Smartsheet Fields Available to OnePager for Version 7.2
Overview
Smartsheet is very flexible when it comes to its column definitions. OnePager requires only that you prepare your Smartsheet source plan with at least three required fields before importing it to OnePager. These required fields are a Task Name, a task Start Date and a task Finish Date. Additionally, if you are creating a chart where you want to display constraints between tasks, we advise that you add and populate a Smartsheet column called Predecessor. OnePager's imported column analysis process is very good at finding and properly categorizing your user defined fields.
After analyzing and categorizing the column headings, OnePager uses this information to create virtual fields that you can use in creating and organizing your chart. The table below shows (1) the OnePager required fields, (2) imported fields, and OnePager, and (3) OnePager virtual fields.