '''COM Add-ins '''forms.  However, under this scenario, it is necessary for you to '''enable''' OnePager Bundle in both Microsoft Project and/or Microsoft Excel in order to get the Microsoft Project and/or Microsoft Excel '''ADD-INS '''tab to show on the respective tool bar ribbons.
+
  
 
==Related Links==
 
==Related Links==
  
[[Installing and Activating OnePager Pro for Version 7.1 (Portal) | Installing and Activating OnePager Pro (Portal)]] 1.0.1-71
+
[[Using Oracle Primavera P6 Source Plans with OnePager Version 7.1 | Using Oracle Primavera P6 Source Plans with OnePager]] 3.0.3.1-71
 
+
[[Uninstalling OnePager (Version 7.1)#Uninstalling OnePager Pro | Uninstalling OnePager Pro]] 1.4.2-71
+
 
+
[[Uninstalling OnePager (Version 7.1)#Uninstalling OnePager Express | Uninstalling OnePager Express]] 1.4.2-71
+
 
+
[[Temporarily Disabling & Re-enabling OnePager for Version 7.1#About Temporarily Disabling & Re-Enabling OnePager Pro for Microsoft Project | Temporarily Disabling & Re-Enabling OnePager Pro for Microsoft Project]] 1.5.2-71
+
  
[[Temporarily Disabling & Re-enabling OnePager for Version 7.1#About Temporarily Disabling & Re-Enabling OnePager Express for Microsoft Excel | Temporarily Disabling & Re-Enabling OnePager Express for Microsoft Excel]] 1.5.2-71
+
[[Basic Workflows for Version 7.1 (Portal) | Basic Workflows (Portal)]] 7.0.1-71
  
[[Installing and Activating OnePager Express for Version 7.1 (Portal) | Installing and Activating OnePager Express (Portal)]] 2.0.2-71
+
[[Conditional Import for Version 7.1 (Portal) | Conditional Import Filters (Portal)]] 7.18.1-71
  
[[Installing and Activating OnePager Bundle for Version 7.1 (Portal) | Installing and Activating OnePager Bundle (Portal)]] 2.0.3-71
+
[[Creating Various Multi-Project Charts with OnePager for Version 7.1 (Portal) | Creating Various Multi-Project Charts with OnePager (Portal)]] 8.0.1-71
  
(2.0.4-71)
+
[[Managing Templates for Version 7.1 (Portal) | Managing Templates (Portal)]] 24.0.1-71
  
[[Category:Version 7.1]]
+
(8.5.2-71+)
[[Category:Installation]]
+
[[Category:Add-in]]
+
[[Category:Standalone]]
+
[[Category:OnePager Pro]]
+
[[Category:OnePager Express]]
+
[[Category:OnePager Bundle]]
+

Revision as of 16:25, 11 March 2022

Creating and Managing Summary Tasks in Oracle Primavera P6 for Version 7.1

OnePager supports the representation of Project Summary Tasks for Oracle Primavera P6 source plans by providing a virtual task which spans the duration and computes the percent complete for the entire project. These Project Summary Tasks can be found by looking at a OnePager field called Project Summary, which will be set to True/Yes for any tasks that summarize at the project level.

If the Outline Level for an imported activity is equal to zero (0), the corresponding Project Summary value is set to True/Yes indicating that the imported activity is a Project Summary type activity. If the Outline Level for an imported activity is greater than zero (0), the corresponding Project Summary value is set to False/No, meaning that the activity is either a lower-level summary task, or simply an individual activity.

The Project Summary field is also available to use when making task selections when creating a NEW chart or when performing an UPDATE of an existing chart. Used this way, the Project Summary field can be used to control the import of just Outline Level zero (0) activity or activities whose Outline Level is greater than zero (0).

This sub-section provides an example of how the Project Summary field in OnePager can be used to create and manage OnePager charts that represent the highest summary level for multi-project source plans managed by Oracle Primavera P6.

Multi-Project Oracle Primavera P6 Example

Consider the Oracle Primavera P6 source plan shown below as a multi-project source plan which is used as the example source plan in this article:

P71-8 5 2-71-(21)-03082022.png
P71-8_5_2-71-(21)-03082022.png

The illustration shown above is a multi-project source plan made up of Project A and Project B each with multiple phases and activities. Creating a detailed OnePager chart from this source plan is described elsewhere. For our purpose here, the requirement is to create a chart that has a task bar for each of the two projects represented above.

Selecting Activities to Represent Project Summaries

Creating a NEW chart in OnePager requires launching OnePager Bundle Standalone from your desktop and selecting the NEW option from the OnePager Bundle Start form shown below:

P71-8 5 2-71-(22)-03082022.png
P71-8_5_2-71-(22)-03082022.png

Clicking the NEW button accesses the abbreviated OnePager choices form where you select the source plan for import to OnePager and other selections and options as discussed further below. The abbreviated OnePager choices form is shown below:

P71-8 5 2-71-(23)-03082022.png
P71-8_5_2-71-(23)-03082022.png

Selecting the Oracle Primavera P6 Source Plan

Going forward and selecting the Oracle Primavera P6 multi-project source plan using the Select… button shown above, expands the OnePager Choices form to look like this:

P71-8 5 2-71-(24)-03082022.png
P71-8_5_2-71-(24)-03082022.png

Selecting the Multi-Project Template Properties Form

As shown above, we need to access a multi-project Template Properties form since our intent is to produce a multi-project Summary chart. To do this, click on the Change… button in the Starting Template sub-control group which accesses a list of Template Properties form as shown below:

P71-8 5 2-71-(25)-03082022.png
P71-8_5_2-71-(25)-03082022.png

Naming the Multi-Project Chart

Upon completing the Template Properties form selection, continue on and enter the chart’s title in the Title of New Chart sub-control group’s text window. When that is done, the OnePager choices form looks like this:

P71-8 5 2-71-(26)-03082022.png
P71-8_5_2-71-(26)-03082022.png

Selecting Project Summary Tasks Using the Project Summary Field

At this point you are ready to make task selections using the one of the three options in the Task Selection sub-control group. The easiest way to do this is to click the Select task with ‘YES’ in field: radio button and click in the window to access the dropdown list as shown here:

P71-8 5 2-71-(27)-03082022.png
P71-8_5_2-71-(27)-03082022.png

Creating the Chart

Once you’ve selected the Project Summary option, you may change the snapshot date, if desired, and go ahead and click the Create new chart button. When this button is clicked, OnePager creates the multi-project chart that looks like this:

P71-8 5 2-71-(28-1)-03092022.png
P71-8_5_2-71-(28-1)-03092022.png

In the chart shown above, created from an XML formatted import from Oracle Primavera P6, OnePager has used the Project Summary field to create a task bar shape that covers the start to finish dates for Project A and Project B. OnePager also made the color selections based on the different project names. Additionally, using the XML formatted import’s data, OnePager calculated the Percent Complete value for each project.

To see this information in text form, adding text columns for Start Date, Finish Date, Percent Complete, provides visual conformation of this information in the chart as shown below:

P71-8 5 2-71-(29-1)-03092022.png
P71-8_5_2-71-(29-1)-03092022.png

Alternative Method for Selecting Project Summary Tasks

As an alternative means of selecting Project Summary Tasks for display in your OnePager chart, you can use the Conditional Import Rules feature. This can be done by using the Select task by custom filter radio button to access the Conditional Import Rules form as shown below:


P71-8 5 2-71-(30)-03082022.png
P71-8_5_2-71-(30)-03082022.png

Using the Conditional Import Rules form, create a rule using the Project Summary field in the Field column of the form and True/Yes in the Operator field as shown below:

P71-8 5 2-71-(31)-03082022.png
P71-8_5_2-71-(31)-03082022.png

Clicking the OK button on the Conditional Import Rules form and the Create new chart on the OnePager choices form creates the same chart as shown above.

For more detailed information on conditional import rules, please see the article at: Conditional Import Filters (Portal) 7.18.1-71.

Related Links

Using Oracle Primavera P6 Source Plans with OnePager 3.0.3.1-71

Basic Workflows (Portal) 7.0.1-71

Conditional Import Filters (Portal) 7.18.1-71

Creating Various Multi-Project Charts with OnePager (Portal) 8.0.1-71

Managing Templates (Portal) 24.0.1-71

(8.5.2-71+)