Difference between revisions of "Deadlines for Version 7.0 (OnePager Express)"

From OnePager Documentation
Jump to: navigation, search
(About Deadlines)
 
(15 intermediate revisions by 2 users not shown)
Line 1: Line 1:
 
==About Editing Deadlines==
 
==About Editing Deadlines==
  
1) OnePager translates '''Deadlines''' from your Microsoft Excel '''source plan''' into '''deadline''' shapes in the '''graph''' to indicate the '''deadline date''' for a task or milestone.   
+
OnePager translates '''Deadlines''' from your Microsoft Excel '''source plan''' into '''deadline''' shapes in the '''graph''' to indicate the '''deadline date''' for a task bar/milestone symbol.  In order to '''import''' '''deadline date''' information, your Microsoft Excel '''source plan''' must have a column header with a name similar to the word '''deadline'''. OnePager Express does its best to translate similar names to '''deadline date''' information and '''import''' this data.  You always have the option to specifically designate a Microsoft Excel column header name as your specific set of dates specifying '''deadlines'''. This option is available in the OnePager Express '''Template Properties''' and '''Chart Properties''' form at the '''Task Bars''' tab as is explained later in this article. To illustrate with a simple example, consider the Microsoft Excel '''source plan''' given below with three tasks containing '''Start and Finish dates''', a '''deadline date''', and a '''Flag''' with the header '''Show It set to '''Yes''' so that OnePager '''imports''' the data for all three tasks:
 
+
:a) In order to '''import''' '''deadline date''' information, your Microsoft Excel '''source plan''' must have a column header with a name similar to the word '''deadline'''.
+
 
+
:b) OnePager Express does its best to translate similar names to '''deadline date''' information and '''import''' this data.
+
 
+
:c) You always have the option to specifically designate a Microsoft Excel column header name as your specific set of dates specifying '''deadlines'''.
+
 
+
:d) This option is available in the OnePager Express '''Template''' and '''Chart Properties''' form at the '''Task Bars''' tab as is explained later in this article.
+
 
+
2) To illustrate with a simple example, consider the Microsoft Excel '''source plan''' given below with three tasks containing '''Start and Finish dates''', a '''deadline date''', and a '''Flag''' with the header '''Show It set to '''Yes''' so that OnePager '''imports''' the data for all three tasks:
+
  
 
<center>[[File:X70-10_9_1-70-(1-1)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(1-1)-09192019.png]]</center>
<center>X70-10_9_1-70-(1-1)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(1-1)-09192019.png</center>-->
  
3) When a simple chart is created from the '''source plan''' above and '''Deadlines''' are turned '''On''', the example chart looks like this:
+
When a simple chart is created from the '''source plan''' above and '''Deadlines''' are turned '''ON''', the example chart looks like this:
  
 
<center>[[File:X70-10_9_1-70-(2)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(2)-09192019.png]]</center>
<center>X70-10_9_1-70-(2)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(2)-09192019.png</center>-->
 
+
:a) When '''deadlines''' are turned on, they appear (by default) as '''red arrow shape''' in each task bar's row at the '''deadline date''' position with respect to the '''time axis'''.
+
  
:b) Above, '''deadline shapes''' that are not contained within their respective task bar are shown with '''back dash-dot connecting lines''' to illustrate the capability.
+
When '''deadlines''' are turned '''ON''', they appear (by default) as '''red arrow shape''' in each task bar's row at the '''deadline date''' position with respect to the '''time axis'''. Above, '''deadline shapes''' that are not contained within their respective task bar are shown with '''back dash-dot connecting lines''' to illustrate the capability.
  
 
==Editing All Deadline Properties==
 
==Editing All Deadline Properties==
  
1) To display '''deadline dates''' in your charts you must first assure that the Microsoft Excel '''source plan''' has a '''Deadline''' field populated with valid '''dates'''.
+
To display '''deadline dates''' in your charts you must first assure that the Microsoft Excel '''source plan''' has a '''Deadline''' field populated with valid '''dates'''. When '''deadline dates''' are present in the '''source plan''' they must first be turned '''ON''' as the default setting in most distributed '''Template Properties''' form is for '''deadlines''' to be turned '''OFF'''. To do this click the '''Chart Properties''' button on the OnePager '''Home''' tab to access the '''Chart Properties''' form. Next, navigate to the '''Chart Properties''' '''Task Bars''' tab and to the '''Task Bars Decoration''' control group. Check the '''Deadline markers''' checkbox '''ON''' to '''enable''' the '''Deadline Properties...''' button to the immediate right of the checkbox as shown below:
  
2) When '''deadline dates''' are present in the '''source plan''' they must first be turned '''On''' as the default setting in most distributed '''Templates''' is for '''deadlines''' to be turned '''Off'''.
+
<center>[[File:X70-10_10_1-70-(3-1)-09222020.png]]</center>
 +
<!--<center>X70-10_10_1-70-(3-1)-09222020.png</center>-->
  
3) To do this click the '''Chart Properties''' button on the OnePager '''Home''' tab to access the '''Chart Properties''' form.
+
By default, '''deadlines''' are mapped to the '''Deadline date''' field in Microsoft Excel if that field is present as a column header.
 
+
4) Next, navigate to the '''Chart Properties''' '''Task Bars''' tab and to the '''Task Bars Decoration''' control group as shown below:
+
 
+
:a) Check the '''Deadline markers''' checkbox '''On''' to '''enable''' the '''Deadline Properties...''' button to the immediate right of the checkbox as shown below:
+
 
+
<center>[[File:X70-10_9_1-70-(3)-09192019.png]]</center>
+
<center>X70-10_9_1-70-(3)-09192019.png</center>
+
 
+
:b) By default, '''deadlines''' are mapped to the '''Deadline date''' field in Microsoft Excel if that field is present as a column header.
+
  
 
===Set Deadline Properties Form===  
 
===Set Deadline Properties Form===  
  
5) To '''edit''' the format of all '''deadlines''', click the '''Deadline Properties...''' button, to access the '''Set deadline properties''' form shown below:
+
To '''edit''' the format of all '''deadlines''', click the '''Deadline Properties...''' button, to access the '''Set deadline properties''' form shown below:
  
<center>[[File:X70-10_9_1-70-(4)-09192019.png]]</center>
+
<center>[[File:X70-10_10_1-70-(4-1)-09222020.png]]</center>
<center>X70-10_9_1-70-(4)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(4-1)-09222020.png</center>-->
  
6) The form above provides all the '''editing''' controls for '''all deadline shapes''' that can be displayed in the chart.
+
The form above provides all the '''editing''' controls for '''all deadline shapes''' that can be displayed in the chart.
  
 
====Standard Basic Deadline Shape Controls====
 
====Standard Basic Deadline Shape Controls====
  
7) As stated previously, many of the controls in this group of the '''Set deadline properties''' form are standard.  
+
As stated previously, many of the controls in this group of the '''Set deadline properties''' form are standard.  The '''deadline shapes''' available are the same as '''Milestone symbols''' found in the '''Milestones''' tab of the '''Template Properties''' and '''Chart Properties''' forms Likewise, the '''Fill patterns''' available are the same for task bars and milestone symbols also found on their respective tabs of the '''Template Properties''' and '''Chart Properties''' forms.
  
:a) The '''deadline shapes''' available are the same as '''Milestone shapes''' found in the '''Milestones''' tab of the '''Template''' and '''Chart Properties''' forms
+
The '''Height percentage''' control represents the percentage of the total task bar/milestone symbol's '''height''' itself, is covered elsewhere and behaves in a standard way.  The default '''Height percentage''' is 100%.
  
:b) Likewise, the '''Fill patterns''' available are the same for Task Bars and Milestone shapes also found on their respective tabs of the '''Template''' and '''Chart Properties''' forms.
+
Similarly, the '''Transparency''' control for the '''deadline''' operates in the same way as '''transparency''' controls for other objects.  The higher the value selected, the greater the '''transparency'''.  Conversely, the low the value selected, the more solid the deadline appears.
  
:c) The '''Height percentage''' control represents the percentage of the total task/milestone '''height''' itself, is covered elsewhere and behaves in a standard way.  The default '''Height percentage''' is 100%.
+
The '''Field''' dropdown in the upper right of the form allows you to select another Microsoft Excel '''source plan date field''' instead of the default '''Deadline''' field. Contents of the '''Field''' dropdown list is shown below:
 
+
8) Similarly, the '''Transparency''' control for the '''deadline''' operates in the same way as '''transparency''' controls for other objects. 
+
 
+
:a) The higher the value selected, the greater the '''transparency'''.
+
 
+
:b) Conversely, the low the value selected, the more solid the deadline appears.
+
 
+
9) The '''Field''' dropdown in the upper right of the form allows you to select another Microsoft Excel '''source plan date field''' instead of the default '''Deadline''' field.  
+
 
+
10) Contents of the '''Field''' dropdown list is shown below:
+
  
 
<center>[[File:X70-10_9_1-70-(5A)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(5A)-09192019.png]]</center>
<center>X70-10_9_1-70-(5A)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(5A)-09192019.png</center>-->
 
+
11) The '''Position''' of the '''deadline''' has a unique meaning.
+
 
+
:a) '''Deadlines''' are always associated with a task/milestone and can be to the left, within, or to the right of the task/milestone itself depending on your Microsoft Excel '''source plan''' data for the task’s '''start''', '''finish''' and '''deadline dates'''. 
+
 
+
:b) The position in this context is about where within the task/milestone’s row area vertically the '''deadline''' should be placed.
+
 
+
:c) There are three available positions for the placement of the deadline with respect to the task:
+
 
+
::(1) centered in the task,
+
  
::(2) above the task/milestone, or  
+
The '''Position''' of the '''deadline''' has a unique meaning.  '''Deadlines''' are always associated with a task bar/milestone symbol and can be to the left, within, or to the right of the task bar/milestone ssymbol itself depending on your Microsoft Excel '''source plan''' data for the task bar’s '''start''', '''finish''' and '''deadline dates'''.  The position in this context is about where within the task bar/milestone symbol’s row area vertically the '''deadline''' should be placed. There are three (3) available positions for the placement of the deadline with respect to the task bar:
  
::(3) below the task as shown below:
+
:* '''Centered''' in the task bar.
 +
:* '''Above''' the task bar/milestone symbol.
 +
:* '''Below''' the task bar as shown here:
  
 
<center>[[File:X70-10_9_1-70-(5)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(5)-09192019.png]]</center>
<center>X70-10_9_1-70-(5)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(5)-09192019.png</center>-->
  
12) The '''Use custom color''' checkbox can be checked '''On''' when it is desired to select a '''color''' for the '''deadline''' other than the '''color''' for its parent task/milestone.   
+
The '''Use custom color''' checkbox can be checked '''ON''' when it is desired to select a '''color''' for the '''deadline''' other than the '''color''' for its parent task bar/milestone symbol.  When the '''Use custom color''' checkbox is checked '''ON''', the '''Custom color''' dropdown is '''enabled. Clicking the dropdown button shows the standard '''Color Chooser''' form.
 
+
:a) When the '''Use custom color''' checkbox is checked '''On''', the '''Custom color''' dropdown is '''enabled.
+
 
+
:b) Clicking the dropdown button shows the standard '''Color Chooser''' form.
+
  
 
====Showing Deadline Delays====
 
====Showing Deadline Delays====
  
13) The purpose of the display of '''Deadline Delays''' is to provide you with the capability to highlight '''deadlines''' that are '''missed''' as shown in the chart.
+
The purpose of the display of '''Deadline Delays''' is to provide you with the capability to highlight '''deadlines''' that are '''missed''' as shown in the chart. When the '''Color-code delays''' checkbox is checked '''ON''', OnePager uses the selected '''Delay color''' (determined by the selection of the '''delay color''' from the standard '''Color Chooser''' form) to show all '''deadlines''' that are '''missed''':
 
+
14) When the '''Color-code delays''' checkbox is checked '''On''', OnePager uses the selected '''Delay color''' (determined by the selection of the '''delay color''' from the '''Color Chooser''' form) to show all '''deadlines''' that are '''missed''':
+
  
 
<center>[[File:X70-10_9_1-70-(8)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(8)-09192019.png]]</center>
<center>X70-10_9_1-70-(8)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(8)-09192019.png</center>-->
  
15) The '''deadline delay''' feature follows this logic:
+
The '''deadline delay''' feature follows this logic. The '''deadline''' is set to the selected '''Delay color''' if, for any '''deadline''':  
  
:a) The '''deadline''' is set to the selected '''Delay color''' if, for any '''deadline''':  
+
:* The '''Color-code delays''' checkbox is checked '''ON''',  
 +
:* The '''deadline date''' is earlier than the '''current snapshot date''',
 +
:*  And the '''percent (%) complete''' for the parent task bar/milestone symbol is less than 100%.
  
::(1) The '''Color-code delays''' checkbox is checked '''On''',  
+
If any of the conditions stated above are not met, the '''color''' of the '''deadline''' is set to the default '''color''', unless a '''custom color''' is otherwise specified.
  
::(2) The '''deadline date''' is earlier than the '''current snapshot date''',
+
====Example Deadline Date Delay====
  
::(3)  And the '''percent (%) complete''' for the parent task/milestone is less than 100%.
+
To illustrate the operation of the '''Color-code delay''' feature, let's set the stage by supposing that a project of three tasks is has the following initial conditions:
  
:b) If any of the conditions stated above are not met, the '''color''' of the '''deadline''' is set to the default '''color''', unless a '''custom color''' is otherwise specified.
+
:* Project Start Date – 10/1/2019
 +
:* Project Finish Date (Estimated) – 10/18/2019
 +
:* First Status Date – 9/11/2019
 +
:* Task A Deadline Date – 10/19/2019 (Task A Finish Date projected before Deadline Date)
 +
:* Task B Deadline Date – 10/10/2019 (Task B Finish Date beyond Deadline Date)
 +
:* Task C Deadline Date- 10/1/2019 (Task C Start Date beyond Deadline Date)
  
16) To illustrate the operation of the '''Color-code delay''' feature, let's set the stage by supposing that a project of three tasks is has the following initial conditions:
+
With these initial conditions, the Microsoft Project '''source plan''' looks like this:
 
+
:::* Project Start Date – 10/1/2019
+
:::* Project Finish Date (Estimated) – 10/18/2019
+
:::* First Status Date – 9/11/2019
+
:::* Task A Deadline Date – 10/19/2019 (Task A Finish Date projected before Deadline Date)
+
:::* Task B Deadline Date – 10/10/2019 (Task B Finish Date beyond Deadline Date)
+
:::* Task C Deadline Date- 10/1/2019 (Task C Start Date beyond Deadline Date)
+
 
+
17) With these initial conditions, the Microsoft Project '''source plan''' looks like this:
+
  
 
<center>[[File:X70-10_9_1-70-(9)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(9)-09192019.png]]</center>
<center>X70-10_9_1-70-(9)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(9)-09192019.png</center>-->
  
18) If we take a snapshot using the above '''source plan''' as of '''10/10/2019''' the cart looks like this:
+
If we take a snapshot using the above '''source plan''' as of '''10/10/2019''' the chart looks like this:
  
 
<center>[[File:X70-10_9_1-70-(10)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(10)-09192019.png]]</center>
<center>X70-10_9_1-70-(10)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(10)-09192019.png</center>-->
  
19) OnePager Express treats the '''snapshot date''' similar to the way Microsoft Project treats its '''Status date''' field.
+
OnePager Express treats the '''snapshot date''' similar to the way Microsoft Project treats its '''Status date''' field.
  
 
====Connecting Lines====
 
====Connecting Lines====
  
20) The '''Connecting Lines''' control group of the '''Set deadline properties''' form deals with '''connecting lines properties''' when you require that '''deadline shapes''' are tied to their parent task/milestone shape.
+
The '''Connecting Lines''' control group of the '''Set deadline properties''' form deals with '''connecting lines properties''' when you require that '''deadline shapes''' are tied to their parent task bar/milestone symbol. The controls available are shown below:
 
+
21) The controls available are shown below:
+
  
 
<center>[[File:X70-10_9_1-70-(6)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(6)-09192019.png]]</center>
<center>X70-10_9_1-70-(6)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(6)-09192019.png</center>-->
  
22) To '''enable deadline shape connection lines''', check the '''Connect deadline markers to current markers''' checkbox '''On''' as shown above.
+
To '''enable deadline shape connection lines''', check the '''Connect deadline markers to current markers''' checkbox '''ON''' as shown above. A default '''color''', '''line style''', and '''line width''' is established from your '''current Template'''. If you wish to specify a '''custom color''', check the '''Use custom color''' checkbox '''ON''' and use the '''Custom color''' dropdown button to access the standard '''Color Chooser''' form. 
  
23) A default '''color''', '''line style''', and '''line width''' is established from your '''current Template'''.
+
You also have the option of selecting from a variety of '''line styles''' by clicking on the '''Line style''' dropdown button.  
  
24) If you wish to specify a '''custom color''', check the '''Use custom color''' checkbox '''On''' and use the '''Custom color''' dropdown button to access the standard '''Color Chooser''' form.
+
There are five (5) standard '''line styles''' to select from which are the same as used to connect '''Baselines''' to their parent task bars/milestone symbols as described in the section of the article at: [[Baselines for Version 7.0 (OnePager Express)#Connect Baselines and Actual Task Bars/Milestone Symbols | Baselines for OnePager Express - Connect Baselines and Actual Task Bar/Milestone Symbols]] <!--10.6.1-70-->
  
25)  You also have the option of selecting from a variety of '''line styles''' by clicking on the '''Line style''' dropdown button.
+
The value dial to the right of the '''Line style''' dropdown provides the capability to '''edit''' the '''width''' of the '''deadline shape connection line'''. The form above shows the extent of control that you have over the lines that can be used to connect a '''deadline''' to its parent task bar/milestone symbol.  These include the specification of a '''custom color''', '''line width''' and '''line style'''.
 
+
:a) There are five (5) standard '''line styles''' to select from which are the same as used to connect '''Baselines''' to their parent task/milestones shapes as described at this link: [[Baselines for Version 7.0 (OnePager Express)#Connect Baselines and Acturals | Baselines for OnePager Express - Connect Baselines and Acturals]] 10.6.1-70.
+
 
+
:b) The value dial to the right of the '''Line style''' dropdown provides the capability to '''edit''' the '''width''' of the '''deadline shape connection line'''.
+
 
+
22) The form above shows the extent of control that you have over the lines that can be used to connect a '''deadline''' to its parent task/milestone.  These include the specification of a '''custom color''', '''line width''' and '''line style'''.
+
  
 
====Deadline Dates====
 
====Deadline Dates====
  
23)  The '''Deadline Dates''' control group in the '''Set deadline properties''' form provides the controls for turning '''On''' and '''positioning''' the '''deadline date text labels''' as shown below:  
+
The '''Deadline Dates''' control group in the '''Set deadline properties''' form provides the controls for turning '''ON''' and '''positioning''' the '''deadline date text labels''' as shown below:  
  
 
<center>[[File:X70-10_9_1-70-(7)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(7)-09192019.png]]</center>
<center>X70-10_9_1-70-(7)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(7)-09192019.png</center>-->
  
24) The form above shows the extent of control that you have over the display of '''date labels''' for '''deadlines'''.  
+
The form above shows the extent of control that you have over the display of '''date labels''' for '''deadlines'''.  These are the same controls as for other '''decoration date''' specifications and include controls for '''date format''', the use of the '''fiscal year''' feature, the positioning of the '''date label''' text, and the '''font properties''' for the '''date label''' text.  
  
:a) These are the same controls as for other '''decoration date''' specifications and include controls for '''date format''', the use of the '''fiscal year''' feature, the positioning of the '''date label''' text, and the '''font properties''' for the '''date label''' text.
+
For more specific information about the controls in this control group, please reference the corresponding section for '''Baseline Decorations''' at: [[Baselines for Version 7.0 (OnePager Express)#Showing Baseline Dates | Baselines for OnePager Express - Showing Baseline Dates]] <!--10.6.1-70-->
 
+
:b) For more specific information about the controls in this control group, please reference the corresponding section for '''Baseline Decorations''' at this link: [[Baselines for Version 7.0 (OnePager Express)#Showing Baseline Dates | Baselines for OnePager Express - Showing Baseline Dates]] 10.6.1-70.
+
  
 
==Editing Individual Task Deadline Properties==
 
==Editing Individual Task Deadline Properties==
  
1) '''Deadline''' displays are normally turned '''Off''' in distributed '''Templates'''.   
+
'''Deadline''' displays are normally turned '''OFF''' in distributed '''Template Properties''' formsIn addition to the capabilities for '''editing all Deadline properties''' using the '''Template Properties''' and/or '''Chart Properties''' forms, you can select and individually '''edit Deadline properties''' showing in the chart. As a prerequisite for '''editing''' individual '''deadline''' properties it is the necessity for '''deadline''' data to be '''imported''' from the Microsoft Project '''source plan'''.
  
2)  In addition to the capabilities for '''editing all Deadline properties''' using the '''Template''' and/or '''Chart Properties''' forms, you can select and individually '''edit Deadline properties''' showing in the chart.
+
===Selecting Individual Task Bar or Bars===
  
3) As a prerequisite for '''editing''' individual '''deadline''' properties it is the necessity for '''deadline''' data to be '''imported''' from the Microsoft Project '''source plan'''.
+
Some individual task '''deadline''' properties can be '''edited''' by selecting the desired task bar or task bars with a left-click operation and then right-clicking one of the selected task bars to show the '''task bar''' right-click '''context menu''' below:
  
===Selecting Individual Task or Tasks===
+
<center>[[File:X70-10_9_1-70-(11)-09192019.png]]</center>
 +
<!--<center>X70-10_10_1-70-(11)-09192019.png</center>-->
  
4) Some individual task '''deadline''' properties can be '''edited''' by selecting the desired task or tasks with a left-click operation and then right-clicking one of the selected tasks to show the '''context menu''' below:
+
Before you can do so, you must confirm that the '''Deadline markers''' checkbox in either the '''Template Properties''' or '''Chart Properties''' form's '''Task Bars''' and/or '''Milestones''' tab is checked '''ON'''.
 
+
<center>[[File:X70-10_9_1-70-(11)-09192019.png]]</center>
+
<center>X70-10_9_1-70-(11)-09192019.png</center>
+
  
 
===Accessing the Change Task/Milestone Properties Form===
 
===Accessing the Change Task/Milestone Properties Form===
  
5) Select the '''Format…''' command which access the '''Change Task/Milestone Properties''' form.  
+
Select the '''Format…''' command which access the '''Change Task/Milestone Properties''' form. Next, navigate to the '''Deadlines''' tab, which displays the '''deadline''' control options shown below:
 
+
6) Next, navigate to the '''Deadlines''' tab, which displays the '''deadline''' control options shown below:
+
 
+
<center>[[File:X70-10_9_1-70-(12)-09192019.png]]</center>
+
<center>X70-10_9_1-70-(12)-09192019.png</center>
+
 
+
7) The '''Deadlines''' tab, shown above controls the display of '''deadline connectors''' and '''deadline text dates''' for the selected task/milestone and the placement of the '''deadline text dates''' with respect to the '''deadline shape'''.
+
 
+
:a) The '''Show Deadline''' checkbox allows you to turn '''On''' and '''Off''' the display of '''deadline''' information for the selected task/milestone.
+
 
+
:b) When the '''Show Deadline''' checkbox is checked '''On''', you have the option to specify the display of the '''connector''' and the display of '''deadline date''' for the selected task/milestone.
+
 
+
8) When the '''Show Deadline Date Label''' checkbox is checked '''On''' you have access to control over the '''Deadline Date Position''' selection dropdown and '''Deadline Date Font''' selection button as discussed above related to '''editing''' all task/milestone '''deadline information'''.
+
  
:a) There are five (5) standard '''deadline date label''' positions to select from.
+
<center>[[File:X70-10_10_1-70-(12-1)-09102020.png]]</center>
 +
<!--<center>X70-10_10_1-70-(12-1)-09102020.png</center>-->
  
:b) Clicking the '''Deadline Date Font''' button accesses the standard '''Font properties''' form where '''edits''' of the '''deadline date text''' can be made.
+
The '''Deadlines''' tab, shown above controls the display of '''deadline connectors''' and '''deadline text dates''' for the selected task bar/milestone symbol and the placement of the '''deadline text dates''' with respect to the '''deadline shape'''. The '''Show Deadline''' checkbox allows you to turn '''ON''' and '''OFF''' the display of '''deadline''' information for the selected task bar/milestone symbol. When the '''Show Deadline''' checkbox is checked '''ON''', you have the option to specify the display of the '''connector''' and the display of '''deadline date''' for the selected task bar/milestone symbol. When the '''Show Deadline Date Label''' checkbox is checked '''ON''' you have access to control over the '''Deadline Date Position''' selection dropdown and '''Deadline Date Font''' selection button as discussed above related to '''editing''' all task bar/milestone symbol '''deadline information'''. There are five (5) standard '''deadline date label''' positions to select from. Clicking the '''Deadline Date Font''' button accesses the standard '''Font properties''' form where '''edits''' of the '''deadline date text''' can be made.
  
===Example===
+
===Individually Edited Deadline Shape Example===
  
9) Below is an example of a single task's '''deadline information using the chart previously shown in this article:
+
Below is an example of a single task bar's '''deadline information using the chart previously shown in this article:
  
 
<center>[[File:X70-10_9_1-70-(13)-09192019.png]]</center>
 
<center>[[File:X70-10_9_1-70-(13)-09192019.png]]</center>
<center>X70-10_9_1-70-(13)-09192019.png</center>
+
<!--<center>X70-10_10_1-70-(13)-09192019.png</center>-->
  
10) The controls at the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form for the '''Show Deadline Date''', that is, the '''Position''' and '''Font''' controls operate exactly as described for other '''start/finish date''' displays in OnePager.
+
The controls at the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form for the '''Show Deadline Date''', that is, the '''Position''' and '''Font''' controls operate exactly as described for other '''start/finish date''' displays in OnePager.
  
11)  For reference, please see the corresponding section describing the use of these controls for the '''Percent Complete''' tab of this form at this link: [[Percent complete for Version 7.0 (OnePager Express)#Example | Percent complete for OnePager Express - Example]] 10.4.1-70
+
For more information describing the use of these controls for the '''Percent Complete''' tab of this form, please see the section in the article at: [[Percent complete for Version 7.0 (OnePager Express)#Example | Percent complete for OnePager Express - Example]] <!--10.4.1-70-->
  
12) There are no controls available in the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form to '''edit''' the properties of the '''connector line''' for an '''individually''' selected task/milestone.
+
There are no controls available in the '''Deadline''' tab of the '''Change Task/Milestone Properties''' form to '''edit''' the properties of the '''connector line''' for an '''individually''' selected task bar/milestone symbol.
  
 
==Related Links==
 
==Related Links==
  
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] 9.0.1-70
+
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!--9.0.1-70-->
  
[[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] 9.2.1-70
+
[[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] <!--9.2.1-70-->
  
[[Labeling Task/Milestone Dates for Version 7.0 (OnePager Express) | Labeling Task/Milestone Dates for OnePager Express]] 10.2.1-70
+
[[Labeling Task/Milestone Dates for Version 7.0 (OnePager Express) | Labeling Task/Milestone Dates for OnePager Express]] <!--10.2.1-70-->
  
[[Percent complete for Version 7.0 (OnePager Express) | Percent complete for OnePager Express]] 10.4.1-70
+
[[Percent complete for Version 7.0 (OnePager Express) | Percent complete for OnePager Express]] <!--10.4.1-70-->
  
[[Baselines for Version 7.0 (OnePager Express) | Baselines for OnePager Express]] 10.6.1-70
+
[[Baselines for Version 7.0 (OnePager Express) | Baselines for OnePager Express]] <!--10.6.1-70-->
  
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] 21.0.1-70
+
[[Editing with the Chart Properties form for Version 7.0 (Portal) | Editing with the Chart Properties form (Portal)]] <!--21.0.1-70-->
  
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] 24.0.1-70
+
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
  
 
(10.10.1-70)
 
(10.10.1-70)

Latest revision as of 15:44, 13 January 2021

About Editing Deadlines

OnePager translates Deadlines from your Microsoft Excel source plan into deadline shapes in the graph to indicate the deadline date for a task bar/milestone symbol. In order to import deadline date information, your Microsoft Excel source plan must have a column header with a name similar to the word deadline. OnePager Express does its best to translate similar names to deadline date information and import this data. You always have the option to specifically designate a Microsoft Excel column header name as your specific set of dates specifying deadlines. This option is available in the OnePager Express Template Properties and Chart Properties form at the Task Bars tab as is explained later in this article. To illustrate with a simple example, consider the Microsoft Excel source plan given below with three tasks containing Start and Finish dates, a deadline date, and a Flag with the header Show It set to Yes so that OnePager imports the data for all three tasks:

X70-10 9 1-70-(1-1)-09192019.png

When a simple chart is created from the source plan above and Deadlines are turned ON, the example chart looks like this:

X70-10 9 1-70-(2)-09192019.png

When deadlines are turned ON, they appear (by default) as red arrow shape in each task bar's row at the deadline date position with respect to the time axis. Above, deadline shapes that are not contained within their respective task bar are shown with back dash-dot connecting lines to illustrate the capability.

Editing All Deadline Properties

To display deadline dates in your charts you must first assure that the Microsoft Excel source plan has a Deadline field populated with valid dates. When deadline dates are present in the source plan they must first be turned ON as the default setting in most distributed Template Properties form is for deadlines to be turned OFF. To do this click the Chart Properties button on the OnePager Home tab to access the Chart Properties form. Next, navigate to the Chart Properties Task Bars tab and to the Task Bars Decoration control group. Check the Deadline markers checkbox ON to enable the Deadline Properties... button to the immediate right of the checkbox as shown below:

X70-10 10 1-70-(3-1)-09222020.png

By default, deadlines are mapped to the Deadline date field in Microsoft Excel if that field is present as a column header.

Set Deadline Properties Form

To edit the format of all deadlines, click the Deadline Properties... button, to access the Set deadline properties form shown below:

X70-10 10 1-70-(4-1)-09222020.png

The form above provides all the editing controls for all deadline shapes that can be displayed in the chart.

Standard Basic Deadline Shape Controls

As stated previously, many of the controls in this group of the Set deadline properties form are standard. The deadline shapes available are the same as Milestone symbols found in the Milestones tab of the Template Properties and Chart Properties forms Likewise, the Fill patterns available are the same for task bars and milestone symbols also found on their respective tabs of the Template Properties and Chart Properties forms.

The Height percentage control represents the percentage of the total task bar/milestone symbol's height itself, is covered elsewhere and behaves in a standard way. The default Height percentage is 100%.

Similarly, the Transparency control for the deadline operates in the same way as transparency controls for other objects. The higher the value selected, the greater the transparency. Conversely, the low the value selected, the more solid the deadline appears.

The Field dropdown in the upper right of the form allows you to select another Microsoft Excel source plan date field instead of the default Deadline field. Contents of the Field dropdown list is shown below:

X70-10 9 1-70-(5A)-09192019.png

The Position of the deadline has a unique meaning. Deadlines are always associated with a task bar/milestone symbol and can be to the left, within, or to the right of the task bar/milestone ssymbol itself depending on your Microsoft Excel source plan data for the task bar’s start, finish and deadline dates. The position in this context is about where within the task bar/milestone symbol’s row area vertically the deadline should be placed. There are three (3) available positions for the placement of the deadline with respect to the task bar:

  • Centered in the task bar.
  • Above the task bar/milestone symbol.
  • Below the task bar as shown here:
X70-10 9 1-70-(5)-09192019.png

The Use custom color checkbox can be checked ON when it is desired to select a color for the deadline other than the color for its parent task bar/milestone symbol. When the Use custom color checkbox is checked ON, the Custom color dropdown is enabled. Clicking the dropdown button shows the standard Color Chooser form.

Showing Deadline Delays

The purpose of the display of Deadline Delays is to provide you with the capability to highlight deadlines that are missed as shown in the chart. When the Color-code delays checkbox is checked ON, OnePager uses the selected Delay color (determined by the selection of the delay color from the standard Color Chooser form) to show all deadlines that are missed:

X70-10 9 1-70-(8)-09192019.png

The deadline delay feature follows this logic. The deadline is set to the selected Delay color if, for any deadline:

  • The Color-code delays checkbox is checked ON,
  • The deadline date is earlier than the current snapshot date,
  • And the percent (%) complete for the parent task bar/milestone symbol is less than 100%.

If any of the conditions stated above are not met, the color of the deadline is set to the default color, unless a custom color is otherwise specified.

Example Deadline Date Delay

To illustrate the operation of the Color-code delay feature, let's set the stage by supposing that a project of three tasks is has the following initial conditions:

  • Project Start Date – 10/1/2019
  • Project Finish Date (Estimated) – 10/18/2019
  • First Status Date – 9/11/2019
  • Task A Deadline Date – 10/19/2019 (Task A Finish Date projected before Deadline Date)
  • Task B Deadline Date – 10/10/2019 (Task B Finish Date beyond Deadline Date)
  • Task C Deadline Date- 10/1/2019 (Task C Start Date beyond Deadline Date)

With these initial conditions, the Microsoft Project source plan looks like this:

X70-10 9 1-70-(9)-09192019.png

If we take a snapshot using the above source plan as of 10/10/2019 the chart looks like this:

X70-10 9 1-70-(10)-09192019.png

OnePager Express treats the snapshot date similar to the way Microsoft Project treats its Status date field.

Connecting Lines

The Connecting Lines control group of the Set deadline properties form deals with connecting lines properties when you require that deadline shapes are tied to their parent task bar/milestone symbol. The controls available are shown below:

X70-10 9 1-70-(6)-09192019.png

To enable deadline shape connection lines, check the Connect deadline markers to current markers checkbox ON as shown above. A default color, line style, and line width is established from your current Template. If you wish to specify a custom color, check the Use custom color checkbox ON and use the Custom color dropdown button to access the standard Color Chooser form.

You also have the option of selecting from a variety of line styles by clicking on the Line style dropdown button.

There are five (5) standard line styles to select from which are the same as used to connect Baselines to their parent task bars/milestone symbols as described in the section of the article at: Baselines for OnePager Express - Connect Baselines and Actual Task Bar/Milestone Symbols

The value dial to the right of the Line style dropdown provides the capability to edit the width of the deadline shape connection line. The form above shows the extent of control that you have over the lines that can be used to connect a deadline to its parent task bar/milestone symbol. These include the specification of a custom color, line width and line style.

Deadline Dates

The Deadline Dates control group in the Set deadline properties form provides the controls for turning ON and positioning the deadline date text labels as shown below:

X70-10 9 1-70-(7)-09192019.png

The form above shows the extent of control that you have over the display of date labels for deadlines. These are the same controls as for other decoration date specifications and include controls for date format, the use of the fiscal year feature, the positioning of the date label text, and the font properties for the date label text.

For more specific information about the controls in this control group, please reference the corresponding section for Baseline Decorations at: Baselines for OnePager Express - Showing Baseline Dates

Editing Individual Task Deadline Properties

Deadline displays are normally turned OFF in distributed Template Properties forms. In addition to the capabilities for editing all Deadline properties using the Template Properties and/or Chart Properties forms, you can select and individually edit Deadline properties showing in the chart. As a prerequisite for editing individual deadline properties it is the necessity for deadline data to be imported from the Microsoft Project source plan.

Selecting Individual Task Bar or Bars

Some individual task deadline properties can be edited by selecting the desired task bar or task bars with a left-click operation and then right-clicking one of the selected task bars to show the task bar right-click context menu below:

X70-10 9 1-70-(11)-09192019.png

Before you can do so, you must confirm that the Deadline markers checkbox in either the Template Properties or Chart Properties form's Task Bars and/or Milestones tab is checked ON.

Accessing the Change Task/Milestone Properties Form

Select the Format… command which access the Change Task/Milestone Properties form. Next, navigate to the Deadlines tab, which displays the deadline control options shown below:

X70-10 10 1-70-(12-1)-09102020.png

The Deadlines tab, shown above controls the display of deadline connectors and deadline text dates for the selected task bar/milestone symbol and the placement of the deadline text dates with respect to the deadline shape. The Show Deadline checkbox allows you to turn ON and OFF the display of deadline information for the selected task bar/milestone symbol. When the Show Deadline checkbox is checked ON, you have the option to specify the display of the connector and the display of deadline date for the selected task bar/milestone symbol. When the Show Deadline Date Label checkbox is checked ON you have access to control over the Deadline Date Position selection dropdown and Deadline Date Font selection button as discussed above related to editing all task bar/milestone symbol deadline information. There are five (5) standard deadline date label positions to select from. Clicking the Deadline Date Font button accesses the standard Font properties form where edits of the deadline date text can be made.

Individually Edited Deadline Shape Example

Below is an example of a single task bar's deadline information using the chart previously shown in this article:

X70-10 9 1-70-(13)-09192019.png

The controls at the Deadline tab of the Change Task/Milestone Properties form for the Show Deadline Date, that is, the Position and Font controls operate exactly as described for other start/finish date displays in OnePager.

For more information describing the use of these controls for the Percent Complete tab of this form, please see the section in the article at: Percent complete for OnePager Express - Example

There are no controls available in the Deadline tab of the Change Task/Milestone Properties form to edit the properties of the connector line for an individually selected task bar/milestone symbol.

Related Links

Manual Editing Task/Milestone Shapes and Text Labels (Portal)

Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)

Labeling Task/Milestone Dates for OnePager Express

Percent complete for OnePager Express

Baselines for OnePager Express

Editing with the Chart Properties form (Portal)

Managing Templates (Portal)

(10.10.1-70)