(Created page with "=Creating a NEW Project View via Pull Operation- OnePager Express for Version 5.3 (X53-7_13_2-12062015)= The purpose of these articles is to acquaint you with the new “Pull...")
 
(Compare Results, Edit, Copy to PowerPoint)
 
(20 intermediate revisions by the same user not shown)
Line 1: Line 1:
=Creating a NEW Project View via Pull Operation- OnePager Express for Version 5.3 (X53-7_13_2-12062015)=
+
===Overview===
  
The purpose of these articles is to acquaint you with the new “Pull” features of OnePager Express and Pro Versions 5.3.  There are eight (8) articles in this series, four (4) providing examples of the “Pull” feature for OnePager Express Desktop and four (4) for OnePager Pro Desktop.  Please see the links at the end of this article to access other articles in the series.
+
The purpose of these articles is to acquaint you with the new '''pull''' features of OnePager Express ('''OPX''') and Pro ('''OPP''')).  There are eight (8) articles in this series, four (4) providing examples of the pull feature for '''OPX''' and four (4) for '''OPP'''.  Please see the links at the end of this article to access the rest of the series.
  
This article shows you how to use the “Pull” feature when you need to create a NEW project view such as when you want to generate a second project views from different source files or from the same slightly modified source files.
+
Creating a NEW project view via '''pull''' is not the main reason why OnePager has '''pull''' operations. This workflow is most useful only when you want to fill an empty Project View Editor ('''PVE''') by making a new project view. The real power of the '''pull''' operation is to let you do repeated snapshot '''REPLACE''' and snapshot add operations on an open project view.  In other words, the '''pull''' operation’s main purpose is to let you update the on-screen project view as you edit its '''source file(s)'''.  The '''pull update''' operation is discussed in other articles in this series.
  
 
==What is a Pull Operation?==
 
==What is a Pull Operation?==
  
Before we get started with the example, this is a good point to describe the “Pull” Operation.  A “Pull” Operation is performed when you start using OnePager from the Project View Editor.  That is, you already have OnePager launched and running and the Project View Editor window is blankAlternatively, a “Push” Operation begins when you launch OnePager from the desktop or from Microsoft Excel and perform the creation of a NEW project view, UPDATE a project view, or OPEN an existing project view from the “OnePager Excel Start” form.
+
A '''pull''' operation starts in the '''PVE'''.  That is, you already have OnePager running and decide to update the open project view or (rarely) create a new project viewIn contrast, a '''push''' operation begins in the '''OnePager Express Start''' from which you make a new project view or update an existing project view.
  
We added the “Pull” Operation because we found that our users were often creating a project view, finding something in the source file that they needed to change, going back to the source file, making the change and then re-launching OnePager to replace the project view.   
+
We added the '''pull''' operation because we found that our users were often creating a project view, finding something in the '''source file''' that they needed to change, going back to the '''source file''', making the change, and then re-launching OnePager to update the project view.   
  
The “Pull” Operation lets you launch OnePager once, create your project view, and, if you need to make a source file change, you may go back to the source file and do thatWhen you’ve updated the source file, you need only go back to OnePager and through the new “Data” tab quickly “pull” in the amended source file, update your project view, and continue.
+
The '''pull update''' lets you open a project view and update it repeatedly as you edit its '''source file(s)'''After each set of changes to the '''source file(s)''', you can quickly see the effect on the screen by using OnePager’s new '''Data''' tab to '''pull''' the '''source file''' changes into the project view.  
  
You’ll see this more in play when you read the articles [[REPLACING a Snapshot via Pull Operation - OnePager Express for Version 5.3]] and [[ADDING a Snapshot via Pull Operation - OnePager Express for Version 5.3]].
+
You’ll see this more when you read the articles [[REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 | REPLACING a Snapshot via Pull Operation - OnePager Pro]] and [[ADDING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 | ADDING a Snapshot via Pull Operation - OnePager Pro]].
  
In the “Pull’ Operation as described above, OnePager “pulls” the data into the Project View Editor whereas in a “Push” Operation Microsoft Excel provides or “pushes” the data to OnePager Pro.
+
The example below illustrates creating a new project view.
 
+
The example below will illustrate a “Pull” Operation when creating a NEW project view.
+
  
 
==Example==
 
==Example==
Line 23: Line 21:
 
1) Let’s suppose you have a Microsoft Excel plan that you want to present to two different audiences – Your Project Management Office (PMO) and your customer.  However, before the presentation you want to quickly examine the two project views made by OnePager side-by-side.
 
1) Let’s suppose you have a Microsoft Excel plan that you want to present to two different audiences – Your Project Management Office (PMO) and your customer.  However, before the presentation you want to quickly examine the two project views made by OnePager side-by-side.
  
2) In preparation, you “flag” the rows to be shown to the PMO using Microsoft Project’s “Show It1” column and put a “Yes” in the appropriate rows of the Microsoft Project plan.  You also decide to use “Show It2” to show those rows that you want to show in your presentation to the customer.  You insert both the “Show It1” and “Show It2” columns into the plan as shown below:
+
2) In preparation, you '''flag''' the rows to be shown to the PMO using Microsoft Excel’s '''Show It1''' column and put a '''Yes''' in the appropriate rows.  You also decide to use '''Show It2''' to show those rows that you want to show in your presentation to the customer.  You insert both the '''Show It1''' and '''Show It2''' columns into the plan as shown below:
  
 
<center>[[File:X53-7_13_2-53-(1)-12022015.png]]</center>
 
<center>[[File:X53-7_13_2-53-(1)-12022015.png]]</center>
 
<center></center>
 
 
<center>X53-7_13_2-53-(1)-12022015.png</center>
 
  
 
==Prepare First Project View==
 
==Prepare First Project View==
  
<center></center>
+
3) For the sake of this example, let’s first use the OnePager Express '''desktop''' application to access the Microsoft Excel plan using the '''Show It1''' flag column shown above.   
 
+
3) We are going to illustrate the “Pull” feature in two ways.  First, we’ll set up the OnePager Express desktop application to “pull in” the Microsoft Excel plan using the “Show It1” flag column shown above.
+
 
+
4) Launch OnePager Express from the desktop icon and when the “OnePager Express Start” form appears just click the “Close” buttonThis action will take you to the “File” tab as shown below:
+
 
+
<center>[[File:X53-7_13_2-53-(1A)-12022015.png]]</center>
+
 
+
<center></center>
+
 
+
<center>X53-7_13_2-53-(1A)-12022015.png</center>
+
 
+
5) Now, click the “New…” button in the “File” tab list.  This action will bring up the Project View Editor screen with the “OnePager choices” form showing.  Next, click the “Select” button which brings down a menu from which we will select the second entry which is the Microsoft Excel plan we are using in this example as shown below:
+
 
+
<center>[[File:X53-7_13_2-53-(1B)-12022015.png]]</center>
+
 
+
<center></center>
+
 
+
<center>X53-7_13_2-53-(1B)-12022015.png</center>
+
 
+
6) When you click on the second entry in the dropdown menu as shown above, OnePager Express will expand the “OnePager choices” form so you can confirm the remainder of the settings before OnePager generates the project view.  This is shown below:
+
 
+
<center>[[File:X53-7_13_2-53-(4)-12022015.png]]</center>
+
 
+
<center></center>
+
 
+
<center>X53-7_13_2-53-(4)-12022015.png</center>
+
  
7) After the settings are confirmed in the above form we will be asking OnePager to generate a project view with the Title shown above, using the indicated “flag” column and designating the snapshot with the date shown.  When you click the “Create new project view” button OnePager will create the following project view:
+
4) After the steps covered in the article above are completed, OnePager will generate a project view with the title shown below, using the '''Show It1''' column, and designating the snapshot with the date shown.  The resulting project view will look like the following:
  
 
<center>[[File:X53-7_13_2-53-(5)-12022015.png]]</center>
 
<center>[[File:X53-7_13_2-53-(5)-12022015.png]]</center>
  
<center></center>
+
5) Since we are using the '''desktop''' application of '''OPX''', it was not necessary to launch Microsoft Excel first.  As long as you’ve properly prepared your Microsoft Excel plan '''source file''' just launching '''OPX''' from the '''desktop''' icon is basically all that is necessary to utilize the new '''pull''' feature. 
  
<center>X53-7_13_2-53-(5)-12022015.png</center>
+
6) At this point it is recommended that you save this first project view for access later.
  
<center></center>
+
==Prepare a Second Project View==
  
8) The above portion of the example is a strict usage of the “Pull” feature to create a new project view.  Since we are using the desktop application of OnePager for this example it was not necessary to launch Microsoft Excel first.  As long as you’ve properly prepared your Microsoft Excel plan source file just launching OnePager Express from the desktop icon is basically all that is necessary to utilize the new “Pull” feature. 
+
7) There are two ways of creating the second project view from the same Microsoft Excel source file:
  
9) At this point it is recommended that you save this first project view for access later.
+
:(1) After saving the first project view, close the '''OPX desktop''' application and repeat the above process by opening the second project view and then using '''Show It2''' to select the tasks.
  
==Prepare Second Project View==
+
:(2) Remain in the current '''OPX''' '''PVE''' window and create a second new project view from there.
  
<center></center>
+
8) Here we will demonstrate the second (2) method as it is more efficient.
  
10) With the above project view saved yet visible in the Project View Editor window, again click on the “File” tab on the OnePager ribbon and then click the “New…” tab on the page that appears:
+
9) With the above project view saved and visible in the '''PVE''' window, click on the '''File''' tab and then click the '''New…''' tab on the page that appears:
  
 
<center>[[File:X53-7_13_2-53-(6)-12022015.png]]</center>
 
<center>[[File:X53-7_13_2-53-(6)-12022015.png]]</center>
  
<center></center>
+
10) When you click the '''New…''' button as shown above, OnePager will display the OnePager choices ('''OPC''') form.  You will now use to create the project view for the customer by giving the new project view a new name, specifying that the “flag” column to be used is “Show It2”, and specifying the appropriate snapshot date as shown in the sequence below:
 
+
<center>X53-7_13_2-53-(6)-12022015.png</center>
+
 
+
<center></center>
+
 
+
11) When you click the “New…” button as shown above, OnePager will display another “OnePager choices” form which you will now use to create the project view for the customer by giving the new project view a new name, specifying that the “flag” column to be used is “Show It2”, and specifying the appropriate snapshot date as shown in the sequence below:
+
  
 
<center>[[File:X53-7_13_2-53-(7)-12022015.png]]</center>
 
<center>[[File:X53-7_13_2-53-(7)-12022015.png]]</center>
  
<center></center>
+
11) When the file is selected, the '''OPC''' form will expand and provide you with the ability to uniquely name the new project view, specify the '''flag''' field to use, and specify the snapshot date as we have done in the illustration below:
 
+
<center>X53-7_13_2-53-(7)-12022015.png</center>
+
 
+
<center></center>
+
 
+
12) When the file is selected the “OnePager choices” form will expand as before and again provide you with the ability to uniquely name the new project view, specify the “flag” field to use, and specify the snapshot date as we have done in the illustration below:
+
  
 
<center>[[File:X53-7_13_2-53-(8)-12022015.png]]</center>
 
<center>[[File:X53-7_13_2-53-(8)-12022015.png]]</center>
  
<center></center>
+
12) With the new settings confirmed in the '''OPC''' form, click the '''Create new project view''' and OnePager will use your new settings to create the second project view and display it as shown below:
 
+
<center>X53-7_13_2-53-(8)-12022015.png</center>
+
 
+
<center></center>
+
 
+
13) With the new settings confirmed in the “OnePager choices” form, click the “Create new project view” and OnePager will use your new settings to create the second project view and display it as shown below:
+
  
 
<center>[[File:X53-7_13_2-53-(9)-12022015.png]]</center>
 
<center>[[File:X53-7_13_2-53-(9)-12022015.png]]</center>
  
<center></center>
+
13) In this example, we used the '''OPX desktop''' application to create two project views from the same Microsoft Excel '''source file''' but using different '''flag''' columns.  Now that the second project view is created, we recommend that it too be saved for future access.
 
+
<center>X53-7_13_2-53-(9)-12022015.png</center>
+
 
+
<center></center>
+
 
+
14) In this example we used the “Pull” feature twice to create two project views from the same Microsoft Project plan source file but using different “flag” columns.  Now that the second project view is created, we recommend that it too be saved for future access.
+
  
 
==Compare Results, Edit, Copy to PowerPoint==
 
==Compare Results, Edit, Copy to PowerPoint==
  
<center></center>
+
14) Once you are satisfied with your project views you may save them, copy them into PowerPoint presentations, or share time in other ways.
  
15) Once you are satisfied with your project view you may save them, copy them into PowerPoint presentations, or share time in other ways.
+
15) The '''pull''' feature is an easy, fast, and convenient way to create multiple project views which will make you more efficient.
  
16) The “Pull” feature is an easy, fast, and convenient way to create multiple project views which will make you more efficient.
+
==Related Links==
  
Related Links:
+
[[Creating a NEW Project View via Pull Operation - OnePager Pro  for Version 5.3 | Creating a NEW Project View via Pull Operation - OnePager Pro]]
  
[[Creating a NEW Project View via Pull Operation - OnePager Pro for Version 5.3]] 7.13.1-53
+
[[REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 | REPLACING a Snapshot via Pull Operation - OnePager Pro]]  
  
[[REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 5.3]] 7.14.1-53
+
[[REPLACING a Snapshot via Pull Operation - OnePager Express for Version 5.3 | REPLACING a Snapshot via Pull Operation - OnePager Express]]
  
[[REPLACING a Snapshot via Pull Operation - OnePager Express for Version 5.3]] 7.14.2-53
+
[[ADDING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 | ADDING a Snapshot via Pull Operation - OnePager Pro]]
  
[[ADDING a Snapshot via Pull Operation - OnePager Pro for Version 5.3]] 7.15.1-53
+
[[ADDING a Snapshot via Pull Operation - OnePager Pro for Version 5.3 | ADDING a Snapshot via Pull Operation - OnePager Pro]]
  
[[ADDING a Snapshot via Pull Operation - OnePager Express for Version 5.3]]   7.15.2-53
+
[[Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro for Version 5.3 | Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro]]
  
[[Custom REPLACING a Snapshot via Pull Operation - OnePager Pro for Version 5.3]] 7.16.1-53
+
[[Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express for Version 5.3 | Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express]]  
  
[[Custom REPLACING a Snapshot via Pull Operation - OnePager Express for Version 5.3]] 7.16.2-53
+
[[Using the OnePager "Data" Tab's "Selected file(s)" Button]]
  
 
(7.13.2-53)
 
(7.13.2-53)
  
 
[[Category:Version 5.3]]
 
[[Category:Version 5.3]]
 
 
[[Category:Desktop]]
 
[[Category:Desktop]]
 
 
[[Category:Basic Workflows]]
 
[[Category:Basic Workflows]]
 
 
[[Category:Project-View Properties Form]]
 
[[Category:Project-View Properties Form]]
 
 
[[Category:OnePager Choices Form]]
 
[[Category:OnePager Choices Form]]
 
 
[[Category:Snapshots]]
 
[[Category:Snapshots]]
 
 
[[Category:Project Views]]
 
[[Category:Project Views]]
 
 
[[Category:OnePager Express]]
 
[[Category:OnePager Express]]

Latest revision as of 20:19, 3 March 2016

Overview

The purpose of these articles is to acquaint you with the new pull features of OnePager Express (OPX) and Pro (OPP)). There are eight (8) articles in this series, four (4) providing examples of the pull feature for OPX and four (4) for OPP. Please see the links at the end of this article to access the rest of the series.

Creating a NEW project view via pull is not the main reason why OnePager has pull operations. This workflow is most useful only when you want to fill an empty Project View Editor (PVE) by making a new project view. The real power of the pull operation is to let you do repeated snapshot REPLACE and snapshot add operations on an open project view. In other words, the pull operation’s main purpose is to let you update the on-screen project view as you edit its source file(s). The pull update operation is discussed in other articles in this series.

What is a Pull Operation?

A pull operation starts in the PVE. That is, you already have OnePager running and decide to update the open project view or (rarely) create a new project view. In contrast, a push operation begins in the OnePager Express Start from which you make a new project view or update an existing project view.

We added the pull operation because we found that our users were often creating a project view, finding something in the source file that they needed to change, going back to the source file, making the change, and then re-launching OnePager to update the project view.

The pull update lets you open a project view and update it repeatedly as you edit its source file(s). After each set of changes to the source file(s), you can quickly see the effect on the screen by using OnePager’s new Data tab to pull the source file changes into the project view.

You’ll see this more when you read the articles REPLACING a Snapshot via Pull Operation - OnePager Pro and ADDING a Snapshot via Pull Operation - OnePager Pro.

The example below illustrates creating a new project view.

Example

1) Let’s suppose you have a Microsoft Excel plan that you want to present to two different audiences – Your Project Management Office (PMO) and your customer. However, before the presentation you want to quickly examine the two project views made by OnePager side-by-side.

2) In preparation, you flag the rows to be shown to the PMO using Microsoft Excel’s Show It1 column and put a Yes in the appropriate rows. You also decide to use Show It2 to show those rows that you want to show in your presentation to the customer. You insert both the Show It1 and Show It2 columns into the plan as shown below:

X53-7 13 2-53-(1)-12022015.png

Prepare First Project View

3) For the sake of this example, let’s first use the OnePager Express desktop application to access the Microsoft Excel plan using the Show It1 flag column shown above.

4) After the steps covered in the article above are completed, OnePager will generate a project view with the title shown below, using the Show It1 column, and designating the snapshot with the date shown. The resulting project view will look like the following:

X53-7 13 2-53-(5)-12022015.png

5) Since we are using the desktop application of OPX, it was not necessary to launch Microsoft Excel first. As long as you’ve properly prepared your Microsoft Excel plan source file just launching OPX from the desktop icon is basically all that is necessary to utilize the new pull feature.

6) At this point it is recommended that you save this first project view for access later.

Prepare a Second Project View

7) There are two ways of creating the second project view from the same Microsoft Excel source file:

(1) After saving the first project view, close the OPX desktop application and repeat the above process by opening the second project view and then using Show It2 to select the tasks.
(2) Remain in the current OPX PVE window and create a second new project view from there.

8) Here we will demonstrate the second (2) method as it is more efficient.

9) With the above project view saved and visible in the PVE window, click on the File tab and then click the New… tab on the page that appears:

X53-7 13 2-53-(6)-12022015.png

10) When you click the New… button as shown above, OnePager will display the OnePager choices (OPC) form. You will now use to create the project view for the customer by giving the new project view a new name, specifying that the “flag” column to be used is “Show It2”, and specifying the appropriate snapshot date as shown in the sequence below:

X53-7 13 2-53-(7)-12022015.png

11) When the file is selected, the OPC form will expand and provide you with the ability to uniquely name the new project view, specify the flag field to use, and specify the snapshot date as we have done in the illustration below:

X53-7 13 2-53-(8)-12022015.png

12) With the new settings confirmed in the OPC form, click the Create new project view and OnePager will use your new settings to create the second project view and display it as shown below:

X53-7 13 2-53-(9)-12022015.png

13) In this example, we used the OPX desktop application to create two project views from the same Microsoft Excel source file but using different flag columns. Now that the second project view is created, we recommend that it too be saved for future access.

Compare Results, Edit, Copy to PowerPoint

14) Once you are satisfied with your project views you may save them, copy them into PowerPoint presentations, or share time in other ways.

15) The pull feature is an easy, fast, and convenient way to create multiple project views which will make you more efficient.

Related Links

Creating a NEW Project View via Pull Operation - OnePager Pro

REPLACING a Snapshot via Pull Operation - OnePager Pro

REPLACING a Snapshot via Pull Operation - OnePager Express

ADDING a Snapshot via Pull Operation - OnePager Pro

ADDING a Snapshot via Pull Operation - OnePager Pro

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express

Using the OnePager "Data" Tab's "Selected file(s)" Button

(7.13.2-53)