==About Editing Baselines==
+
==About Editing Deadlines==
  
'''Baseline property''' displays are driven by the '''baseline start and finish dates''' imported from the Microsoft Excel '''source plan'''.  Not every task/milestone in a Microsoft Excel '''source plan''' has designated '''baseline start and finish dates'''.  A milestones’ '''start and finish dates''' are usually the same.  When you need to display '''baseline property''' information, it is essential that the associated data be properly represented in your Microsoft Project '''source plan''' before the data are '''imported''' to OnePager Pro ('''OPP''').
+
OnePager translates '''Deadlines''' from your Microsoft Project '''source plan''' into '''deadline''' shapes in the '''graph''' to indicate the '''deadline date''' for a task bar or milestone symbolTo illustrate with a simple example, consider the Microsoft Project '''source plan''' given below with three tasks containing '''Start and Finish dates''', a '''deadline date''', and the Microsoft Project '''Flag20''' field set to '''Yes''' so that OnePager '''imports''' the data for all three task bars:
  
==Editing All Task/Milestone Baseline Properties== 
+
<center>[[File:P70-10_9_1-(1)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(1)-09182019.png</center>-->
  
All task bar and milestone symbol '''baseline properties''' can be modified without changing the settings in the current '''Template Properties''' form by using these steps. Click the '''Chart Properties''' button on the OnePager '''Home''' ribbon tool bar tab in the '''Settings''' group. Next, navigate to either the '''Task Bars''' or '''Milestones''' tab as appropriate. Ensure that the '''Baseline shapes''' checkbox is checked '''ON''' as shown below:
+
When a simple chart is created from the '''source plan''' above and '''Deadlines''' are turned '''ON''', the example chart looks like this:
  
<center>[[File:X70-10_6_1-70-(1-1)-09222020.png]]</center>
+
<center>[[File:P70-10_9_1-(2)-06032020.png]]</center>
<!--<center>X70-10_6_1-70-(1-1)-09222020.png</center>-->
+
<!--<center>P70-10_9_1-70-(2)-09182019.png</center>-->
  
Once the '''Baseline shapes''' checkbox is checked '''ON''', '''baselines''' can be customized by clicking the '''Baseline Properties''' button which accesses the '''Set baseline properties''' form shown here:
+
When '''deadlines''' are turned '''ON''', they appear (by default) as '''red down-arrow shape''' in each task bar's row at the '''deadline date''' position with respect to the '''time axis'''. Above, '''deadline shapes''' that are not contained within their respective task bar are shown with '''back dash-dot connecting lines''' to illustrate the capability.
  
<center>[[File:X70-10_6_1-70-(2-1)-09222020.png]]</center>
+
==Editing All Deadline Properties==
<!--<center>X70-10_6_1-70-(2-1)-09222020.png</center>-->
+
  
You can now '''edit''' '''baseline properties''' for task bars/milestone symbols using the '''Set Baseline Properties''' form.
+
To display '''deadline dates''' in your charts you must first assure that the Microsoft Project '''source plan''' has its '''Deadline''' field populated with valid '''dates'''. When '''deadline dates''' are present in the '''source plan''' they must first be turned '''ON''' as the '''default setting''' in most distributed '''Template Properties''' form is for '''deadlines''' to be turned '''OFF'''. To do this, click the '''Chart Properties''' button on the OnePager '''Home''' ribbon tool bar tab to access the '''Chart Properties''' form. Next, navigate to the '''Chart Properties''' '''Task Bars''' tab and to the '''Task Bars Decoration''' control group. Check the '''Deadline markers''' checkbox '''ON''' to '''enable''' the '''Deadline Properties...''' button to the immediate right of the checkbox as shown below:
  
===Change Baseline Shape===
+
<center>[[File:P70-10_9_1-(3)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(3)-09182019.png</center>-->
  
The controls for changing the '''shape''' of the '''baseline''' are the same as for task bars/milestone symbols discussed in this article at:  [[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] <!--9.2.1-70-->
+
By default, '''deadlines''' are mapped to the '''Deadline date''' field in Microsoft Project.
  
The '''baseline''' shapes available are the same as for task bars/milestone symbols as shown in the '''Set baseline properties''' form below:
+
===Set Deadline Properties Form===
  
<center>[[File:X70-10_6_1-70-(3)-09172019.png]]</center>
+
To '''edit''' the format of all '''deadlines''', click the '''Deadline Properties...''' button, to access the '''Set deadline properties''' form shown below:
<!--<center>X70-10_6_1-70-(3)-09172019.png</center>-->
+
  
There are numerous '''baseline''' shapes that can be selected. Use the scroll bar on the right of the dropdown list to make your selection. When the selection is made, either continue to make additional properties changes or click the '''OK''' button to get back to the '''Chart Properties''' form where all '''edits''' are applied.
+
<center>[[File:P70-10_9_1-(4)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(4)-09182019.png</center>-->
  
===Change Baseline Fill Pattern===
+
The form above provides all the '''editing''' controls for '''all deadline shapes''' that can be displayed in the chart.
  
In a fashion very similar to the way '''fill patterns''' are changed for task bars/milestone symbols, once again access the '''Set baseline properties''' form as before, navigate to the '''Use custom fills''' checkbox, check it '''ON''' to '''enable''' the dropdown, and use the associated dropdown list to make your selection as shown below:
+
====Standard Basic Deadline Shape Controls====
  
<center>[[File:X70-10_6_1-70-(4)-09172019.png]]</center>
+
As stated previously, many of the controls in this group of the '''Set deadline properties''' form are standard.
<!--<center>X70-10_6_1-70-(4)-09172019.png</center>-->
+
  
When the selection is made, either continue to make additional properties changes or click the '''OK''' button to get back to the '''Chart Properties''' form where all changes can be applied.
+
The '''deadline shapes''' available are the same as '''Milestone symbols''' found in the '''Milestones''' tab of the '''Template Properties''' and '''Chart Properties''' forms. Likewise, the '''Fill patterns''' available are the same for task bars and milestone symbols also found on their respective tabs of the '''Template Properties''' and '''Chart Properties''' forms.  
  
===Change Baseline Height Percentage===
+
The '''Height percentage''' control represents the '''percentage''' of the total task bar/milestone symbol's '''height''' itself, is covered elsewhere and behaves in a standard way.  The default '''Height percentage''' is 100% meaning that the '''deadline shape''' is the same '''height''' as the task bar/milestone symbol.
  
This control, shown above, allows you to change the '''height''' of the '''baseline''' as a percentage of the total '''height''' of the parent task bar/milestone symbol  (task and baseline information included). The default setting is 30 percent (%) and a portion of the chart with '''baselines''' checked '''ON''' looks like this:
+
Similarly, the '''Transparency''' control for the '''deadline''' operates in the same way as '''transparency''' controls for other objects. The higher the value selected, the greater the '''transparency'''. Conversely, the low the value selected, the more solid the '''deadline shape''' appears.
  
<center>'''Baseline Shapes with 30 Percent Height Setting'''</center>
+
The '''Field''' dropdown in the upper right of the form allows you to select another Microsoft Project '''source plan date field''' instead of the default '''Deadline''' field typically used in Microsoft Project. Contents of the '''Field''' dropdown list is shown below:
<center>[[File:X70-10_6_1-70-(5)-09172019.png]]</center>
+
<!--<center>X70-10_6_1-70-(5)-09172019.png</center>-->
+
  
Increasing this value makes the '''baseline''' taller (higher) with respect to the task bar/milestone symbol. To change the value, navigate to the '''Height percentage''' control in the '''Specify how to display baseline properties''' group of the '''Set baseline properties''' form.  Change the value with the controls provided. If you double the value to 60 percent, for example, the resulting baselines would look like this:
+
<center>[[File:P70-10_9_1-(5)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(5)-09182019.png</center>-->
  
<center>'''Baseline Shapes with 60 Percent Height Setting'''</center>
+
The '''Position''' of the '''deadline''' has a unique meaning. '''Deadlines''' are always associated with a task bar/milestone symbol and can be to the left, within, or to the right of the task bar/milestone symbol itself depending on your Microsoft Project '''source plan''' data for the task bar’s '''start''', '''finish''' and '''deadline dates'''. The position in this context is about where within the task bar/milestone symbol’s row area vertically the '''deadline''' should be placed. There are three (3) available positions for the placement of the '''deadline shapes''' with respect to the task bar:
<center>[[File:X70-10_6_1-70-(5B)-09172019.png]]</center>
+
<!--<center>X70-10_6_1-70-(5B)-09172019.png</center>-->
+
  
===Change Baseline Transparency===
+
:* '''Centered''' in the task bar/milestone symbol.
 +
:* '''Above''' the task bar/milestone symbol.
 +
:* '''Below''' the task bar/milestone symbol
  
The '''transparency''' control makes the '''baseline less transparent''' (opaque) when the value in the window of the form is '''decreased''' or as shown below where the value is set at its default of 0% (the '''baseline''' is highlighted in orange):
+
The three available positions are shown here:
  
<center>[[File:X70-10_6_1-70-(5C)-09172019.png]]</center>
+
<center>[[File:P70-10_9_1-(6)-06032020.png]]</center>
<!--<center>X70-10_6_1-70-(5C)-09172019.png</center>-->
+
<!--<center>P70-10_9_1-70-(6)-09182019.png</center>-->
  
With this setting for '''transparency''' and '''baseline''' shape '''color''', the chart portion looks like this:
+
The '''Use custom color''' checkbox can be checked '''ON''' when it is desired to select a '''color''' for the '''deadline shape''' other than the '''color''' for its parent task bar/milestone symbol.  When the '''Use custom color''' checkbox is checked '''ON''', the standard '''Custom color''' dropdown is '''enabled. Clicking the dropdown button shows the standard '''Color Chooser''' form.
  
<center>[[File:X70-10_6_1-70-(6)-09172019.png]]</center>
+
====Showing Deadline Delays====
<!--<center>X70-10_6_1-70-(6)-09172019.png</center>-->
+
  
When you need to make the '''baseline more transparent''' '''increase''' the percentage value as shown below where the value is '''increased''' to 60%:
+
The purpose of the display of '''Deadline Delays''' is to provide you with the capability to highlight '''deadlines''' that are '''missed''' as shown in the chart. When the '''Color-code delays''' checkbox is checked '''On''', OnePager uses the selected '''Delay color''' (determined by the selection of the '''delay color''' from the standard '''Color Chooser''' form) to show all '''deadlines''' that are '''missed''':
  
<center>[[File:X70-10_6_1-70-(7)-09172019.png]]</center>
+
<center>[[File:P70-10_9_1-(7)-06032020.png]]</center>
<!--<center>X70-10_6_1-70-(7)-09172019.png</center>-->
+
<!--<center>P70-10_9_1-70-(7)-09182019.png</center>-->
  
With the '''transparency''' for the '''baseline''' set at 60%, the chart portion looks like this:
+
The '''deadline''' is set to the selected '''Delay color''' if, for any '''deadline shape''':  
  
<center>[[File:X70-10_6_1-70-(8)-09172019.png]]</center>
+
:* The '''Color-code delays''' checkbox is checked '''ON''',
<!--<center>X70-10_6_1-70-(8)-09172019.png</center>-->
+
:* The '''deadline date''' is '''earlier than the current snapshot date''',
 +
:*  And the '''percent (%) complete''' for the parent task bar/milestone symbolis less than 100%.
  
===Change Baseline Color===
+
If any of the conditions stated above are '''not met''', the '''color''' of the '''deadline''' is set to the '''default color''', unless a '''custom color''' is otherwise specified.
  
You can also make the '''baseline''' any '''color''' different from the parent task bar/milestone symbol as we did above.  To '''edit''' the '''color properties''' of the '''baseline''', go to the same '''Set baseline properties''' form as described above and check the '''Use custom color''' checkbox '''ON'''.  Then, click the dropdown to gain access to the '''Color Chooser''' form as shown below:
+
====Example Deadline Date Delay====
  
<center>[[File:X70-10_6_1-70-(9)-09172019.png]]</center>
+
To illustrate the operation of the '''Color-code delay''' feature, let's set the stage by supposing that a project of three task bar is has the following initial conditions:
<!--<center>X70-10_6_1-70-(9)-09172019.png</center>-->
+
  
Finally, select a desired '''color''', for example, orange as used above. When the '''color''' is selected, the '''Color Chooser''' form disappears and after clicking '''OK''' in the '''Set baseline properties''' form, the chart looks like this:
+
:* Project Start Date – 10/1/2020
 +
:* Project Finish Date (Estimated) – 10/18/2020
 +
:* First Status Date – 9/11/2020
 +
:* Task A Deadline Date – 10/15/2020 (Task A Finish Date projected before Deadline Date)
 +
:* Task B Deadline Date – 10/10/2020 (Task B Finish Date beyond Deadline Date)
 +
:* Task C Deadline Date- 10/1/2020 (Task C Start Date beyond Deadline Date)
  
<center>[[File:X70-10_6_1-70-(10)-09172019.png]]</center>
+
With these initial conditions, the Microsoft Project '''source plan''' looks like this:
<!--<center>X70-10_6_1-70-(10)-09172019.png</center>-->
+
  
===Connect Baselines and Actual Task Bars/Milestone Symbols===
+
<center>[[File:P70-10_9_1-(8)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(8)-09182019.png</center>-->
  
The '''Connecting Lines''' control group in the '''Set baseline properties''' form tells the OnePager whether you want to connect '''baselines''' to their task bars with a '''line'''.  This control group is shown below with its controls highlighted:
+
If we take a snapshot using the above '''source plan''' as of '''10/10/2019''' the chart looks like this:
  
<center>[[File:X70-10_6_1-70-(11)-09172019.png]]</center>
+
<center>[[File:P70-10_9_1-(9)-06032020.png]]</center>
<!--<center>X70-10_6_1-70-(11)-09172019.png</center>-->
+
<!--<center>P70-10_9_1-70-(9)-09182019.png</center>-->
  
Check the '''Connect baselines and actuals''' checkbox '''ON''' to '''enable''' the control group and apply the '''default baseline connection''' settings. To change the '''color''' of the '''connecting line''', check the '''Use custom color''' checkbox '''ON'''.  Then, click the '''color''' window dropdown button to access the standard '''Color Chooser'''.  Making a selection changes the '''color''' of the '''connecting line'''.  If you do not check this checkbox '''ON''', OnePager uses the '''color''' of the task bar/milestone symbol as the '''color''' of the '''connecting line''' segments.
+
OnePager recognizes the '''snapshot date''' similar to the way Microsoft Project recognizes its '''Status date'''.
  
To change the '''type of line segment''' ('''solid, dotted, dashed, etc.'''), click the '''Line style''' dropdown button and make your selection. Finally, you can '''edit''' the '''width''' of the '''line''' by changing the value in the '''Line width''' control window.
+
====Connecting Lines====
  
Click '''OK''' on the '''Set baseline properties form''' click the '''OK''' button on the '''Chart Properties''' form to see the '''baselines''' connected to their current schedule task bars/milestone symbols as shown in the sample below:
+
The '''Connecting Lines''' control group of the '''Set deadline properties''' form deals with '''connecting lines properties''' when you require that '''deadline shapes''' are tied to their parent task bar/milestone symbol. The controls available are shown below:
  
<center>[[File:X70-10_6_1-70-(12)-09172019.png]]</center>
+
<center>[[File:P70-10_9_1-(10)-06032020.png]]</center>
<!--<center>X70-10_6_1-70-(12)-09172019.png-Reshoot for top row</center>-->
+
<!--<center>P70-10_9_1-70-(10)-09182019.png</center>-->
  
In the sample above, two of the three orange '''baselines''' are '''connected''' to their respective task bars with a '''red dash-dot line''' that was '''widened''' to '''2.0''' to enhance visibility. The third '''baseline''' shown above does not display a '''connecting''' like because its '''finish date''' is within the '''start/finish dates''' boundaries of its task bar.
+
To '''enable deadline shape connection lines''', check the '''Connect deadline markers to current markers''' checkbox '''ON''' as shown above. A default '''color''', '''line style''', and '''line width''' is established from your '''current Template Properties''' form. If you wish to specify a '''custom color''', check the '''Use custom color''' checkbox '''ON''' and use the '''Custom color''' dropdown button to access the standard '''Color Chooser''' form.
  
===Showing Baseline Dates===
+
You also have the option of selecting from a variety of '''line styles''' by clicking on the '''Line style''' dropdown button. There are five (5) standard '''line styles''' to select from which are the same as used to connect '''Baselines''' to their parent task bar/milestone symbols as described in the section of the article at: [[Baselines for Version 7.0 (OnePager Pro)#Connect Baselines and Actual Task Bars/Milestone Symbols | Baselines for OnePager Pro - Connect Baselines and Actual Task Bars/Milestone Symbols]] <!--10.5.1-70-->
  
'''Baseline start/finish dates''' are automatically '''imported''' by OnePager. The '''Baseline dates''' control group on the '''Set baseline properties''' form provides the controls for '''showing, positioning, and editing''' '''baseline dates''' near the '''baselines''' for a more detailed information of target dates:
+
The value dial to the right of the '''Line style''' dropdown provides the capability to '''edit''' the '''width''' of the '''deadline shape connection line'''. The form above shows the extent of control that you have over the '''connecting lines'''.  These include the specification of a '''custom color''', '''line width''' and '''line style'''.
  
<center>[[File:X70-10_6_1-70-(13)-09172019.png]]</center>
+
====Deadline Dates====
<!--<center>X70-10_6_1-70-(13)-09172019.png</center>-->
+
  
By checking the '''Show start date''' and/or '''Show finish date''' '''ON''' you can select the '''date format''' that OnePager uses in annotating the '''baseline date''', including whether or not to use the '''fiscal year'''. 
+
The '''Deadline Dates''' control group in the '''Set deadline properties''' form provides the controls for turning '''ON''' and '''positioning''' the '''deadline date text labels''' as shown below:
  
If you choose to show both '''start and finish dates''' the same '''date format''' is applied both. The controls in this control group are very similar to the '''date controls''' associated with task bar/milestone symbol '''date labels''' as described in this article at: [[Labeling Task/Milestone Dates for Version 7.0 (OnePager Express) | Labeling Task/Milestone Dates for OnePager Express]] <!--10.2.1-70-->
+
<center>[[File:P70-10_9_1-(11)-06032020.png]]</center>
 
+
<!--<center>P70-10_9_1-70-(11)-09182019.png</center>-->
A sample of the '''date''' formats from the '''Date format''' dropdown menu is shown here:
+
  
<center>[[File:P70-10_5_1-70-(14)-09162019.png]]</center>
+
The form above shows the extent of control that you have over the display of '''date labels''' for '''deadline shapes'''. These are the same controls as for other '''decoration date''' specifications and include controls for '''date format''', the use of the '''fiscal year''' feature, the positioning of the '''date label/text''', and the '''font properties''' for the '''date label''' text.
<!--<center>P70-10_5_1-70-(14)-09162019.png</center>-->
+
  
To specify the location of the '''baseline (date) text''', relative to the '''baseline''', use the dropdown menu shown below from the '''Baseline dates''' group:
+
For more specific information about the controls in this control group, please reference the corresponding section for '''Baseline Decorations''' at: [[Baselines for Version 7.0 (OnePager Pro)#Showing Baseline Dates | Baselines for OnePager Pro - Showing Baseline Dates]] <!--10.5.1-70-->
  
<center>[[File:X70-10_6_1-70-(15)-09172019.png]]</center>
+
==Editing Individual Task Deadline Properties==
<!--<center>X70-10_6_1-70-(15)-09172019.png</center>-->
+
  
Some care needs to be taken when determining the positions of '''baseline start/finish dates''' as the settings discussed here are '''global''' setting and may result in the '''baseline start/finish date text''' colliding with other '''text information''' on the chart. When these '''baseline start/finish date text''' collisions do occur they can be corrected by individual '''editing''' of the '''baseline properties''' associated with the offending task bars.  
+
'''Deadline shape''' displays are normally turned '''OFF''' in distributed '''Template Properties''' forms. In addition to the capabilities for '''editing all Deadline properties''' using the '''Template Properties''' and/or '''Chart Properties''' forms, you can select and individually '''edit Deadline properties''' showing in the chart. As a prerequisite for '''editing''' individual '''deadline''' properties it is the necessity for '''deadline''' data to be '''imported''' from the Microsoft Project '''source plan'''.  
  
For more information on '''Editing''' individual task bar '''baseline properties''', please see the section in the article at: [[Baselines for Version 7.0 (OnePager Express)#Editing Individual Task/Milestone Baseline Properties | Editing Individual Task/Milestone Baseline Properties]] <!--10.6.1-70-->
+
===Selecting Individual Task Bar or Bars===
  
The '''Use fiscal year''' checkbox in the '''Baseline dates''' group is an instruction, if checked '''ON''', tells OnePager to show the displayed '''baseline date''' in the '''fiscal year''' format in coordination with the chart’s '''time axis'''. OnePager takes the action only if the '''time axis''' is, indeed, displaying the '''time axis''' in a '''fiscal year''' format. 
+
Some individual task bar '''deadline''' properties can be '''edited''' by selecting the desired task bar or bars with a left-click operation, then right-clicking one of the selected task bars to access the task bar right-click '''context menu''', and click the '''Format...'''button. This action accesses the '''Change Task/Milestone Properties''' form at the '''Format''' tab. Navigate to the '''Deadlines''' tab as shown below:
  
To select the '''text font''' to use in displaying  '''baseline start/finish dates''', click the '''Date font''' dropdown button.   This accesses the '''Font properties''' form. The controls in this form are the same as the controls for '''editing''' any '''text font''' in OnePager.  The '''Font properties''' form is shown below:
+
<center>[[File:P70-10_9_1-(12)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(12)-09182019.png</center>-->
  
<center>[[File:X70-10_6_1-70-(16)-09172019.png]]</center>
+
Before you can do so, you must confirm that the '''Deadline markers''' checkbox in either the '''Template Properties''' or '''Chart Properties''' form's '''Task Bars''' and/or '''Milestones''' tab is checked '''ON'''.
<!--<center>X70-10_6_1-70-(16)-09172019.png</center>-->
+
 
+
The chart below is an example of positioning '''baseline start''' and '''finish dates''' below the '''baseline''':
+
 
+
<center>[[File:X70-10_6_1-70-(17)-09172019.png]]</center>
+
<!--<center>X70-10_6_1-70-(17)-09172019.png-May have to Reshoot</center>
+
 
+
==Editing Individual Task/Milestone Baseline Properties==
+
 
+
The default settings for displaying '''baseline information''' for individual task bars/milestone symbols can be '''edited''' by using the following steps:
+
 
+
===Selecting Individual Task  Bar or Bars===
+
 
+
Before you can do so, you must confirm that the '''Baseline markers''' checkbox in either the '''Template Properties''' or '''Chart Properties''' form's '''Task Bars''' and/or '''Milestones''' tab is checked '''ON'''. You can select the task bar by right-clicking on it to access the '''task bar''' right-click '''context menu''' with the '''Format…''' command or click the '''Format…''' button on the '''Home''' ribbon tool bar tab after selecting the desired task bars/milestone symbols.
+
  
 
===Accessing the Change Task/Milestone Properties Form===
 
===Accessing the Change Task/Milestone Properties Form===
  
Using either method, click the '''Format...''' command to access the '''Change Task/Milestone Properties''' form. Then, navigate to the '''Baselines''' tab in the '''Change Task/Milestone Properties''' form which looks like this:
+
Select the '''Format…''' command which access the '''Change Task/Milestone Properties''' form. Next, navigate to the '''Deadlines''' tab, which displays the '''deadline''' control options shown below:
  
<center>[[File:X70-10_6_1-70-(18-1)-09102020.png]]</center>
+
<center>[[File:P70-10_9_1-(13)-06032020.png]]</center>
<!--<center>X70-10_6_1-70-(18-1)-09102020.png</center>-->
+
<!--<center>P70-10_9_1-70-(13)-09182019.png</center>-->
  
====Baseline Tab Editing Controls====
+
The '''Deadlines''' tab, shown above controls the display of '''deadline connectors''' and '''deadline text dates''' for the selected task bar/milestone symbol and the placement of the '''deadline date labels/text''' with respect to the '''deadline shape'''.  The '''Show Deadline''' checkbox allows you to turn '''ON''' and '''OFF''' the display of '''deadline shape''' information. When the '''Show Deadline''' checkbox is checked '''ON''', you have the option to specify the display of the '''connector''' and the display of '''deadline date''' for the selected task bar/milestone symbol. When the '''Show Deadline Date Label''' checkbox is checked '''ON''', you have access to control over the '''Deadline Date Position''' selection dropdown and '''Deadline Date Font''' selection button as discussed above related to '''editing''' all task bar/milestone symbol '''deadline information'''. There are seven (7) standard '''deadline date label''' positions to select from as shown below:
  
The '''Baselines''' tab, shown above controls the display of the '''baseline dates''' and '''connectors''' for the selected task bar/milestone symbol and the placement of the numeric text (dates) for '''baseline''' information. The '''Show Baseline''' checkbox allows you to turn on and off the display of '''baseline''' information for the selected task bar/milestone symbol. When the '''Show Baseline''' checkbox is checked '''ON''', you have the option to specify the display of the '''connector''' and the display of '''baseline start and baseline finish dates''' or both for the selected task bar/milestone symbol. When the '''Show Baseline Start Date''' checkbox is checked '''ON''' or when the '''Show Baseline Finish Date''' checkbox is checked '''ON''' (or both) you have access to control over the '''date positions''' and '''font properties''' as discussed above related to modifying all task bar/milestone symbol '''baseline information'''.
+
<center>[[File:P70-10_9_1-(14)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(14)-09182019.png</center>-->
  
====Use Baseline Defaults====
+
Clicking the '''Deadline Date Font''' button accesses the standard '''Font properties''' form where '''edits''' of the '''deadline date text''' can be made.
  
Clicking the '''Use Baseline Defaults''' button in the '''Baselines''' tab of the '''Change Task/Milestone Properties''' form resets all '''format properties of the selected '''date label or labels''' back to the settings established in the '''Chart Properties''' form.
+
===Individually Edited Deadline Shape Example===
  
===Example===
+
Below is an example of a single task bar's '''deadline information using the chart previously shown in this article:
  
Below is an example of a single task’s '''baseline information''' modified:
+
<center>[[File:P70-10_9_1-(15)-06032020.png]]</center>
 +
<!--<center>P70-10_9_1-70-(15)-09182019.png</center>-->
  
<center>[[File:X70-10_6_1-70-(19)-09172019.png]]</center>
+
The controls at the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form for the '''Show Deadline Date''', that is, the '''Position''' and '''Font''' controls operate exactly as described for other '''start/finish date''' displays in OnePager.  
<!--<center>X70-10_6_1-70-(19)-09172019.png-May have to Reshoot</center>-->
+
  
The controls at the '''Baselines''' tab of the '''Change Task/Milestone Properties''' form for '''Show Baseline Start Date''' and '''Show Baseline Finish Date''', that is, the '''Position''' and '''Font''' controls operate exactly as described for other '''start/finish date''' displays in OnePager. For reference, please see the corresponding section describing the use of these controls for the '''Percent Complete''' tab of this form at this link: [[Percent complete for Version 7.0 (OnePager Express)#Example | Percent complete for OnePager Express - Example]] <!--10.4.1-70-->
+
For more information describing the use of these controls for the '''Percent Complete''' tab of this form, please see the section in the article at: [[Percent complete for Version 7.0 (OnePager Pro)#Example | Percent complete for OnePager Pro - Example]] <!--10.3.1-70-->
  
There are no controls available in the '''Baseline''' tab of the '''Change Task/Milestone Properties''' form to '''edit''' the properties of the '''connector line''' for an '''individually''' selected task bar/milestone symbol.
+
There are no controls available in the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form to '''edit''' the properties of the '''connector line''' for an '''individually''' selected task/milestone shape.
  
==Related Link==
+
==Related Links==
  
 
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!--9.0.1-70-->
 
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!--9.0.1-70-->
Line 180: Line 167:
 
[[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] <!--9.2.1-70-->
 
[[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] <!--9.2.1-70-->
  
[[Labeling Task/Milestone Dates for Version 7.0 (OnePager Express) | Labeling Task/Milestone Dates for OnePager Express]] <!--10.2.1-70-->
+
[[Labeling Task/Milestone Dates for Version 7.0 (OnePager Pro) | Labeling Task/Milestone Dates for OnePager Pro]] <!--10.1.1-70-->
 +
 
 +
[[Percent complete for Version 7.0 (OnePager Pro) | Percent complete for OnePager Pro]] <!--10.3.1-70-->
 +
 
 +
[[Baselines for Version 7.0 (OnePager Pro) | Baselines for OnePager Pro]] <!--10.5.1-70-->
  
 
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] <!--21.0.1-70-->
 
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] <!--21.0.1-70-->
Line 186: Line 177:
 
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
 
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
  
(10.6.1-70)
+
(10.9.1-70)
  
 
[[Category:Version 7.0]]
 
[[Category:Version 7.0]]
Line 194: Line 185:
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Decorations]]
 
[[Category:Task/Milestone Decorations]]
[[Category:Baselines]]
+
[[Category:Deadlines]]
 
[[Category:Mavericks]]
 
[[Category:Mavericks]]
[[Category:OnePager Express]]
+
[[Category:OnePager Pro]]

Revision as of 15:32, 13 January 2021

About Editing Deadlines

OnePager translates Deadlines from your Microsoft Project source plan into deadline shapes in the graph to indicate the deadline date for a task bar or milestone symbol. To illustrate with a simple example, consider the Microsoft Project source plan given below with three tasks containing Start and Finish dates, a deadline date, and the Microsoft Project Flag20 field set to Yes so that OnePager imports the data for all three task bars:

P70-10 9 1-(1)-06032020.png

When a simple chart is created from the source plan above and Deadlines are turned ON, the example chart looks like this:

P70-10 9 1-(2)-06032020.png

When deadlines are turned ON, they appear (by default) as red down-arrow shape in each task bar's row at the deadline date position with respect to the time axis. Above, deadline shapes that are not contained within their respective task bar are shown with back dash-dot connecting lines to illustrate the capability.

Editing All Deadline Properties

To display deadline dates in your charts you must first assure that the Microsoft Project source plan has its Deadline field populated with valid dates. When deadline dates are present in the source plan they must first be turned ON as the default setting in most distributed Template Properties form is for deadlines to be turned OFF. To do this, click the Chart Properties button on the OnePager Home ribbon tool bar tab to access the Chart Properties form. Next, navigate to the Chart Properties Task Bars tab and to the Task Bars Decoration control group. Check the Deadline markers checkbox ON to enable the Deadline Properties... button to the immediate right of the checkbox as shown below:

P70-10 9 1-(3)-06032020.png

By default, deadlines are mapped to the Deadline date field in Microsoft Project.

Set Deadline Properties Form

To edit the format of all deadlines, click the Deadline Properties... button, to access the Set deadline properties form shown below:

P70-10 9 1-(4)-06032020.png

The form above provides all the editing controls for all deadline shapes that can be displayed in the chart.

Standard Basic Deadline Shape Controls

As stated previously, many of the controls in this group of the Set deadline properties form are standard.

The deadline shapes available are the same as Milestone symbols found in the Milestones tab of the Template Properties and Chart Properties forms. Likewise, the Fill patterns available are the same for task bars and milestone symbols also found on their respective tabs of the Template Properties and Chart Properties forms.

The Height percentage control represents the percentage of the total task bar/milestone symbol's height itself, is covered elsewhere and behaves in a standard way. The default Height percentage is 100% meaning that the deadline shape is the same height as the task bar/milestone symbol.

Similarly, the Transparency control for the deadline operates in the same way as transparency controls for other objects. The higher the value selected, the greater the transparency. Conversely, the low the value selected, the more solid the deadline shape appears.

The Field dropdown in the upper right of the form allows you to select another Microsoft Project source plan date field instead of the default Deadline field typically used in Microsoft Project. Contents of the Field dropdown list is shown below:

P70-10 9 1-(5)-06032020.png

The Position of the deadline has a unique meaning. Deadlines are always associated with a task bar/milestone symbol and can be to the left, within, or to the right of the task bar/milestone symbol itself depending on your Microsoft Project source plan data for the task bar’s start, finish and deadline dates. The position in this context is about where within the task bar/milestone symbol’s row area vertically the deadline should be placed. There are three (3) available positions for the placement of the deadline shapes with respect to the task bar:

  • Centered in the task bar/milestone symbol.
  • Above the task bar/milestone symbol.
  • Below the task bar/milestone symbol

The three available positions are shown here:

P70-10 9 1-(6)-06032020.png

The Use custom color checkbox can be checked ON when it is desired to select a color for the deadline shape other than the color for its parent task bar/milestone symbol. When the Use custom color checkbox is checked ON, the standard Custom color dropdown is enabled. Clicking the dropdown button shows the standard Color Chooser form.

Showing Deadline Delays

The purpose of the display of Deadline Delays is to provide you with the capability to highlight deadlines that are missed as shown in the chart. When the Color-code delays checkbox is checked On, OnePager uses the selected Delay color (determined by the selection of the delay color from the standard Color Chooser form) to show all deadlines that are missed:

P70-10 9 1-(7)-06032020.png

The deadline is set to the selected Delay color if, for any deadline shape:

  • The Color-code delays checkbox is checked ON,
  • The deadline date is earlier than the current snapshot date,
  • And the percent (%) complete for the parent task bar/milestone symbolis less than 100%.

If any of the conditions stated above are not met, the color of the deadline is set to the default color, unless a custom color is otherwise specified.

Example Deadline Date Delay

To illustrate the operation of the Color-code delay feature, let's set the stage by supposing that a project of three task bar is has the following initial conditions:

  • Project Start Date – 10/1/2020
  • Project Finish Date (Estimated) – 10/18/2020
  • First Status Date – 9/11/2020
  • Task A Deadline Date – 10/15/2020 (Task A Finish Date projected before Deadline Date)
  • Task B Deadline Date – 10/10/2020 (Task B Finish Date beyond Deadline Date)
  • Task C Deadline Date- 10/1/2020 (Task C Start Date beyond Deadline Date)

With these initial conditions, the Microsoft Project source plan looks like this:

P70-10 9 1-(8)-06032020.png

If we take a snapshot using the above source plan as of 10/10/2019 the chart looks like this:

P70-10 9 1-(9)-06032020.png

OnePager recognizes the snapshot date similar to the way Microsoft Project recognizes its Status date.

Connecting Lines

The Connecting Lines control group of the Set deadline properties form deals with connecting lines properties when you require that deadline shapes are tied to their parent task bar/milestone symbol. The controls available are shown below:

P70-10 9 1-(10)-06032020.png

To enable deadline shape connection lines, check the Connect deadline markers to current markers checkbox ON as shown above. A default color, line style, and line width is established from your current Template Properties form. If you wish to specify a custom color, check the Use custom color checkbox ON and use the Custom color dropdown button to access the standard Color Chooser form.

You also have the option of selecting from a variety of line styles by clicking on the Line style dropdown button. There are five (5) standard line styles to select from which are the same as used to connect Baselines to their parent task bar/milestone symbols as described in the section of the article at: Baselines for OnePager Pro - Connect Baselines and Actual Task Bars/Milestone Symbols

The value dial to the right of the Line style dropdown provides the capability to edit the width of the deadline shape connection line. The form above shows the extent of control that you have over the connecting lines. These include the specification of a custom color, line width and line style.

Deadline Dates

The Deadline Dates control group in the Set deadline properties form provides the controls for turning ON and positioning the deadline date text labels as shown below:

P70-10 9 1-(11)-06032020.png

The form above shows the extent of control that you have over the display of date labels for deadline shapes. These are the same controls as for other decoration date specifications and include controls for date format, the use of the fiscal year feature, the positioning of the date label/text, and the font properties for the date label text.

For more specific information about the controls in this control group, please reference the corresponding section for Baseline Decorations at: Baselines for OnePager Pro - Showing Baseline Dates

Editing Individual Task Deadline Properties

Deadline shape displays are normally turned OFF in distributed Template Properties forms. In addition to the capabilities for editing all Deadline properties using the Template Properties and/or Chart Properties forms, you can select and individually edit Deadline properties showing in the chart. As a prerequisite for editing individual deadline properties it is the necessity for deadline data to be imported from the Microsoft Project source plan.

Selecting Individual Task Bar or Bars

Some individual task bar deadline properties can be edited by selecting the desired task bar or bars with a left-click operation, then right-clicking one of the selected task bars to access the task bar right-click context menu, and click the Format...button. This action accesses the Change Task/Milestone Properties form at the Format tab. Navigate to the Deadlines tab as shown below:

P70-10 9 1-(12)-06032020.png

Before you can do so, you must confirm that the Deadline markers checkbox in either the Template Properties or Chart Properties form's Task Bars and/or Milestones tab is checked ON.

Accessing the Change Task/Milestone Properties Form

Select the Format… command which access the Change Task/Milestone Properties form. Next, navigate to the Deadlines tab, which displays the deadline control options shown below:

P70-10 9 1-(13)-06032020.png

The Deadlines tab, shown above controls the display of deadline connectors and deadline text dates for the selected task bar/milestone symbol and the placement of the deadline date labels/text with respect to the deadline shape. The Show Deadline checkbox allows you to turn ON and OFF the display of deadline shape information. When the Show Deadline checkbox is checked ON, you have the option to specify the display of the connector and the display of deadline date for the selected task bar/milestone symbol. When the Show Deadline Date Label checkbox is checked ON, you have access to control over the Deadline Date Position selection dropdown and Deadline Date Font selection button as discussed above related to editing all task bar/milestone symbol deadline information. There are seven (7) standard deadline date label positions to select from as shown below:

P70-10 9 1-(14)-06032020.png

Clicking the Deadline Date Font button accesses the standard Font properties form where edits of the deadline date text can be made.

Individually Edited Deadline Shape Example

Below is an example of a single task bar's deadline information using the chart previously shown in this article:

P70-10 9 1-(15)-06032020.png

The controls at the Deadline tab of the Change Task/Milestone Properties form for the Show Deadline Date, that is, the Position and Font controls operate exactly as described for other start/finish date displays in OnePager.

For more information describing the use of these controls for the Percent Complete tab of this form, please see the section in the article at: Percent complete for OnePager Pro - Example

There are no controls available in the Deadline tab of the Change Task/Milestone Properties form to edit the properties of the connector line for an individually selected task/milestone shape.

Related Links

Manual Editing Task/Milestone Shapes and Text Labels (Portal)

Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)

Labeling Task/Milestone Dates for OnePager Pro

Percent complete for OnePager Pro

Baselines for OnePager Pro