Difference between revisions of "ADDING a Snapshot via Pull Operation - OnePager Express for Version 5.3"

From OnePager Documentation
Jump to: navigation, search
(ADDING a Snapshot via Pull Operation - OnePager Express for Version 5.3 (X53-7_15_2-121212015))
Line 1: Line 1:
=ADDING a Snapshot via Pull Operation - OnePager Express for Version 5.3 (X53-7_15_2-121212015)=
+
=ADDING a Snapshot via Pull Operation - OnePager Express for Version 5.3 (X53-7_15_2-12212015)=
  
 
The purpose of these articles is to acquaint you with the new pull features of OnePager Pro and Express.  There are eight (8) articles in this series, four (4) providing examples of the pull feature for OnePager Pro and four (4) for OnePager Express.  Please see the links at the end of this article to access other articles in the series.
 
The purpose of these articles is to acquaint you with the new pull features of OnePager Pro and Express.  There are eight (8) articles in this series, four (4) providing examples of the pull feature for OnePager Pro and four (4) for OnePager Express.  Please see the links at the end of this article to access other articles in the series.

Revision as of 15:36, 23 December 2015

ADDING a Snapshot via Pull Operation - OnePager Express for Version 5.3 (X53-7_15_2-12212015)

The purpose of these articles is to acquaint you with the new pull features of OnePager Pro and Express. There are eight (8) articles in this series, four (4) providing examples of the pull feature for OnePager Pro and four (4) for OnePager Express. Please see the links at the end of this article to access other articles in the series.

What is a Pull Operation?

A pull operation starts in the Project View Editor. That is, you already have OnePager running and decide to UPDATE the open project view or (rarely) create a NEW project view. In contrast, a push operation begins in the “OnePager Pro Start” from which you make a NEW project view or UPDATE an existing project view.

We added the pull operation because we found that our users were often creating a project view, finding something in the source file that they needed to change, going back to the source file, making the change, and then re-launching OnePager to update the project view.

The pull UPDATE lets you open a project view and update it repeatedly as you edit its source file(s). After each set of changes to the source file(s), you can quickly see the effect on the screen by using OnePager’s new “Data” tab to pull the source file changes into the project view.

The example below will illustrate a pull operation when adding a snapshot.

Example

1) Let’s suppose you have a Microsoft Excel plan for which you have already created a snapshot for a particular date, say, 12/1/2015. Later on in the project, say on 12/15/2015 you receive updated status information that updates your Microsoft Excel plan accordingly. You now want to add this latest status information to your project view as an additional snapshot for 12/15/2015 to reflect the new status information.

2) Further, let’s suppose that there are two different project views created form this one Microsoft Excel plan: (a) One for the PMO audience created with the “Show It1” column and (b) The second created for the Customer audience created with the “Show It2” column. In this example, we’ll do a replacement for the PMO audience first and then do the same replacement for the Customer audience.

3) Since the Microsoft Excel plan was updated and now reflects the latest status information for 12/15/2015 we just need to use the pull operation to bring in the updated Microsoft Excel plan data and add the snapshot.

Launching OnePager Express from the Desktop Icon

4) First, update the Microsoft Excel source file with the updated data you want to add in a new snapshot.

5) Launch OnePager Express from the desktop and when the “OnePager Express Start” form appears click the “OPEN” button which, in our example, will provide a drop down menu with the name of the project view you wish to update by replacement. In this case it’s “BlueGrass 2J-303-PMO-X” as shown below:

X53-7 14 2-53-(1)-12062015.png
X53-7_14_2-53-(1)-12062015.png

6) The OnePager Express desktop application will bring the selected project view up in the Project View Editor window. This is the project view that has one snapshot currently for 12/1/2015 for which we want to add a second snapshot for 12/15/2015. To proceed with the snapshot add click the “Data” tab on the OnePager Express ribbon and prepare to click the “Add Snapshot” button. The Project View Editor will look like this:

X53-7 15 2-53-(1A)-12072015.png
X53-7_15_2-53-(1A)-12072015.png

Use the Microsoft Excel Source File to Add a Snapshot

7) To add a snapshot, simply click the “Add Snapshot” button on the “Data” tab of the ribbon. A calendar drop down will appear. Select the date of the new snapshot in the calendar and click “OK” in the calendar drop down as shown below:

X53-7 15 2-53-(1B)-12072015.png
X53-7_15_2-53-(1B)-12072015.png

8) OnePager Express adds the snapshot by loading the Microsoft Excel associated with the project view and uses it to add a new snapshot as shown above.

9) The added snapshot for project view “BlueGrass 2J-303-PMO-X” is shown below:

X53-7 15 2-53-(5)-12072015.png
X53-7_15_2-53-(5)-12072015.png

10) Since we are using the desktop application of OnePager for this example it was not necessary to launch Microsoft Excel first. As long as you’ve properly prepared your Microsoft Excel plan source file just launching OnePager Express from the desktop icon is basically all that is necessary to utilize the new pull operation for adding a snapshot.

11) At this point it is recommended that you save this the project view for access later.

Preparing a Second Project View for Adding a Snapshot

12) There are two ways of updating the second project view from the same Microsoft Excel source file:

a) After saving the first project view, close the OnePager Express desktop application and repeat the above process by opening the second project view and then using “Show It2” to select the tasks.
b) Remain in the current OnePager Express desktop application window and update the second project view from there.

13) Here we will demonstrate the second method as it is more efficient.

14) With the above project view visible in the Project View Editor window, click on the “File” tab on the OnePager ribbon and then click the “Open…” tab on the page that appears. Then click the project view for the Customer audience as shown below:

X53-7 14 2-53-(3)-12062015.png
X53-7_14_2-53-(3)-12062015.png

15) When you click the desired project view name as shown above, OnePager will display that project view in a separate Project View Editor window as shown here:

X53-7 15 2-53-(3A)-12072015.png
X53-7_15_2-53-(3A)-12072015.png

16) You may want to expand this Project View Editor window. Now, navigate to the “Data” tab on the OnePager Express ribbon as shown below:

X53-7 15 2-53-(3B)-12072015.png
X53-7_15_2-53-(3B)-12072015.png

17) Clicking the “Add Snapshot” button on the OnePager “Data” tab and select the new snapshot date from the drop down calendar as shown previously. This tells OnePager Express to go to the Microsoft Excel plan source file for this project view (previously updated with the 12/15/2015 status information), perform the snapshot replacement under the control of the “Show It2” column of the plan, and display the results in the current Project View Editor window.

18) The added snapshot is shown below:

X53-7 15 2-53-(9)-12072015.png
X53-7_15_2-53-(9)-12072015.png

19) In this example we used the pull operation twice to update two project views from the same Microsoft Excel plan source file but using different “flag” columns. Now that the second project view is created, we recommend that it too be saved for future access.

Compare Results, Edit, Copy to PowerPoint

20) Once you are satisfied with your project view you may save them, copy them into PowerPoint presentations, or share time in other ways.

21) At the end of the ADD Snapshot process described in this article, your projects will contain multiple snapshots. You may move from one to another in the Project View Editor window by going to the “View” tab on the OnePager ribbon and either click the left and right buttons to switch from snapshot to snapshot or use the “List All” button to display snapshot dates associated with the project view as shown below:

X53-7 15 2-53-(10)-12072015.png
X53-7_15_2-53-(10)-12072015.png

22) The pull operation is an easy, fast, and convenient way to create multiple project views which will make you more efficient.

Related Links

Creating a NEW Project View via Pull Operation - OnePager Pro for Version 5.3 7.13.1-53

Creating a NEW Project View via Pull Operation - OnePager Express for Version 5.3 7.13.2-53

REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 7.14.1-53

REPLACING a Snapshot via Pull Operation - OnePager Express for Version 5.3 7.14.2-53

ADDING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 7.15.1-53

Custom REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 7.16.1-53

Custom REPLACING a Snapshot via Pull Operation - OnePager Express for Version 5.3 7.16.2-53

(7.15.2-53)