ADDING a Snapshot via Pull Operation - OnePager Pro for Version 7.0

From OnePager Documentation
Revision as of 21:29, 22 February 2019 by Rfeingold (Talk | contribs)

Jump to: navigation, search

Overview

1) The purpose of these articles is to acquaint you with the new pull features of OnePager Pro (OPP) and Express (OPX).

2) There are eight (8) articles in this series, four (4) providing examples of the pull feature for OPP and four (4) for OPX.

3) Please see the links at the end of this article to access other articles in the series.

What is a Pull Operation?

1) A pull operation starts in the Chart Editor. That is, you already have OnePager running and decide to update the open chart or (rarely) create a new chart. In contrast, a push operation begins in the OnePager Pro Start from which you make a new chart or update an existing chart.

2) We added the pull operation because we found that our users were often creating a chart, finding something in the source file that they needed to change, going back to the source plan, making the change, and then re-launching OnePager to update the chart.

3) The pull update lets you open a chart and update it repeatedly as you edit its source plan. After each set of changes to the source plan(s), you can quickly see the effect on the screen by using OnePager’s new Data tab to pull the source plan changes into the chart.

4) The example below illustrates a pull operation when adding a snapshot.

Example

1) Let’s suppose you have a Microsoft Project source plan with an already created a snapshot for a particular date, say, 12/1/2015. Later on in the project, say on 12/15/2015 you receive updated status information that updates your Microsoft Project source plan accordingly. You now want to add this latest status information to your chart as an additional snapshot for 12/15/2015 to reflect the new status information.

2) Further, let’s suppose that there are two different charts created from this one Microsoft Project source plan:

(1) One for the PMO audience created with the Flag20 field and
(2) The second created for the customer audience created with the Flag10 field. In this example, we’ll do a replacement for the PMO audience first and then do the same replacement for the customer audience.

3) Since the Microsoft Project source plan was updated and now reflects the latest status information for 12/15/2015 we just need to use the pull operation to bring in the updated Microsoft Project source plan data and add the snapshot.

Launching OnePager Pro from the Desktop Icon

4) First, update the Microsoft Project source plan with the updated data you want to add in a new snapshot.

5) Launch OPP from the desktop and when the OnePager Pro Start form appears click the OPEN button which, in our example, provides a dropdown menu with the name of the chart you wish to update by adding a new snapshot. In this case it’s BlueGrass 2J-303-PMO as shown below:

P60-7 14 1-60-(1)-02012017.png
P60-7_14_1-60-(1)-02012017.png

6) The OPP desktop application accesses the selected chart up in the Chart Editor window. This is the chart that has one snapshot currently for 12/1/2015 for which we want to add a second snapshot for 12/15/2015. To proceed with the snapshot add click the Data tab on the ribbon and prepare to click the Add Snapshot button. The Chart Editor looks like this:

P60-7 15 1-60-(1A)-02022017.png
P60-7_15_1-60-(1A)-02022017.png

Use the Microsoft Project Source Plan to Add a Snapshot

7) To add a snapshot, click the Add Snapshot button on the Data tab of the ribbon. A calendar dropdown appears. Select the date of the new snapshot in the calendar and click OK in the calendar drop down as shown below:

P60-7 15 1-60-(1B)-02022017.png
P60-7_15_1-60-(1B)-02022017.png

8) OPP adds the snapshot by loading the Microsoft Project source plan associated with the chart and uses it to add a new snapshot as shown above.

9) The added snapshot for Chart BlueGrass 2J-303-PMO is shown below:

P53-7 15 1-53-(5)-12072015.png

10) Since we are using the OPP desktop application for this example, it was not necessary to launch Microsoft Project first. As long as you’ve properly prepared your Microsoft Project source plan just launching OPP from the desktop icon is basically all that is necessary to utilize the new pull operation for adding a snapshot.

11) At this point it is recommended that you save this the chart for access later.

Preparing a Second chart for Adding a Snapshot

12) There are two ways of updating the second chart from the same Microsoft Project source plan:

(1) After saving the first chart, close the OPP desktop application and repeat the above process by opening the second chart and then using Flag10 to select the tasks.
(2) Remain in the current OnePager Pro desktop application window and update the second chart from there.

13) Here we demonstrates the second method as it is more efficient.

14) With the above chart visible in the Chart Editor window, click on the File tab on the ribbon and then click the Open… tab on the page that appears. Then click the chart for the customer audience as shown below:

P60-7 15 1-60-(3)-02022017.png
P60-7_15_1-60-(3)-02022017.png

15) When you click the desired chart name as shown above, OnePager displays that chart in a separate Chart Editor window as shown here:

P60-7 15 1-60-(3A)-02022017.png
P60-7_15_1-60-(3A)-02022017.png

16) You can expand this Chart Editor window. Now, navigate to the Data tab on the ribbon as shown below:

P60-7 15 1-60-(3B)-02022017.png
P60-7_15_1-60-(3B)-02022017.png

17) Click the Add Snapshot button on the Data tab and select the new snapshot date from the dropdown calendar as shown previously. This tells OPP to go to the Microsoft Project source plan for this chart (previously updated with the 12/15/2015 status information), perform the snapshot add function under the control of the Flag10 field, and display the results in the current Chart Editor window.

18) The added snapshot is shown below:

P60-7 15 1-60-(9)-02022017.png
P60-7_15_1-60-(9)-02022017.png

19) In this example, we used the pull operation twice to update two charts from the same Microsoft Project source plan but using different flag fields. Now that the second chart is created, we recommend that it too be saved for future access.

Compare Results, Edit, Copy to PowerPoint

20) Once you are satisfied with your charts you can save them, copy them into Microsoft PowerPoint presentations, or share time in other ways.

21) At the end of the ADD Snapshot process described in this article, your projects contains multiple snapshots. You can move from one to another in the Chart Editor window by going to the View tab on the ribbon and either click the Forward/Back buttons to switch from snapshot to snapshot or use the List All button to display snapshot dates associated with the chart as shown below:

P60-7 15 1-60-(10)-02022017.png
P60-7_15_1-60-(10)-02022017.png

22) The pull operation is an easy, fast, and convenient way to create multiple charts which makes you more efficient.

Related Links

Creating a NEW Chart via Pull Operation - OnePager Pro 7.13.1-70

Creating a NEW Chart via Pull Operation - OnePager Express 7.13.2-70

REPLACING a Snapshot via Pull Operation - OnePager Pro 7.14.1-70

REPLACING a Snapshot via Pull Operation - OnePager Express 7.14.2-70

ADDING a Snapshot via Pull Operation - OnePager Express 7.15.2-70

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro 7.16.1-70

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express 7.16.2-70

Using the OnePager "Data" Tab's "Selected file(s)" Button 7.17.1-70

(7.15.1-70)