==About Modifying Deadlines==
+
==About Deadlines==
  
1) '''Deadlines''' indicate the '''deadline date''' for a task or milestone.  
+
1) OnePager translates '''Deadlines''' from your Microsoft Excel '''source plan''' into '''deadline''' shapes in the '''graph''' to indicate the '''deadline date''' for a task or milestone.
  
2) Just to illustrate with a simple example, consider the Microsoft Excel '''source plan''' given below which has three tasks with '''Start and Finish dates''', a '''deadline date''', and the Microsoft Excel '''Show It''' field set to '''Yes''' so that OnePager imports the data for all three tasks:
+
:a) In order to '''import''' '''deadline date''' information, your Microsoft Excel '''source plan''' must have a column header with a name similar to the word '''deadline'''.
  
<center>[[File:X52-10_10-(1)-06082015.png]]</center>
+
:b) OnePager Express does its best to translate similar names to '''deadline date''' information and '''import''' this data.
  
==Displaying Deadline Properties==
+
:c)  You always have the option to specifically designate a Microsoft Excel column header name as your specific set of dates specifying '''deadlines'''.
  
When '''deadlines''' are turned on, they appear (by default) as red arrows next to each task bar:
+
:d) This option is available in the OnePager Express '''Template''' and '''Chart Properties''' form at the '''Task Bars''' tab as is explained later in this article.
  
<center>[[File:X52-10_10-(2)-06082015.png]]</center>
+
2) To illustrate with a simple example, consider the Microsoft Excel '''source plan''' given below with three tasks containing '''Start and Finish dates''', a '''deadline date''', and a '''Flag''' with the header '''Show It set to '''Yes''' so that OnePager '''imports''' the data for all three tasks:
  
1) To display '''deadlines''' for tasks, navigate to the '''Chart Properties''' '''Task Bars''' tab. To display '''deadlines''' for milestones, go to the '''Chart Properties''' '''Milestones''' tab.
+
<center>[[File:X70-10_9_1-70-(1-1)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(1-1)-09192019.png</center>
  
2) Check the '''Deadline shapes''' checkbox to ensure that '''deadlines''' are showing. By default, '''deadlines''' are mapped to the closest field name resembling a '''Deadline date''' field you specified in your Microsoft Excel '''source plan'''.
+
3) When a simple chart is created from the '''source plan''' above and '''Deadlines''' are turned '''On''', the example chart looks like this:
  
<center>[[File:X60-10_10_1-60-(3)-02102017.png]]</center>
+
<center>[[File:X70-10_9_1-70-(2)-09192019.png]]</center>
<center>X60-10_10_1-60-(3)-02102017.png</center>
+
<center>X70-10_9_1-70-(2)-09192019.png</center>
  
==Modifying All Deadline Properties==
+
:a) When '''deadlines''' are turned on, they appear (by default) as '''red arrow shape''' in each task bar's row at the '''deadline date''' position with respect to the '''time axis'''.
  
1) To change the format of all '''deadlines''', click the '''Deadline Properties....''' button, to bring up the '''Set date label properties''' form shown below:
+
:b) Above, '''deadline shapes''' that are not contained within their respective task bar are shown with '''back dash-dot connecting lines''' to illustrate the capability.
  
<center>[[File:X60-10_10_1-60-(4)-02102017.png]]</center>
+
==Editing All Deadline Properties==
<center>X60-10_10_1-60-(4)-02102017.png</center>
+
  
:a) '''Deadline Shape, Fill, Position, Transparency, and Color Controls'''.  As stated previously, many of the controls in this group of the '''Set deadline properties''' form are standard.  
+
1) To display '''deadline dates''' in your charts you must first assure that the Microsoft Excel '''source plan''' has a '''Deadline''' field populated with valid '''dates'''.
  
:b) The '''Position''' of the '''deadline''' has a unique meaning. '''Deadlines''' are always associated with a task/milestone and can be to the left, within, or to the right of the task/milestone itself depending on your Microsoft Excel '''source plan''' data for the task’s '''start''', '''finish''' and '''deadline dates'''.  The position in this context is about where within the task/milestone’s area vertically the '''deadline''' should be placed. There are three available positions for the placement of the deadline with respect to the task:  
+
2) When '''deadline dates''' are present in the '''source plan''' they must first be turned '''On''' as the default setting in most distributed '''Templates''' is for '''deadlines''' to be turned '''Off'''.
 +
 
 +
3) To do this click the '''Chart Properties''' button on the OnePager '''Home''' tab to access the '''Chart Properties''' form.
 +
 
 +
4) Next, navigate to the '''Chart Properties''' '''Task Bars''' tab and to the '''Task Bars Decoration''' control group as shown below:
 +
 
 +
:a) Check the '''Deadline markers''' checkbox '''On''' to '''enable''' the '''Deadline Properties...''' button to the immediate right of the checkbox as shown below:
 +
 
 +
<center>[[File:X70-10_9_1-70-(3)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(3)-09192019.png</center>
 +
 
 +
:b) By default, '''deadlines''' are mapped to the '''Deadline date''' field in Microsoft Excel if that field is present as a column header.
 +
 
 +
===Set Deadline Properties Form===
 +
 
 +
5) To '''edit''' the format of all '''deadlines''', click the '''Deadline Properties...''' button, to access the '''Set deadline properties''' form shown below:
 +
 
 +
<center>[[File:X70-10_9_1-70-(4)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(4)-09192019.png</center>
 +
 
 +
6) The form above provides all the '''editing''' controls for '''all deadline shapes''' that can be displayed in the chart.
 +
 
 +
====Standard Basic Deadline Shape Controls====
 +
 
 +
7) As stated previously, many of the controls in this group of the '''Set deadline properties''' form are standard.
 +
 
 +
:a) The '''deadline shapes''' available are the same as '''Milestone shapes''' found in the '''Milestones''' tab of the '''Template''' and '''Chart Properties''' forms
 +
 
 +
:b) Likewise, the '''Fill patterns''' available are the same for Task Bars and Milestone shapes also found on their respective tabs of the '''Template''' and '''Chart Properties''' forms.
 +
 
 +
:c) The '''Height percentage''' control represents the percentage of the total task/milestone '''height''' itself, is covered elsewhere and behaves in a standard way.  The default '''Height percentage''' is 100%.
 +
 
 +
8) Similarly, the '''Transparency''' control for the '''deadline''' operates in the same way as '''transparency''' controls for other objects. 
 +
 
 +
:a) The higher the value selected, the greater the '''transparency'''.
 +
 
 +
:b) Conversely, the low the value selected, the more solid the deadline appears.
 +
 
 +
9) The '''Field''' dropdown in the upper right of the form allows you to select another Microsoft Excel '''source plan date field''' instead of the default '''Deadline''' field.
 +
 
 +
10) Contents of the '''Field''' dropdown list is shown below:
 +
 
 +
<center>[[File:X70-10_9_1-70-(5A)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(5A)-09192019.png</center>
 +
 
 +
11) The '''Position''' of the '''deadline''' has a unique meaning.  
 +
 
 +
:a) '''Deadlines''' are always associated with a task/milestone and can be to the left, within, or to the right of the task/milestone itself depending on your Microsoft Excel '''source plan''' data for the task’s '''start''', '''finish''' and '''deadline dates'''.   
 +
 
 +
:b) The position in this context is about where within the task/milestone’s row area vertically the '''deadline''' should be placed.  
 +
 
 +
:c) There are three available positions for the placement of the deadline with respect to the task:  
  
 
::(1) centered in the task,
 
::(1) centered in the task,
Line 37: Line 88:
 
::(3) below the task as shown below:
 
::(3) below the task as shown below:
  
<center>[[File:X52-10_10-(5)-06082015.png]]</center>
+
<center>[[File:X70-10_9_1-70-(5)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(5)-09192019.png</center>
 +
 
 +
12) The '''Use custom color''' checkbox can be checked '''On''' when it is desired to select a '''color''' for the '''deadline''' other than the '''color''' for its parent task/milestone. 
 +
 
 +
:a) When the '''Use custom color''' checkbox is checked '''On''', the '''Custom color''' dropdown is '''enabled.
 +
 
 +
:b) Clicking the dropdown button shows the standard '''Color Chooser''' form.
 +
 
 +
====Showing Deadline Delays====
 +
 
 +
13) The purpose of the display of '''Deadline Delays''' is to provide you with the capability to highlight '''deadlines''' that are '''missed''' as shown in the chart.
 +
 
 +
14) When the '''Color-code delays''' checkbox is checked '''On''', OnePager uses the selected '''Delay color''' (determined by the selection of the '''delay color''' from the '''Color Chooser''' form) to show all '''deadlines''' that are '''missed''':
 +
 
 +
<center>[[File:X70-10_9_1-70-(8)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(8)-09192019.png</center>
 +
 
 +
15) The '''deadline delay''' feature follows this logic:
 +
 
 +
:a) The '''deadline''' is set to the selected '''Delay color''' if, for any '''deadline''':
 +
 
 +
::(1) The '''Color-code delays''' checkbox is checked '''On''',
 +
 
 +
::(2) The '''deadline date''' is earlier than the '''current snapshot date''',
 +
 
 +
::(3)  And the '''percent (%) complete''' for the parent task/milestone is less than 100%.
 +
 
 +
:b) If any of the conditions stated above are not met, the '''color''' of the '''deadline''' is set to the default '''color''', unless a '''custom color''' is otherwise specified.
 +
 
 +
16) To illustrate the operation of the '''Color-code delay''' feature, let's set the stage by supposing that a project of three tasks is has the following initial conditions:
 +
 
 +
:::* Project Start Date – 10/1/2019
 +
:::* Project Finish Date (Estimated) – 10/18/2019
 +
:::* First Status Date – 9/11/2019
 +
:::* Task A Deadline Date – 10/19/2019 (Task A Finish Date projected before Deadline Date)
 +
:::* Task B Deadline Date – 10/10/2019 (Task B Finish Date beyond Deadline Date)
 +
:::* Task C Deadline Date- 10/1/2019 (Task C Start Date beyond Deadline Date)
 +
 
 +
17) With these initial conditions, the Microsoft Project '''source plan''' looks like this:
 +
 
 +
<center>[[File:X70-10_9_1-70-(9)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(9)-09192019.png</center>
 +
 
 +
18) If we take a snapshot using the above '''source plan''' as of '''10/10/2019''' the cart looks like this:
 +
 
 +
<center>[[File:X70-10_9_1-70-(10)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(10)-09192019.png</center>
 +
 
 +
19) OnePager Express treats the '''snapshot date''' similar to the way Microsoft Project treats its '''Status date''' field.
 +
 
 +
====Connecting Lines====
 +
 
 +
20) The '''Connecting Lines''' control group of the '''Set deadline properties''' form deals with '''connecting lines properties''' when you require that '''deadline shapes''' are tied to their parent task/milestone shape.
 +
 
 +
21) The controls available are shown below:
 +
 
 +
<center>[[File:X70-10_9_1-70-(6)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(6)-09192019.png</center>
 +
 
 +
22) To '''enable deadline shape connection lines''', check the '''Connect deadline markers to current markers''' checkbox '''On''' as shown above.
 +
 
 +
23) A default '''color''', '''line style''', and '''line width''' is established from your '''current Template'''.
 +
 
 +
24) If you wish to specify a '''custom color''', check the '''Use custom color''' checkbox '''On''' and use the '''Custom color''' dropdown button to access the standard '''Color Chooser''' form.
 +
 
 +
25)  You also have the option of selecting from a variety of '''line styles''' by clicking on the '''Line style''' dropdown button.
 +
 
 +
:a) There are five (5) standard '''line styles''' to select from which are the same as used to connect '''Baselines''' to their parent task/milestones shapes as described at this link: [[Baselines for Version 7.0 (OnePager Express)#Connect Baselines and Acturals | Baselines for OnePager Express - Connect Baselines and Acturals]] 10.6.1-70.
 +
 
 +
:b) The value dial to the right of the '''Line style''' dropdown provides the capability to '''edit''' the '''width''' of the '''deadline shape connection line'''.
 +
 
 +
22) The form above shows the extent of control that you have over the lines that can be used to connect a '''deadline''' to its parent task/milestone.  These include the specification of a '''custom color''', '''line width''' and '''line style'''.
 +
 
 +
====Deadline Dates====
 +
 
 +
23)  The '''Deadline Dates''' control group in the '''Set deadline properties''' form provides the controls for turning '''On''' and '''positioning''' the '''deadline date text labels''' as shown below:
 +
 
 +
<center>[[File:X70-10_9_1-70-(7)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(7)-09192019.png</center>
 +
 
 +
24) The form above shows the extent of control that you have over the display of '''date labels''' for '''deadlines'''.
  
:c) '''Height''' The '''height''' of the '''deadline''', which is a percentage of the total '''height''' of the task/milestone itself, is covered elsewhere and behaves in a standard way.  
+
:a) These are the same controls as for other '''decoration date''' specifications and include controls for '''date format''', the use of the '''fiscal year''' feature, the positioning of the '''date label''' text, and the '''font properties''' for the '''date label''' text.  
  
:d) Similarly, the '''Transparency''' control for the '''deadline''' operates in the same way as '''transparency''' controls for other objects. The higher the value selected, the greater the '''transparency'''. Conversely, the low the value selected, the more solid the deadline appears.
+
:b) For more specific information about the controls in this control group, please reference the corresponding section for '''Baseline Decorations''' at this link: [[Baselines for Version 7.0 (OnePager Express)#Showing Baseline Dates | Baselines for OnePager Express - Showing Baseline Dates]] 10.6.1-70.
  
:e)  '''Custom Color'''.  The '''Use custom color''' checkbox can be checked when it is desired to select a '''color''' for the '''deadline''' other than the '''color''' for its parent task/milestone.  When the '''Use custom color''' checkbox is checked, the '''Custom color''' dropdown is activated and clicking the dropdown button shows the standard '''Color Chooser''' form.
+
==Editing Individual Deadline Properties==
  
:f) '''Connections'''.  The central group of the '''Set deadline properties''' form deals with '''connecting lines'''. The controls available are shown below:
+
1) '''Deadline''' displays are normally turned '''Off''' in distributed '''Templates'''.
  
<center>[[File:X52-10_10-(6)-06082015.png]]</center>
+
2) In addition to the capabilities for '''editing all Deadline properties''' using the '''Template''' and/or '''Chart Properties''' forms, you can select and individually '''edit Deadline properties''' showing in the chart as follows:
  
:The form above shows the extent of control that you have over the lines that can be used to connect a '''deadline''' to its parent task/milestone.  These include the specification of a '''custom color''', '''line width''' and '''line style'''.  
+
3) As a prerequisite for '''editing''' individual '''deadline''' properties it is the necessity for '''deadline''' data to be '''imported''' from the Microsoft Project '''source plan'''.  
  
:g) '''Setting Date Labels for Deadline'''. The lower group of the '''Set deadline properties''' form holds the controls for turning on and positioning the '''date labels''' for '''deadlines'''. This group of the form looks like this:
+
===Selecting Individual Task or Tasks===
  
<center>[[File:P60-10_9_1-60-(7)-01102017.png]]</center>
+
4) Some individual task '''deadline''' properties can be '''edited''' by selecting the desired task or tasks with a left-click operation and then right-clicking one of the selected tasks to show the '''context menu''' below:
<center>P60-10_9_1-60-(7)-01102017.png</center>
+
  
::i) The form above shows the extent of control that you have over the display of '''date labels''' for '''deadlines'''.  
+
<center>[[File:X70-10_9_1-70-(11)-09192019.png]]</center>
::ii) These are the same controls as for other '''decoration date''' specifications and include the specification of '''date format''', the use of the '''fiscal year''' feature, the positioning of the '''date label''' text, and the '''font properties''' for the '''date label''' text.
+
<center>X70-10_9_1-70-(11)-09192019.png</center>
::iii) The illustration in the following sub-section shows an example of a '''deadline date labels''' which are positioned below their respect '''deadline'''.
+
  
:h) '''Showing Deadline Delays'''.  When the '''Color-code delays''' checkbox is checked, OnePager uses the selected '''Delay color''' (determined by the selection of the '''delay color''' from the '''Color Chooser''' form to show all '''deadlines''' that have been missed:
+
===Accessing the Change Task/Milestone Properties Form===
  
<center>[[File:P60-10_9_1-60-(8)-02102017.png]]</center>
+
5) Select the '''Format…''' command which access the '''Change Task/Milestone Properties''' form.  
<center>P60-10_9_1-60-(8)-02102017.png</center>
+
  
:i) The deadline-delay feature follows this logic:
+
6) Next, navigate to the '''Deadlines''' tab, which displays the '''deadline''' control options shown below:
  
::i) The '''deadline''' is set to the selected '''Delay color''' if, for any '''deadline''', the '''Color-code delays''' checkbox is checked, the '''deadline date''' is earlier than the '''current snapshot date''' and the '''percent (%) complete''' for the parent task/milestone  is less than 100%
+
<center>[[File:X70-10_9_1-70-(12)-09192019.png]]</center>
::ii) If any of the conditions stated in the previous paragraph are not met, the '''color''' of the '''deadline''' is set to the default '''color''', unless a '''custom color''' is otherwise specified.
+
<center>X70-10_9_1-70-(12)-09192019.png</center>
::iii) This section illustrates the use of the '''deadline''' '''Color-Code Delay''' features. To set the stage, suppose we have a project of three tasks with the following initial conditions:
+
  
:::* Project Start Date – 10/1/2015
+
7) The '''Deadlines''' tab, shown above controls the display of '''deadline connectors''' and '''deadline text dates''' for the selected task/milestone and the placement of the '''deadline text dates''' with respect to the '''deadline shape'''.
:::* Project Finish Date (Estimated) – 10/16/2015
+
:::* First Status Date – 9/11/2015
+
:::* Task A Deadline Date – 10/10/2015 (Task A Finish projected before deadline)
+
:::* Task B Deadline Date – 10/10/2015 (Task B Finish beyond deadline date)
+
:::* Task C Deadline Date- 10/1/2015 (Task C Start beyond deadline date)
+
  
:j) With these initial conditions, the Microsoft Excel '''source plan''' looks like this:
+
:a) The '''Show Deadline''' checkbox allows you to turn '''On''' and '''Off''' the display of '''deadline''' information for the selected task/milestone.
  
<center>[[File:X52-10_10-(9)-06082015.png]]</center>
+
:b) When the '''Show Deadline''' checkbox is checked '''On''', you have the option to specify the display of the '''connector''' and the display of '''deadline date''' for the selected task/milestone.
  
:k) Creating the chart of the above schedule with '''OPX''' you’ll see the following:
+
8) When the '''Show Deadline Date Label''' checkbox is checked '''On''' you have access to control over the '''Deadline Date Position''' selection dropdown and '''Deadline Date Font''' selection button as discussed above related to '''editing''' all task/milestone '''deadline information'''.
  
<center>[[File:X52-10_10-(10)-06082015.png]]</center>
+
:a) There are five (5) standard '''deadline date label''' positions to select from.
  
:l) Moving forward in time to the next '''status date''' of 10/5/2015 we can suppose that the '''percent (%) complete''' data for the three Tasks A, B, and C are 50%, 25% and 0% respectively. As a result of this progress, the Microsoft Excel '''source plan''' looks like this:
+
:b) Clicking the '''Deadline Date Font''' button accesses the standard '''Font properties''' form where '''edits''' of the '''deadline date text''' can be made.
  
<center>[[File:X52-10_10-(11)-06082015.png]]</center>
+
===Example===
  
:m) Performing the '''Update''' function with '''OPX''' we get the following snapshot for 10/5/2015:
+
9) Below is an example of a single task's '''deadline information using the chart previously shown in this article:
  
<center>[[File:X52-10_10-(12)-06082015.png]]</center>
+
<center>[[File:X70-10_9_1-70-(13)-09192019.png]]</center>
 +
<center>X70-10_9_1-70-(13)-09192019.png</center>
  
:n) Again, moving forward in time to the next '''status date''' of 11/10/2015, we can further suppose that the '''percent (%) complete''' data for the three Tasks A, B, and C are now 100%, 75% and 100% respectively. As a result of this progress, the Microsoft Excel '''source plan''' looks like this:
+
10) The controls at the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form for the '''Show Deadline Date''', that is, the '''Position''' and '''Font''' controls operate exactly as described for other '''start/finish date''' displays in OnePager.
  
<center>[[File:X52-10_10-(13)-06082015.png]]</center>
+
11)  For reference, please see the corresponding section describing the use of these controls for the '''Percent Complete''' tab of this form at this link: [[Percent complete for Version 7.0 (OnePager Express)#Example | Percent complete for OnePager Express - Example]] 10.4.1-70
  
2) At this point, all '''deadlines''' for all three tasks are exceeded. Performing another '''Update''' with '''OPX''', we get the following snapshot for 11/10/2015:
+
12) There are no controls available in the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form to '''edit''' the properties of the '''connector line''' for an '''individually''' selected task/milestone.
  
<center>[[File:X52-10_10-(14)-06082015.png]]</center>
+
==Related Links==
  
==Modifying Individual Deadline Properties==
+
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] 9.0.1-70
  
1) '''Deadline''' properties can be set or changed for individual tasks.  
+
[[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] 9.2.1-70
  
2) A prerequisite for modifying individual '''deadline''' properties is the necessity for '''deadline''' data to be imported from the Microsoft Excel '''source plan'''. Some individual task '''deadline''' properties can be changed by selecting the desired task or tasks with a left-click operation and then right-clicking one of the selected task to show the '''context menu''' below:
+
[[Labeling Task/Milestone Dates for Version 7.0 (OnePager Express) | Labeling Task/Milestone Dates for OnePager Express]] 10.2.1-70
  
<center>[[File:X53-10_10_1-53-(15)-03082016.png]]</center>
+
[[Percent complete for Version 7.0 (OnePager Express) | Percent complete for OnePager Express]] 10.4.1-70
  
:a) Select the '''Format…''' command which brings up the '''Change Task/Milestone Properties''' form. Next, navigate to the '''Deadlines''' tab, which displays the '''deadline''' control options shown below:
+
[[Baselines for Version 7.0 (OnePager Express) | Baselines for OnePager Express]] 10.6.1-70
  
<center> [[File:P53-10_9_1-53-(16)-03082016.png]]</center>
+
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] 21.0.1-70
  
:b) From the '''Deadlines''' tab of the form above, you are able to turn the selected '''deadline''' off or on, show the '''deadline''' connector to the task and display or turn off the '''deadline''' date label.
+
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] 24.0.1-70
  
 
(10.10.1-70)
 
(10.10.1-70)

Revision as of 16:27, 19 September 2019

About Deadlines

1) OnePager translates Deadlines from your Microsoft Excel source plan into deadline shapes in the graph to indicate the deadline date for a task or milestone.

a) In order to import deadline date information, your Microsoft Excel source plan must have a column header with a name similar to the word deadline.
b) OnePager Express does its best to translate similar names to deadline date information and import this data.
c) You always have the option to specifically designate a Microsoft Excel column header name as your specific set of dates specifying deadlines.
d) This option is available in the OnePager Express Template and Chart Properties form at the Task Bars tab as is explained later in this article.

2) To illustrate with a simple example, consider the Microsoft Excel source plan given below with three tasks containing Start and Finish dates, a deadline date, and a Flag with the header Show It set to Yes so that OnePager imports the data for all three tasks:

X70-10 9 1-70-(1-1)-09192019.png
X70-10_9_1-70-(1-1)-09192019.png

3) When a simple chart is created from the source plan above and Deadlines are turned On, the example chart looks like this:

X70-10 9 1-70-(2)-09192019.png
X70-10_9_1-70-(2)-09192019.png
a) When deadlines are turned on, they appear (by default) as red arrow shape in each task bar's row at the deadline date position with respect to the time axis.
b) Above, deadline shapes that are not contained within their respective task bar are shown with back dash-dot connecting lines to illustrate the capability.

Editing All Deadline Properties

1) To display deadline dates in your charts you must first assure that the Microsoft Excel source plan has a Deadline field populated with valid dates.

2) When deadline dates are present in the source plan they must first be turned On as the default setting in most distributed Templates is for deadlines to be turned Off.

3) To do this click the Chart Properties button on the OnePager Home tab to access the Chart Properties form.

4) Next, navigate to the Chart Properties Task Bars tab and to the Task Bars Decoration control group as shown below:

a) Check the Deadline markers checkbox On to enable the Deadline Properties... button to the immediate right of the checkbox as shown below:
File:X70-10 9 1-70-(3)-09192019.png
X70-10_9_1-70-(3)-09192019.png
b) By default, deadlines are mapped to the Deadline date field in Microsoft Excel if that field is present as a column header.

Set Deadline Properties Form

5) To edit the format of all deadlines, click the Deadline Properties... button, to access the Set deadline properties form shown below:

File:X70-10 9 1-70-(4)-09192019.png
X70-10_9_1-70-(4)-09192019.png

6) The form above provides all the editing controls for all deadline shapes that can be displayed in the chart.

Standard Basic Deadline Shape Controls

7) As stated previously, many of the controls in this group of the Set deadline properties form are standard.

a) The deadline shapes available are the same as Milestone shapes found in the Milestones tab of the Template and Chart Properties forms
b) Likewise, the Fill patterns available are the same for Task Bars and Milestone shapes also found on their respective tabs of the Template and Chart Properties forms.
c) The Height percentage control represents the percentage of the total task/milestone height itself, is covered elsewhere and behaves in a standard way. The default Height percentage is 100%.

8) Similarly, the Transparency control for the deadline operates in the same way as transparency controls for other objects.

a) The higher the value selected, the greater the transparency.
b) Conversely, the low the value selected, the more solid the deadline appears.

9) The Field dropdown in the upper right of the form allows you to select another Microsoft Excel source plan date field instead of the default Deadline field.

10) Contents of the Field dropdown list is shown below:

X70-10 9 1-70-(5A)-09192019.png
X70-10_9_1-70-(5A)-09192019.png

11) The Position of the deadline has a unique meaning.

a) Deadlines are always associated with a task/milestone and can be to the left, within, or to the right of the task/milestone itself depending on your Microsoft Excel source plan data for the task’s start, finish and deadline dates.
b) The position in this context is about where within the task/milestone’s row area vertically the deadline should be placed.
c) There are three available positions for the placement of the deadline with respect to the task:
(1) centered in the task,
(2) above the task/milestone, or
(3) below the task as shown below:
X70-10 9 1-70-(5)-09192019.png
X70-10_9_1-70-(5)-09192019.png

12) The Use custom color checkbox can be checked On when it is desired to select a color for the deadline other than the color for its parent task/milestone.

a) When the Use custom color checkbox is checked On, the Custom color dropdown is enabled.
b) Clicking the dropdown button shows the standard Color Chooser form.

Showing Deadline Delays

13) The purpose of the display of Deadline Delays is to provide you with the capability to highlight deadlines that are missed as shown in the chart.

14) When the Color-code delays checkbox is checked On, OnePager uses the selected Delay color (determined by the selection of the delay color from the Color Chooser form) to show all deadlines that are missed:

X70-10 9 1-70-(8)-09192019.png
X70-10_9_1-70-(8)-09192019.png

15) The deadline delay feature follows this logic:

a) The deadline is set to the selected Delay color if, for any deadline:
(1) The Color-code delays checkbox is checked On,
(2) The deadline date is earlier than the current snapshot date,
(3) And the percent (%) complete for the parent task/milestone is less than 100%.
b) If any of the conditions stated above are not met, the color of the deadline is set to the default color, unless a custom color is otherwise specified.

16) To illustrate the operation of the Color-code delay feature, let's set the stage by supposing that a project of three tasks is has the following initial conditions:

  • Project Start Date – 10/1/2019
  • Project Finish Date (Estimated) – 10/18/2019
  • First Status Date – 9/11/2019
  • Task A Deadline Date – 10/19/2019 (Task A Finish Date projected before Deadline Date)
  • Task B Deadline Date – 10/10/2019 (Task B Finish Date beyond Deadline Date)
  • Task C Deadline Date- 10/1/2019 (Task C Start Date beyond Deadline Date)

17) With these initial conditions, the Microsoft Project source plan looks like this:

X70-10 9 1-70-(9)-09192019.png
X70-10_9_1-70-(9)-09192019.png

18) If we take a snapshot using the above source plan as of 10/10/2019 the cart looks like this:

X70-10 9 1-70-(10)-09192019.png
X70-10_9_1-70-(10)-09192019.png

19) OnePager Express treats the snapshot date similar to the way Microsoft Project treats its Status date field.

Connecting Lines

20) The Connecting Lines control group of the Set deadline properties form deals with connecting lines properties when you require that deadline shapes are tied to their parent task/milestone shape.

21) The controls available are shown below:

X70-10 9 1-70-(6)-09192019.png
X70-10_9_1-70-(6)-09192019.png

22) To enable deadline shape connection lines, check the Connect deadline markers to current markers checkbox On as shown above.

23) A default color, line style, and line width is established from your current Template.

24) If you wish to specify a custom color, check the Use custom color checkbox On and use the Custom color dropdown button to access the standard Color Chooser form.

25) You also have the option of selecting from a variety of line styles by clicking on the Line style dropdown button.

a) There are five (5) standard line styles to select from which are the same as used to connect Baselines to their parent task/milestones shapes as described at this link: Baselines for OnePager Express - Connect Baselines and Acturals 10.6.1-70.
b) The value dial to the right of the Line style dropdown provides the capability to edit the width of the deadline shape connection line.

22) The form above shows the extent of control that you have over the lines that can be used to connect a deadline to its parent task/milestone. These include the specification of a custom color, line width and line style.

Deadline Dates

23) The Deadline Dates control group in the Set deadline properties form provides the controls for turning On and positioning the deadline date text labels as shown below:

X70-10 9 1-70-(7)-09192019.png
X70-10_9_1-70-(7)-09192019.png

24) The form above shows the extent of control that you have over the display of date labels for deadlines.

a) These are the same controls as for other decoration date specifications and include controls for date format, the use of the fiscal year feature, the positioning of the date label text, and the font properties for the date label text.
b) For more specific information about the controls in this control group, please reference the corresponding section for Baseline Decorations at this link: Baselines for OnePager Express - Showing Baseline Dates 10.6.1-70.

Editing Individual Deadline Properties

1) Deadline displays are normally turned Off in distributed Templates.

2) In addition to the capabilities for editing all Deadline properties using the Template and/or Chart Properties forms, you can select and individually edit Deadline properties showing in the chart as follows:

3) As a prerequisite for editing individual deadline properties it is the necessity for deadline data to be imported from the Microsoft Project source plan.

Selecting Individual Task or Tasks

4) Some individual task deadline properties can be edited by selecting the desired task or tasks with a left-click operation and then right-clicking one of the selected tasks to show the context menu below:

X70-10 9 1-70-(11)-09192019.png
X70-10_9_1-70-(11)-09192019.png

Accessing the Change Task/Milestone Properties Form

5) Select the Format… command which access the Change Task/Milestone Properties form.

6) Next, navigate to the Deadlines tab, which displays the deadline control options shown below:

File:X70-10 9 1-70-(12)-09192019.png
X70-10_9_1-70-(12)-09192019.png

7) The Deadlines tab, shown above controls the display of deadline connectors and deadline text dates for the selected task/milestone and the placement of the deadline text dates with respect to the deadline shape.

a) The Show Deadline checkbox allows you to turn On and Off the display of deadline information for the selected task/milestone.
b) When the Show Deadline checkbox is checked On, you have the option to specify the display of the connector and the display of deadline date for the selected task/milestone.

8) When the Show Deadline Date Label checkbox is checked On you have access to control over the Deadline Date Position selection dropdown and Deadline Date Font selection button as discussed above related to editing all task/milestone deadline information.

a) There are five (5) standard deadline date label positions to select from.
b) Clicking the Deadline Date Font button accesses the standard Font properties form where edits of the deadline date text can be made.

Example

9) Below is an example of a single task's deadline information using the chart previously shown in this article:

X70-10 9 1-70-(13)-09192019.png
X70-10_9_1-70-(13)-09192019.png

10) The controls at the Deadline tab of the Change Task/Milestone Properties form for the Show Deadline Date, that is, the Position and Font controls operate exactly as described for other start/finish date displays in OnePager.

11) For reference, please see the corresponding section describing the use of these controls for the Percent Complete tab of this form at this link: Percent complete for OnePager Express - Example 10.4.1-70

12) There are no controls available in the Deadline tab of the Change Task/Milestone Properties form to edit the properties of the connector line for an individually selected task/milestone.

Related Links

Manual Editing Task/Milestone Shapes and Text Labels (Portal) 9.0.1-70

Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.) 9.2.1-70

Labeling Task/Milestone Dates for OnePager Express 10.2.1-70

Percent complete for OnePager Express 10.4.1-70

Baselines for OnePager Express 10.6.1-70

Editing with the Chart Properties form (Portal) 21.0.1-70

Managing Templates (Portal) 24.0.1-70

(10.10.1-70)