==Overview==
 
==Overview==
  
1) As with previous version of OnePager Express, version 7.0 of '''OPX''' can be launched from a '''Desktop icon''' as well as from within Microsoft Excel ('''Add-in''').
+
As with previous version of OnePager Express, version 7.0 of '''OPX''' can be launched from a '''Desktop icon''' as well as from within Microsoft Excel ('''Add-in'''). Please note that after selecting the '''Add-in''' launch option that you are not be able to launch the OnePager '''Desktop''' application. Only one of these applications ('''Add-in''' or '''Desktop''') can be active at a time. If you attempt to launch both, a warning message appears as shown below:
 
+
2) Please note that after selecting the '''Add-in''' launch option that you are not be able to launch the OnePager '''Desktop''' application.
+
 
+
3) Only one of these applications ('''Add-in''' or '''Desktop''') can be active at a time.
+
 
+
4) If you attempt to launch both, a warning message appears as shown below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(1)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(1)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(1)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(1)-07102019.png</center>-->
  
5) Further note that as mentioned in [[What's New with OnePager Release 7.0?]] 0.4-70, this new version has enhanced features such as the '''User Interface Upgrade''' and  '''Smart Task/Milestone Text Label Collision Avoidance Feature''' to name a few.
+
Further note that as mentioned in [[What's New with OnePager Release 7.0?]] <!--0.4-70-->, this new version has enhanced features such as the '''User Interface Upgrade''' and  '''Smart Task/Milestone Text Label Collision Avoidance Feature''' to name a few. This article provides the basic information needed to '''Getting Started''' and use OnePager Express ('''OPX''') after you launch '''OPX''' from Microsoft Excel.
  
6) This article provides the basic information needed to '''Getting Started''' and use OnePager Express ('''OPX''') after you launch '''OPX''' from Microsoft Excel. 
+
The article providing '''Getting Started''' guidance when launching from the '''OPX Desktop icon''' is at: [[Getting Started with OnePager Express Version 7.0 Desktop | Getting Started with OnePager Express Desktop]] <!--3.0.2.2-70-->
 
+
7) The article providing '''Getting Started''' guidance when launching from the '''OPX Desktop icon''' is at: [[Getting Started with OnePager Express Version 7.0 Desktop | Getting Started with OnePager Express Desktop]]. 3.0.2.2-70
+
  
 
==Launching OnePager Express for the First Time==
 
==Launching OnePager Express for the First Time==
  
1) The '''OPX Add-in''' automatically displays the '''OnePager icon''' on the Microsoft Excel ribbon's '''Add-in''' tool tab once OnePager is installed. That tool bar looks like this:
+
The '''OPX Add-in''' automatically displays the '''OnePager icon''' on the Microsoft Excel ribbon's '''Add-in''' tool tab once OnePager is installed. That tool bar looks like this:
  
 
<center>[[File:X70-3_0_2_1-70-(2)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(2)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(2)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(2)-07102019.png</center>-->
  
2) Clicking the '''OnePager Express…''' button takes you to the '''Chart Editor'''.  
+
Clicking the '''OnePager Express…''' button takes you to the '''Chart Editor'''. Clicking the '''Templates…''' button lets you '''edit''' the '''Template Properties''' form for your graphs. For now, it is simplest to use the default '''Template Properties''' form. 
  
3) Clicking the '''Templates…''' button lets you '''edit''' the '''Templates''' for your graphs.  
+
You can learn how '''Template Properties''' forms let you customize and standardize graph features later at: [[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
  
4) For now, it is simplest to use the default '''Template'''.   
+
Before you launch '''OPX''', however, you must have certain scheduling fields in your Microsoft Excel '''source plan'''.  There is a lot of flexibility in how these fields can be named.  A typical example is shown below.  The only '''mandatory fields''' are fields representing '''Start''', '''Finish''', and '''Name'''. In this example, however, we are also including three optional fields:
  
5) You can learn how '''Templates''' let you customize and standardize graph features later at: [[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] 24.0.1-70..
+
:1) A category field ('''Category''') used to assign '''colors''' to tasks.
  
6) Before you launch '''OPX''', however, you must have certain scheduling fields in your Microsoft Excel '''source plan'''.  
+
:2) A selection field ('''Show It''') used to choose which tasks to '''graph'''.
  
7) There is a lot of flexibility in how these fields can be named. 
+
:3) A '''Task ID''' field that OnePager uses to keep track of tasks/milestones as your Microsoft Excel plan is change through additions or deletions over the course of the project.
 
+
8) A typical example is shown below. 
+
 
+
9) The only '''mandatory fields''' are fields representing '''Start''', '''Finish''', and '''Name'''. 
+
 
+
10) In this example, however, we are also including three optional fields:
+
 
+
:a) A category field ('''Category''') used to assign '''colors''' to tasks.
+
 
+
:b) A selection field ('''Show It''') used to choose which tasks to '''graph'''.
+
 
+
:c) A '''Task ID''' field that OnePager uses to keep track of tasks/milestones as your Microsoft Excel plan is change through additions or deletions over the course of the project.
+
  
 
<center>[[File:X70-3_0_2_1-70-(2A-1)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(2A-1)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(2A-1)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(2A-1)-07102019.png</center>-->
 
+
11) To control which tasks get '''graphed''', you must specify a '''Flag''' field (e.g. '''Show It''') that you wish to use. 
+
 
+
12) '''Numeric''' fields can also be used the same as the text fields where a '''1''' in a '''Number''' field indicates '''Yes''' and a '''0''' in a '''Number''' field indicates '''No'''. 
+
 
+
13) See how this is done in the illustration above.
+
 
+
14) When making your first chart, we strongly recommend that you select 50 or fewer tasks with '''Yes'''.
+
 
+
15) Please note that '''OPX''' is shipped with a number of fully populated '''Templates''' that are based on the Microsoft Excel '''source plan''' used in the '''Tutorial''' also shipped with the product – BlueGrass Project Plan.
+
 
+
16) The following table describes field-heading types that '''OPX''' uses and shows variations on the heading titles that OnePager Express recognizes. 
+
 
+
17) It is not mandatory that you used these field names, since '''OPX''' gives you a chance to choose the actual Microsoft Excel '''source plan''' fields that it employs.   
+
 
+
18) However, using these names  speeds things up because it helps '''OPX''' make reasonable guesses on which fields to use as its default selections. 
+
 
+
19) Note that three field heading types must always be present: '''Name''', '''Start''', and '''Finish'''. 
+
  
20) We recommend the inclusion of an '''ID''' field with sequential numbering from top to bottom.   
+
To control which tasks get '''graphed''', you must specify a '''Flag''' field (e.g. '''Show It''') that you wish to use.  '''Numeric''' fields can also be used the same as the text fields where a '''1''' in a '''Number''' field indicates '''Yes''' and a '''0''' in a '''Number''' field indicates '''No'''.  See how this is done in the illustration above. When making your first chart, we strongly recommend that you select 50 or fewer tasks with '''Yes'''. Please note that '''OPX''' is shipped with a number of fully populated '''Template Properties''' forms that are based on the Microsoft Excel '''source plan''' used in the '''Tutorial''' also shipped with the product – BlueGrass Project Plan. The following table describes field-heading types that '''OPX''' uses and shows variations on the heading titles that OnePager Express recognizes.  It is not mandatory that you used these field names, since '''OPX''' gives you a chance to choose the actual Microsoft Excel '''source plan''' fields that it employs.    However, using these names  speeds things up because it helps '''OPX''' make reasonable guesses on which fields to use as its default selections.  Note that three field heading types must always be present: '''Name''', '''Start''', and '''Finish'''.   
  
21) This assists OnePager maintain a correspondence with Microsoft Excel’s rows after the Microsoft Excel '''source plan''' is updated.
+
We recommend the inclusion of an '''ID''' field with sequential numbering from top to bottom.  This assists OnePager maintain a correspondence with Microsoft Excel’s rows after the Microsoft Excel '''source plan''' is updated.
  
<center>[[File:X53-3_0_3-53-(3)-11092015.png]]</center>
+
<center>[[File:X70-3_0_3-70-(3)-12082020.png]]</center>
<center>X53-3_0_3-53-(3)-11092015.png</center>
+
<!--<center>X70-3_0_3-70-(3)-12082020.png</center>-->
  
22) To launch '''OPX''' and make a chart, click on the '''OnePager Express...''' button on the Microsoft Express tool bar’s '''Add-ins''' tab, which accesses the '''OnePager Express Start''' form:
+
To launch '''OPX''' and make a chart, click on the '''OnePager Express...''' button on the Microsoft Express tool bar’s '''Add-ins''' tab, which accesses the '''OnePager Express Start''' form:
  
 
<center>[[File:X70-3_0_2_1-70-(4)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(4)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(4)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(4)-07102019.png</center>-->
  
23) The '''OnePager Express Start''' form provides you with three options:
+
The '''OnePager Express Start''' form provides you with three options:
  
:a) '''NEW'''  Clicking the '''NEW''' button brings up the '''OnePager choices''' ('''OPC''') form.
+
:1) '''NEW'''  Clicking the '''NEW''' button brings up the '''OnePager choices''' ('''OPC''') form.
  
:b) '''UPDATE'''  Clicking the '''UPDATE''' button allows you to '''BROWSE FILES''' for an existing chart or select a recently-opened chart.
+
:2) '''UPDATE'''  Clicking the '''UPDATE''' button allows you to '''BROWSE FILES''' for an existing chart or select a recently-opened chart.
  
:c) '''OPEN'''  Clicking the '''OPEN''' button allows you to '''BROWSE FILES''' for an existing chart or select a recently-opened chart.  Once selected and opened, the chart is available for editing.
+
:3) '''OPEN'''  Clicking the '''OPEN''' button allows you to '''BROWSE FILES''' for an existing chart or select a recently-opened chart.  Once selected and opened, the chart is available for editing.
  
 
==Creating a New Chart==
 
==Creating a New Chart==
  
1) Clicking the '''NEW''' button accesses the OnePager choices ('''OPC''') form as shown below:
+
Clicking the '''NEW''' button accesses the OnePager choices ('''OPC''') form as shown below:
  
 
<center>[[File:X70-3_0_2_1-70-(5)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(5)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(5)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(5)-07102019.png</center>-->
  
 
===Options on the New OnePager Choices form===
 
===Options on the New OnePager Choices form===
  
2) The '''OPC''' form gives you more options for selecting '''source plans'''.   
+
The '''OPC''' form gives you more options for selecting '''source plans'''.  The illustration above shows that '''OPX''' was initiated from Microsoft Excel with the '''source plan''' shown in the '''Selected File(s)''' group shown above.  The '''Add/Remove''' button gives you the capability to '''add''' more '''source plans''' to the '''source packet''' or, for multiple file packets, to '''remove''' files. Clicking the '''Add/Remove''' button accesses the '''Data source selection''' form as shown below:
 
+
3) The illustration above shows that '''OPX''' was initiated from Microsoft Excel with the '''source plan''' shown in the '''Selected File(s)''' group shown above.   
+
 
+
4) The '''Add/Remove''' button gives you the capability to '''add''' more '''source plans''' to the '''source packet''' or, for multiple file packets, to '''remove''' files.
+
 
+
5) Clicking the '''Add/Remove''' button accesses the '''Data source selection''' form as shown below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(6)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(6)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(6)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(6)-07102019.png</center>-->
  
6) The '''Data source selection''' form displays the current '''source plan''' that was loaded with Microsoft Excel when you clicked the '''OnePager Express...''' button.   
+
The '''Data source selection''' form displays the current '''source plan''' that was loaded with Microsoft Excel when you clicked the '''OnePager Express...''' button.  This form lets you '''Add''' more source Microsoft Excel '''source plans''' to create a multi-project chart or '''Remove''' a '''source plan''' from a multi-file '''source packet'''.  These options are detailed below.
 
+
7) This form lets you '''Add''' more source Microsoft Excel '''source plans''' to create a multi-project chart or '''Remove''' a '''source plan''' from a multi-file '''source packet'''.  These options are detailed below.
+
  
 
===Adding a New Source Plan===
 
===Adding a New Source Plan===
  
8) When you click the '''Add''' button, '''OPX''' gives you the option to access a Windows '''Open''' form when you select the '''BROWSE FILES…''' option as shown here:
+
When you click the '''Add''' button, '''OPX''' gives you the option to access a Windows '''Open''' form when you select the '''BROWSE FILES…''' option as shown here:
  
 
<center>[[File:X70-3_0_2_1-70-(7)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(7)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(7)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(7)-07102019.png</center>-->
  
:a) Clicking the '''BROWSE FILES…''' option displays a Window’s '''Open''' from which you can select a Microsoft Excel '''source plan''' to add to the '''source packet'''.  A sample '''Open''' form is shown below:
+
Clicking the '''BROWSE FILES…''' option displays a Window’s '''Open''' from which you can select a Microsoft Excel '''source plan''' to add to the '''source packet'''.  A sample '''Open''' form is shown below:
  
 
<center>[[File:X70-3_0_2_1-70-(8)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(8)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(8)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(8)-07102019.png</center>-->
  
:b) When you select a desired Microsoft Excel '''source plan''' and click the '''Open''' button as shown above, '''OPX''' adds the '''source plan''' to the '''source packet''' and displays it in the '''Data source selection''' window as shown below:
+
When you select a desired Microsoft Excel '''source plan''' and click the '''Open''' button as shown above, '''OPX''' adds the '''source plan''' to the '''source packet''' and displays it in the '''Data source selection''' window as shown below:
  
 
<center>[[File:X70-3_0_2_1-70-(9)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(9)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(9)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(9)-07102019.png</center>-->
  
:c) The selected '''source plan''' is added to the '''source packet''' as shown above.   
+
The selected '''source plan''' is added to the '''source packet''' as shown above.  '''OPX''' shows the path name of the '''source plan''' in the window if you hover the mouse over the '''source plan''' name. If you select a recently used '''source plan''' from the dropdown menu displayed with the '''Add''' button is clicked in the '''Data source selection''' form, '''OPX''' adds that '''source plan''' to the '''source packet'''.
 
+
:d) '''OPX''' shows the path name of the '''source plan''' in the window if you hover the mouse over the '''source plan''' name.
+
 
+
:e) If you select a recently used '''source plan''' from the dropdown menu displayed with the '''Add''' button is clicked in the '''Data source selection''' form, '''OPX''' adds that '''source plan''' to the '''source packet'''.
+
  
 
===Removing a Source Plan===
 
===Removing a Source Plan===
  
9) The '''Remove''' button allows you to remove a '''source plan''' from a '''source packet.''' if that '''source plan''' is not needed to create the new chart.   
+
The '''Remove''' button allows you to remove a '''source plan''' from a '''source packet.''' if that '''source plan''' is not needed to create the new chart.  To remove a file, first select the file in the '''Data source selection''' form’s window so that it is highlighted in blue then click the '''Remove''' button as shown in the sequence below:
 
+
10) To remove a file, first select the file in the '''Data source selection''' form’s window so that it is highlighted in blue then click the '''Remove''' button as shown in the sequence below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(10)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(10)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(10)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(10)-07102019.png</center>-->
 
+
  
 
<center>[[File:X70-3_0_2_1-70-(11)-07102019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(11)-07102019.png]]</center>
<center>X70-3_0_2_1-70-(11)-07102019.png</center>
+
<!--<center>X70-3_0_2_1-70-(11)-07102019.png</center>-->
  
 
===Other Choices to Make===
 
===Other Choices to Make===
  
11) Moving on to the other groups of the '''OPC''' form, you are asked to confirm a few things before you build the chart.
+
Moving on to the other groups of the '''OPC''' form, you are asked to confirm a few things before you build the chart.  '''OPX''' makes good guesses for each of these choices, but you can change any of them:
 
+
12) '''OPX''' makes good guesses for each of these choices, but you can change any of them:
+
  
 
<center>[[File:X70-3_0_2_1-70-(15)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(15)-07112019.png</center>-->
  
 
====Starting Template====
 
====Starting Template====
  
13) The current '''Template''' determines which fields get imported from Microsoft Excel and how the initial chart looks.
+
The current '''Template Properties''' form determines which fields get imported from Microsoft Excel and how the initial chart looks. '''OPX''' ships with many sample '''Template Properties''' forms, but you can also customize your own '''Template Properties''' form. To choose which '''Template Properties''' form to use in building your chart, click the '''Change…''' button in the top group of the '''OPC''' form.  
 
+
14) '''OPX''' ships with many sample '''Templates''', but you can also customize your own '''Templates'''.  
+
 
+
15) To choose which '''Template''' to use in building your chart, click the '''Change…''' button in the top group of the '''OPC''' form.  
+
  
 
<center>[[File:X70-3_0_2_1-70-(15A)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15A)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15A)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(15A)-07112019.png</center>-->
  
16) For now, just stick with the default '''Template''' entitled '''Single Project Gantt View – Detailed''', but you can always use a different '''Template''' to get a different type of chart.
+
For now, just stick with the default '''Template Properties''' form entitled '''Single Project Gantt View – Detailed''', but you can always use a different '''Template Properties''' form to get a different type of chart.
  
 
====Title of the New Chart====
 
====Title of the New Chart====
  
17) This is the '''Title''' of the '''graph''' and also the suggested '''save''' name in which it is saved.  You can change the '''save''' name when you save it.   
+
This is the '''Title''' of the '''graph''' and also the suggested '''save''' name in which it is saved.  You can change the '''save''' name when you save it.  We recommend that you enter a '''Title''' that helps you identify the chart later on as shown here:
 
+
18) We recommend that you enter a '''Title''' that helps you identify the chart later on as shown here:
+
  
 
<center>[[File:X70-3_0_2_1-70-(15B)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15B)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15B)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(15B)-07112019.png</center>-->
+
19) For each chart you create, OnePager remembers '''colors, titles, legends, font sizes''', and all other '''graph properties''' so that your work is saved.
+
+
20) Later, you can update the chart with a snapshot of how the project looks on a different date. Then you can browse through the snapshots to see how the project is changing over time.
+
 
   
 
   
21) '''OPX''' also saves the '''path name''' associated with the '''save''' name ('''.TAM''').  
+
For each chart you create, OnePager remembers '''colors, titles, legends, font sizes''', and all other '''graph properties''' so that your work is saved. Later, you can update the chart with a snapshot of how the project looks on a different date. Then you can browse through the snapshots to see how the project is changing over time. '''OPX''' also saves the '''path name''' associated with the '''save''' name ('''.TAM'''). '''Path names''' are not available in '''.TAMs''' produced with version of '''OPX''' prior to version 6.0.
 
+
22) '''Path names''' are not available in '''.TAMs''' produced with version of '''OPX''' prior to version 6.0.
+
  
 
====Task Selection====
 
====Task Selection====
  
23) This is how you tell '''OPX''' which tasks to import from your Microsoft Excel '''source plan''' as indicated below:
+
This is how you tell '''OPX''' which tasks to import from your Microsoft Excel '''source plan''' as indicated below:
  
 
<center>[[File:X70-3_0_2_1-70-(15C)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15C)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15C)-07112019.png</center>  
+
<!--<center>X70-3_0_2_1-70-(15C)-07112019.png</center>-->  
  
24) Either click the '''Select all tasks''' radio button to graph everything or choose a '''Flag''' field.  
+
Either click the '''Select all tasks''' radio button to graph everything or choose a '''Flag''' field. You can make several charts from a single Microsoft Excel '''source plan''', each using a different '''Flag''' or '''Number''' field.  In '''OPX''' if no '''Flags''' are set to '''Yes''', '''OPX''' provides the user with a warning message shown below:
 
+
25) You can make several charts from a single Microsoft Excel '''source plan''', each using a different '''Flag''' or '''Number''' field.   
+
 
+
26) In '''OPX''' if no '''Flags''' are set to '''Yes''', '''OPX''' provides the user with a warning message shown below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(15D)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15D)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15D)-07112019.png</center>  
+
<!--<center>X70-3_0_2_1-70-(15D)-07112019.png</center>-->
 
+
27) Clicking the '''Select tasks by custom filter''' button enables the '''Edit filters...''' button. 
+
  
28) Clicking the '''Edit filters...''' button takes you to a form that controls the '''Conditional Import Filters''' feature  as shown here:   
+
Clicking the '''Select tasks by custom filter''' button enables the '''Edit filters...''' button.  Clicking the '''Edit filters...''' button takes you to a form that controls the '''Conditional Import Filters''' feature  as shown here:   
  
 
<center>[[File:X70-3_0_2_1-70-(15E)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15E)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15E)-07112019.png</center>  
+
<!--<center>X70-3_0_2_1-70-(15E)-07112019.png</center>-->  
  
29) For more detailed information, please see the article at: [[Conditional Import for Version 6.0 (Portal) | Conditional Import Filters (Portal)]] 7.18.1-70.
+
For more detailed information, please see the article at: [[Conditional Import for Version 6.0 (Portal) | Conditional Import Filters (Portal)]] <!--7.18.1-70-->
  
 
====Snapshot Date====
 
====Snapshot Date====
  
30) This is the date of the report and lets you keep track of how schedules change over time.
+
This is the date of the report and lets you keep track of how schedules change over time. The snapshot date is set by default as the current date taken from your computer. You can change the snapshot date by clicking on the dropdown button at the window shown in the illustration below:
 
+
31) The snapshot date is set by default as the current date taken from your computer.
+
 
+
32)  You can change the snapshot date by clicking on the dropdown button at the window shown in the illustration below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(15F)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15F)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15F)-07112019.png</center>  
+
<!--<center>X70-3_0_2_1-70-(15F)-07112019.png</center>-->  
  
33) Making a calendar date selection as shown above establishes the '''snapshot date''' for the chart and the '''snapshot''' being created.  
+
Making a calendar date selection as shown above establishes the '''snapshot date''' for the chart and the '''snapshot''' being created. Each chart can have many snapshots. Snapshots and their management are important topics.  Snapshots are the basis of how OnePager Express helps you track the progress of your project. 
  
34) Each chart can have many snapshots.
+
For more information, please see the articles at:  [[Managing Chart Data for Version 7.0 | Managing Chart Data (Portal)]] <!--23.0.1-70-->
 
+
35)  Snapshots and their management are important topics.  Snapshots are the basis of how OnePager Express helps you track the progress of your project. 
+
 
+
36) For more information, please see the articles at:  [[Managing Chart Data for Version 7.0 | Managing Chart Data (Portal)]] 23.0.1-70.
+
  
 
====Show Field Mappings====
 
====Show Field Mappings====
  
37) The '''Show field mappings''' checkbox near the bottom of the form.
+
The '''Show field mappings''' checkbox near the bottom of the form. When this box is checked you have a chance to review and change the Microsoft Excel '''field mappings''' to '''OPX''' before you make your first chart.  To do this, click the '''Next&gt;''' button.    You see the following screen:
 
+
38) When this box is checked you have a chance to review and change the Microsoft Excel '''field mappings''' to '''OPX''' before you make your first chart.   
+
 
+
39) To do this, click the '''Next&gt;''' button.    You see the following screen:
+
  
 
<center>[[File:X70-3_0_2_2-70-(15AA)-07162019.png]]</center>
 
<center>[[File:X70-3_0_2_2-70-(15AA)-07162019.png]]</center>
<center>X70-3_0_2_2-70-(15AA)-07162019.png</center>  
+
<!--<center>X70-3_0_2_2-70-(15AA)-07162019.png</center>-->  
  
40) Notice in the graphic above that '''OPX''' has relied on the current '''Template''' to make some guesses on what Microsoft Excel fields should be used in making the graph.     
+
Notice in the graphic above that '''OPX''' has relied on the current '''Template Properties''' form to make some guesses on what Microsoft Excel fields should be used in making the graph.    You can easily change any of these '''field mappings''' by making selections from the dropdown menus.  For example, we show below how to change the '''Color''':
 
+
41) You can easily change any of these '''field mappings''' by making selections from the dropdown menus.   
+
 
+
42) For example, we show below how to change the '''Color''':
+
  
 
<center>[[File:X70-3_0_2_1-70-(15H)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(15H)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(15H)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(15H)-07112019.png</center>-->
  
 
===Making the Graph===
 
===Making the Graph===
  
43) Once you are satisfied with the '''field mappings''', click on '''Create new chart''' button to import your selected Microsoft Excel '''source plan''' data and create a chart.   
+
Once you are satisfied with the '''field mappings''', click on '''Create new chart''' button to import your selected Microsoft Excel '''source plan''' data and create a chart.  After a few second you see a screen that looks like this:
 
+
44) After a few second you see a screen that looks like this:
+
  
 
<center>[[File:X70-3_0_2_1-70-(17)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(17)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(17)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(17)-07112019.png</center>-->
  
45) Note that each task or milestone was '''color''' coded based on the value in the '''Category''' field.   
+
Note that each task or milestone was '''color''' coded based on the value in the '''Category''' field.  The '''Legend''' contains an optional diagram near the bottom, explaining that the bars inside the Gantt bars represent percent complete extracted from Microsoft Excel.    '''Percent complete''' comes from a Microsoft Excel field that you specified in the '''field mapping''' form.  Note that the current '''Template Properties''' form is the '''Template''' used by OnePager Express to create the first chart and determines how your data looks in the new chart.  The '''Template Properties''' form’s '''Task Bars''' tab showing where the '''color''' control is located is shown below:
  
46)  The '''Legend''' contains an optional diagram near the bottom, explaining that the bars inside the Gantt bars represent percent complete extracted from Microsoft Excel. 
+
<center>[[File:X70-3_0_2_1-70-(18-1)-09212020.png]]</center>
 
+
<!--<center>X70-3_0_2_1-70-(18-1)-09212020.png</center>-->
47)  '''Percent complete''' comes from a Microsoft Excel field that you specified in the '''field mapping''' form. 
+
 
+
48)  Note that the current '''Template''' is the '''Template''' used by OnePager Express to create the first chart and determines how your data looks in the new chart. 
+
 
+
49) The '''Template''' form’s '''Task Bars''' tab showing where the '''color''' control is located is shown below:
+
 
+
<center>[[File:X70-3_0_2_1-70-(18)-07112019.png]]</center>
+
<center>X70-3_0_2_1-70-(18)-07112019.png</center>
+
  
 
===Copying the Chart to Microsoft PowerPoint===
 
===Copying the Chart to Microsoft PowerPoint===
  
50) OnePager provides access to the Windows clipboard so you can '''copy''' the chart and '''paste''' it into another application.
+
OnePager provides access to the Windows clipboard so you can '''copy''' the chart and '''paste''' it into another application. To copy the current snapshot to the clipboard click the '''Copy''' button on the '''Home''' ribbon as shown below:
 
+
51) To copy the current snapshot to the clipboard click the '''Copy''' button on the '''Home''' ribbon as shown below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(32A)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(32A)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(32A)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(32A)-07112019.png</center>-->
  
52) Then launch Microsoft PowerPoint and paste the clipboard copy of the chart into a Microsoft PowerPoint slide, as shown below:
+
Then launch Microsoft PowerPoint and paste the clipboard copy of the chart into a Microsoft PowerPoint slide, as shown below:
  
 
<center>[[File:X61-3_0_2_1-61-(32)-5032018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(32)-5032018.png]]</center>
<center>X61-3_0_2_1-61-(32)-5032018.png</center>
+
<!--<center>X61-3_0_2_1-61-(32)-5032018.png</center>-->
  
53) That’s it! You created a professional 1-page schedule summary from a complex Microsoft Excel schedule and copied it into a Microsoft PowerPoint presentation.   
+
That’s it! You created a professional 1-page schedule summary from a complex Microsoft Excel schedule and copied it into a Microsoft PowerPoint presentation.   
  
54) You can also print the chart by selecting the '''Print''' button on the '''File''' tab.   
+
You can also print the chart by selecting the '''Print''' button on the '''File''' tab.  OnePager has other features that let you move tasks vertically to different '''rows and swimlanes''', change the number of swimlanes, add swimlane titles, show dependencies among tasks, change task colors, hide tasks, add floating comment boxes, and standardize on graph styles across organizations. 
  
55) OnePager has other features that let you move tasks vertically to different '''rows and swimlanes''', change the number of swimlanes, add swimlane titles, show dependencies among tasks, change task colors, hide tasks, add floating comment boxes, and standardize on graph styles across organizations. 
+
To learn more about these features, read about the specific workflows in this Wiki at [[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] <!--7.0.1-70--> and [[Manual Editing for Version 7.0 (Portal) | Manual versus Data-Driven Editing (Portal)]] <!--9.0.1-70-->
 
+
56) To learn more about these features, read about the specific workflows in this Wiki at [[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] 7.0.1-70 and [[Manual Editing for Version 7.0 (Portal) | Manual versus Data-Driven Editing (Portal)]]. 9.0.1-70
+
  
 
==Opening a Chart==
 
==Opening a Chart==
  
1) The right-most button on the '''OPC''' form is the '''OPEN''' button.   
+
The right-most button on the '''OPC''' form is the '''OPEN''' button.  Clicking the '''OPEN''' button displays a dropdown menu which happens to be the same for the '''UPDATE''' buttons.  The options in the dropdown are discussed below:
 
+
2) Clicking the '''OPEN''' button displays a dropdown menu which happens to be the same for the '''UPDATE''' buttons.   
+
 
+
3) The options in the dropdown are discussed below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(18A)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(18A)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(18A)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(18A)-07112019.png</center>-->
  
4) Clicking the '''BROWSE FILES...''' option accesses a Windows '''Open''' form from which you can select a '''.TAM''' that you want to open.   
+
Clicking the '''BROWSE FILES...''' option accesses a Windows '''Open''' form from which you can select a '''.TAM''' that you want to open.  Selecting the desired '''.TAM''' causes '''OPX''' to display the selected chart in the '''Chart Editor'''.  From this position, you can '''edit''' the chart, '''save it''', or '''share it''' with others. Clicking any of the '''RECENT chart ''' items the dropdown menu above causes '''OPX''' to load the associated '''.TAM''' into the '''Chart Editor''' where you can '''edit''' the chart, '''save it''', or '''share it''' with others.
 
+
5) Selecting the desired '''.TAM''' causes '''OPX''' to display the selected chart in the '''Chart Editor'''.   
+
 
+
6) From this position, you can '''edit''' the chart, '''save it''', or '''share it''' with others.
+
 
+
7) Clicking any of the '''RECENT chart ''' items the dropdown menu above causes '''OPX''' to load the associated '''.TAM''' into the '''Chart Editor''' where you can '''edit''' the chart, '''save it''', or '''share it''' with others.
+
  
 
==Replacing A Snapshot - Updating a Chart with Changes Made to the Microsoft Excel Source Plan's Data==
 
==Replacing A Snapshot - Updating a Chart with Changes Made to the Microsoft Excel Source Plan's Data==
  
1) Suppose after examining the chart you created and '''saved''', you realize that it might be best to show more task bars.   
+
Suppose after examining the chart you created and '''saved''', you realize that it might be best to show more task bars.  This, you think, would greatly improve the schedule presentation. Updating the chart at this point is a simple matter.  Recall that '''OPX''' is active and the '''Chart Editor''' is displaying the current chart you want to update.  Additionally, the Microsoft Excel '''source plan''' and the application are active.  The original chart looked like this:
 
+
2) This, you think, would greatly improve the schedule presentation.
+
 
+
3) Updating the chart at this point is a simple matter.   
+
 
+
4) Recall that '''OPX''' is active and the '''Chart Editor''' is displaying the current chart you want to update.   
+
 
+
5) Additionally, the Microsoft Excel '''source plan''' and the application are active.  The original chart looked like this:
+
  
 
<center>[[File:X61-3_0_2_1-61-(18B)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18B)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18B)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(18B)-5022018.png</center>-->
  
6) Since Microsoft Excel is still an active program and the Microsoft Excel '''source plan''' you are using is still being displayed, go back to the Microsoft Excel application and change the '''Show It''' field setting for the rows you want to now display from '''No''' to '''Yes''' for the rows you want to now display.   
+
Since Microsoft Excel is still an active program and the Microsoft Excel '''source plan''' you are using is still being displayed, go back to the Microsoft Excel application and change the '''Show It''' field setting for the rows you want to now display from '''No''' to '''Yes''' for the rows you want to now display.  As section of the Microsoft Excel '''source plan''' where this is done is shown below:
 
+
7) As section of the Microsoft Excel '''source plan''' where this is done is shown below:
+
  
 
<center>[[File:X61-3_0_2_1-61-(18C)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18C)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18C)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(18C)-5022018.png</center>-->
  
8) Once you’ve made the '''Show It'''  field changes lines 7 through 15 in the Microsoft Excel the '''source plan''' looks like this:
+
Once you’ve made the '''Show It'''  field changes lines 7 through 15 in the Microsoft Excel the '''source plan''' looks like this:
  
 
<center>[[File:X61-3_0_2_1-61-(18D)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18D)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18D)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(18D)-5022018.png</center>-->
  
9) With the Microsoft Excel '''source plan''' updated, go back to '''OPX''' and navigate to the '''Data''' tab on the ribbon where there are several buttons.   
+
With the Microsoft Excel '''source plan''' updated, go back to '''OPX''' and navigate to the '''Data''' tab on the ribbon where there are several buttons.  To '''update''' your chart to now show the additional rows from your Microsoft Excel '''source plan''' click the '''Replace Snapshot''' button as shown below:
 
+
10) To '''update''' your chart to now show the additional rows from your Microsoft Excel '''source plan''' click the '''Replace Snapshot''' button as shown below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(17C)-07112019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(17C)-07112019.png]]</center>
<center>X70-3_0_2_1-70-(17C)-07112019.png</center>
+
<!--<center>X70-3_0_2_1-70-(17C)-07112019.png</center>-->
 
+
11) When you click the '''Replace Snapshot''' button, '''OPX'''  goes back to the associated Microsoft Excel '''source plan''' that you just changed, imports all the rows that changed, and update your chart.
+
  
12) At the conclusion of the operation, the updated chart looks like this:
+
When you click the '''Replace Snapshot''' button, '''OPX'''  goes back to the associated Microsoft Excel '''source plan''' that you just changed, imports all the rows that changed, and update your chart. At the conclusion of the operation, the updated chart looks like this:
  
 
<center>[[File:X61-3_0_2_1-61-(18E)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18E)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18E)-5022018.png</center>  
+
<!--<center>X61-3_0_2_1-61-(18E)-5022018.png</center>-->  
  
13) The example above is just one of many uses of the '''Data''' tab’s '''Replace Snapshot''' button when you need to update a chart.   
+
The example above is just one of many uses of the '''Data''' tab’s '''Replace Snapshot''' button when you need to update a chart.  You can do this as many times as necessary until the chart is the way you need it.  In addition to adding and removing rows by changing the '''Show It''' field, you can change '''source plan''' task '''Start Dates''', '''Finish Dates''', or '''Resource Names'''' and display these data changes in the chart.  Using the procedure above you can do this very efficiently. You can now '''save''' the chart by giving it a '''save''' name.  When you '''save''' the chart in '''OPX''', OnePager saves the '''.TAM''' and saves the Microsoft Excel '''source plan name''' and '''path''' information.  This is useful when you want to further update the chart or when you want to add a snapshot later on. In the examples below it is assumes that the chart is saved as '''BlueGrass Project Report - Express'''.
 
+
14) You can do this as many times as necessary until the chart is the way you need it.   
+
 
+
15) In addition to adding and removing rows by changing the '''Show It''' field, you can change '''source plan''' task '''Start Dates''', '''Finish Dates''', or '''Resource Names'''' and display these data changes in the chart.   
+
 
+
16) Using the procedure above you can do this very efficiently.  
+
 
+
17) You can now '''save''' the chart by giving it a '''save''' name.   
+
 
+
18) When you '''save''' the chart in '''OPX''', OnePager saves the '''.TAM''' and saves the Microsoft Excel '''source plan name''' and '''path''' information.   
+
 
+
19) This is useful when you want to further update the chart or when you want to add a snapshot later on.  
+
 
+
20) In the examples below it is assumes that the chart is saved as '''BlueGrass Project Report - Express'''.
+
  
 
==Adding a Snapshot - Adding to the Chart with Changes Made to the Microsoft Excel Source Plan's Data==
 
==Adding a Snapshot - Adding to the Chart with Changes Made to the Microsoft Excel Source Plan's Data==
  
1) The power of '''OPX''' is illustrated when, after a period of progress on the project, it is time to produce another chart.   
+
The power of '''OPX''' is illustrated when, after a period of progress on the project, it is time to produce another chart.  OnePager produces your next snapshot with the same look and feel as the original.  Assuming that the Microsoft Excel '''source plan''' was updated with '''actual start and finish, percent complete''', and other relevant data during the reporting interval, '''OPX''' can easily generate a new snapshot.  Suppose we have the following chart created on 11/1/2018 and we want to create another graph from the updated Microsoft Project '''source plan''' on 12/1/2018.
 
+
2) OnePager produces your next snapshot with the same look and feel as the original.   
+
 
+
3) Assuming that the Microsoft Excel '''source plan''' was updated with '''actual start and finish, percent complete''', and other relevant data during the reporting interval, '''OPX''' can easily generate a new snapshot.
+
 
+
4) Suppose we have the following chart created on 11/1/2018 and we want to create another graph from the updated Microsoft Project '''source plan''' on 12/1/2018.
+
  
 
<center>[[File:X61-3_0_2_1-61-(18F)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18F)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18F)-5022018.png</center>  
+
<!--<center>X61-3_0_2_1-61-(18F)-5022018.png</center>-->  
  
5) Before creating a new snapshot for 12/1/2018 as planned, we need to update the Microsoft Excel '''source plan''' say by updating the '''Percent Complete''' for the following tasks to the percentage indicated:
+
Before creating a new snapshot for 12/1/2018 as planned, we need to update the Microsoft Excel '''source plan''' say by updating the '''Percent Complete''' for the following tasks to the percentage indicated:
  
:a) Eng. Team 1 Dev. - 100%
+
:* Eng. Team 1 Dev. - 100%
 +
:* Internal Perf. Test - 10%
 +
:* Create MERLIN System - 100%
 +
:* Create ADONIS System - 25%
  
:b) Internal Perf. Test - 10%
+
When the '''source plan''' is updated with this revised information we can proceed. Launch '''OPX''' either from Microsoft Excel or from the '''Desktop icon''' and click the '''UPDATE''' button on the '''OnePager Express Start''' form.  Doing so accesses the following '''OnePager choices''' ('''OPC''') form:
 
+
;c) Create MERLIN System - 100%
+
 
+
:d) Create ADONIS System - 25%
+
 
+
6)  When the '''source plan''' is updated with this revised information we can proceed.
+
 
+
7) Launch '''OPX''' either from Microsoft Excel or from the '''Desktop icon''' and click the '''UPDATE''' button on the '''OnePager Express Start''' form.   
+
 
+
8) Doing so accesses the following '''OnePager choices''' ('''OPC''') form:
+
  
 
<center>[[File:X61-3_0_2_1-61-(18G)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18G)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18G)-5022018.png</center>  
+
<!--<center>X61-3_0_2_1-61-(18G)-5022018.png</center>-->  
  
9) In the '''OPC''' form above we selected the '''NEW snapshot at date:''' as shown.   
+
In the '''OPC''' form above we selected the '''NEW snapshot at date:''' as shown.  You can also select a date for the snapshot so that this snapshot represents the project at the status date point in time.  To see which snapshot dates already exist, just position your mouse over the '''NEW snapshot-date:''' window to see a list of the existing dates.   
 
+
10) You can also select a date for the snapshot so that this snapshot represents the project at the status date point in time.   
+
 
+
11) To see which snapshot dates already exist, just position your mouse over the '''NEW snapshot-date:''' window to see a list of the existing dates.   
+
  
 
<center>[[File:X61-3_0_2_1-61-(18H)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18H)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18H)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(18H)-5022018.png</center>-->
  
12) You can  use the built in calendar dropdown or type in the new snapshot’s month, day, and year in the window provided as shown below:
+
You can  use the built in calendar dropdown or type in the new snapshot’s month, day, and year in the window provided as shown below:
  
 
<center>[[File:X61-3_0_2_1-61-(18I)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(18I)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(18I)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(18I)-5022018.png</center>-->
  
13) Un-check the '''Show field mappings''' checkbox '''Off''' if you want to use the same '''field mappings''' as you used before.     
+
Un-check the '''Show field mappings''' checkbox '''OFF''' if you want to use the same '''field mappings''' as you used before.    The bottom of the screen now looks like this:
 
+
14) The bottom of the screen now looks like this:
+
  
 
<center>[[File:P60-3_0_1-60-(26)-01252017.png]]</center>
 
<center>[[File:P60-3_0_1-60-(26)-01252017.png]]</center>
<center>P60-3_0_1-60-(26)-01252017.png</center>
+
<!--<center>P60-3_0_1-60-(26)-01252017.png</center>-->
 
+
15) Pressing the large '''New''' button creates a new snapshot for the chart.  The chart opens at the new snapshot.   
+
  
16) The '''color''', '''fonts''', '''title''', and '''swimlane''' assignments are consistent between the two snapshots:
+
Pressing the large '''New''' button creates a new snapshot for the chart.  The chart opens at the new snapshot.    The '''color''', '''fonts''', '''title''', and '''swimlane''' assignments are consistent between the two snapshots:
  
 
<center>[[File:X61-3_0_2_1-61-(22)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(22)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(22)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(22)-5022018.png</center>-->
  
17) You can go back and forth between the two snapshots by using the '''snapshot forward/backward''' buttons on the '''View''' tab as shown below:
+
You can go back and forth between the two snapshots by using the '''snapshot forward/backward''' buttons on the '''View''' tab as shown below:
  
 
<center>[[File:X70-3_0_2_1-70-(23)-07122019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(23)-07122019.png]]</center>
<center>X70-3_0_2_1-70-(23)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(23)-07122019.png</center>-->
  
 
==Editing the Chart==
 
==Editing the Chart==
Line 442: Line 280:
 
===Editing Text Label Font Sizes===
 
===Editing Text Label Font Sizes===
  
1) You can '''edit''' the '''font sizes''' and '''text positions''' on task shapes to optimize readability.   
+
You can '''edit''' the '''font sizes''' and '''text positions''' on task bars to optimize readability.  To do this, hold down the left mouse button and '''drag''' a selection box ('''Lasso''') that encloses many tasks/milestones at once:
 
+
:a) To do this, hold down the left mouse button and '''drag''' a selection box ('''Lasso''') that encloses many tasks/milestones at once:
+
  
 
<center>[[File:X61-3_0_2_1-61-(24)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(24)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(24)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(24)-5022018.png</center>-->
  
:b) When you release the mouse, the enclosed tasks/milestones are all be selected:
+
When you release the mouse, the enclosed tasks/milestones are all be selected:
  
 
<center>[[File:X61-3_0_2_1-61-(25)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(25)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(25)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(25)-5022018.png</center>-->
  
:c) Click the '''Increase Font Size''' button on the tool bar shown below:
+
Click the '''Increase Font Size''' button on the tool bar shown below:
  
 
<center>[[File:X70-3_0_2_1-70-(26)-07122019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(26)-07122019.png]]</center>
<center>X70-3_0_2_1-70-(26)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(26)-07122019.png</center>-->
  
:d) The chart now looks something like this:
+
The chart now looks something like this:
  
 
<center>[[File:X61-3_0_2_1-61-(27)-5022018.png]]</center>
 
<center>[[File:X61-3_0_2_1-61-(27)-5022018.png]]</center>
<center>X61-3_0_2_1-61-(27)-5022018.png</center>
+
<!--<center>X61-3_0_2_1-61-(27)-5022018.png</center>-->
  
:e) Repeating this operation for the remaining tasks/milestones (we could have done '''Select All''' and done it all at once!), we obtain a chart with larger '''fonts''' on all the tasks/milestones:
+
Repeating this operation for the remaining tasks/milestones (we could have done '''Select All''' and done it all at once!), we obtain a chart with larger '''fonts''' on all the tasks/milestones:
  
 
<center>[[File:X70-3_0_2_1-70-(28)-07122019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(28)-07122019.png]]</center>
<center>X70-3_0_2_1-70-(28)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(28)-07122019.png</center>-->
  
 
===Editing Text Label Positions===
 
===Editing Text Label Positions===
  
2) Another common '''editing''' action is to move the task '''text label''' from their current positions to positions elsewhere around or on the task shape.   
+
Another common '''editing''' action is to move the task bar '''text label''' from their current positions to positions elsewhere around or on the task bar.  To do this, click the '''text label''' to select it and then click the '''Label Position''' button on the tool bar.  This action accesses the '''Label Position''' dropdown list where you can select one of the '''text-positioning''' buttons as shown here:
 
+
:a) To do this, click the '''text label''' to select it and then click the '''Label Position''' button on the tool bar.   
+
 
+
:b) This action accesses the '''Label Position''' dropdown list where you can select one of the '''text-positioning''' buttons as shown here:
+
  
<center>[[File:X70-3_0_2_1-70-(29)-07122019.png]]</center>
+
<center>[[File:X70-3_0_2_1-70-(29-1)-09082020.png]]</center>
<center>X70-3_0_2_1-70-(29)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(29-1)-09082020.png</center>-->
  
:c) At this point, as an example, click the '''Left''' option in the dropdown and the selected '''text label''' is moved to the left side of the task shape as shown here:
+
At this point, as an example, click the '''Left''' option in the dropdown and the selected '''text label''' is moved to the left side of the task bar as shown here:
  
 
<center>[[File:X70-3_0_2_1-70-(29A)-07122019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(29A)-07122019.png]]</center>
<center>X70-3_0_2_1-70-(29A)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(29A)-07122019.png</center>-->
  
:d) In case you change your mind about the '''last editing action''' you took, you can '''UNDO''' the '''last editing action''' by clicking the '''UNDO''' button above the OnePager tool bar.  Successive clicking the '''UNDO''' button undoes editing actions in the reverse order that they were applied.
+
In case you change your mind about the '''last editing action''' you took, you can '''UNDO''' the '''last editing action''' by clicking the '''UNDO''' button above the OnePager tool bar.  Successive clicking the '''UNDO''' button undoes editing actions in the reverse order that they were applied.
  
 
<center>[[File:X70-3_0_2_1-70-(31)-07122019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(31)-07122019.png]]</center>
<center>X70-3_0_2_1-70-(31)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(31)-07122019.png</center>-->
  
3) Save the '''edited''' chart by pressing the '''Save''' button above the tool bar next to the '''UNDO''' button.  All of the '''font size''' changes, '''text-position edits''', and the new '''Legend''' position are now '''saved''' in case you need to update this chart with new data at a later time.
+
Save the '''edited''' chart by pressing the '''Save''' button above the tool bar next to the '''UNDO''' button.  All of the '''font size''' changes, '''text-position edits''', and the new '''Legend''' position are now '''saved''' in case you need to update this chart with new data at a later time.
  
 
===Editing Other Chart Contents===
 
===Editing Other Chart Contents===
  
4) The examples above are just samples of '''Chart Editor''' capabilities provided for '''editing''' within the chart.   
+
The examples above are just samples of '''Chart Editor''' capabilities provided for '''editing''' within the chart.  Making other '''edits''' to task bars/milestone symbols and '''text labels''' are covered in more detail in this article:  [[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!--9.0.1-70-->
  
:a) Making other '''edits''' to task/milestone shapes and '''text labels''' are covered in more detail in this article:  [[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] 9.0.1-70.
+
Additionally, you can add task bar/milestone symbol information related to each task bar such as '''baseline data''', '''percent complete''' information, and '''critical path information'''. You can add '''comment boxes''' to task bars, '''free floating comment boxes in the chart''', vertical '''curtains''', and '''background images'''. And you can change the chart's '''Start/End Dates''', add or hide the '''Legend''', and add '''time axes''' at the top, bottom, and within the '''graph'''. Further, you are able to '''edit''' task bar/milestone symbol '''shapes''', you have at your disposal controls for '''editing''' '''rows/swimlanes''', '''headers and footers''' in the chart, '''background colors''', and other text information shown in the '''graph'''.
  
:b) Additionally, you can add task/milestone information related to each task shape such as '''baseline data''', '''percent complete''' information, and '''critical path information'''; you can add '''comment boxes''' to task shapes, '''free floating comment boxes in the chart''', vertical '''curtains''', and '''background images'''; and you can change the chart's '''Start/End Dates''', add or hide the '''Legend''', and add '''time axes''' at the top, bottom, and within the '''graph'''.
+
These capabilities and the articles that provide the detailed information on how to use them can be found in the set of article links at: [[OnePager Version 7.0#Ways to Make Changes to Your Chart | Ways to Make Changes to Your Chart]] <!--0.04-70 -->
 
+
:c) Further, you are able to '''edit''' task/milestone '''shapes''', you have at your disposal controls for '''editing''' '''rows/swimlanes''', '''headers and footers''' in the chart, '''background colors''', and other text information shown in the '''graph'''.
+
 
+
5) These capabilities and the articles that provide the detailed information on how to use them can be found in the set of article links at:   [[OnePager Version 7.0#Ways to Make Changes to Your Chart | Ways to Make Changes to Your Chart]] 0.04-70
+
  
 
==Enhanced Editing Capabilities Provided in OnePager Express Version 7.0==
 
==Enhanced Editing Capabilities Provided in OnePager Express Version 7.0==
Line 508: Line 336:
 
===Displaying Data-Driven Task Links===
 
===Displaying Data-Driven Task Links===
  
1) OnePager Express 7.0 is enhanced to assist you with displaying '''Task Link''' '''dependencies''' from the Microsoft Excel '''source plan''' data you provide.   
+
OnePager Express 7.0 is enhanced to assist you with displaying '''Task Link''' '''dependencies''' from the Microsoft Excel '''source plan''' data you provide.  Typically, this feature is turned '''OFF''' in all '''Template Properties''' forms distributed with OnePager.  However, the feature can be turned '''ON''' either before or after the creation of a chart. To turn the '''Data-Driven Task Link''' feature '''ON''' prior to creating a chart, go to the '''Template Properties''' form you plan to uses and click on the '''Task Links''' tab and then click the '''Import predecessors''' checkbox '''ON''' in the '''Data-Driven Task Links''' control group as shown below:
  
:a) Typically, this feature is turned '''OFF''' in all '''Templates''' distributed with OnePager.
+
<center>[[File:X70-3_0_2_1-70-(38-1)-09252020.png]]</center>
 +
<!--<center>X70-3_0_2_1-70-(38-1)-09252020.png</center>-->
  
:b) However, the feature can be turned '''ON''' either before or after the creation of a chart.
+
In the '''Template Task Link''' tab above there are two additional controls that need to be set to tell OnePager Express which data field you are using to express task '''dependencies''' in the form of '''predecessors''' and which '''dependency format''' you are using either (1) Microsoft Project or (2) Oracle Primavera.  These controls are in the form of dropdown menus as shown for the '''dependency format''' selector below:
  
2) To turn the '''Data-Driven Task Link''' feature '''ON''' prior to creating a chart, go to the '''Template''' form you plan to uses and click on the '''Task Links''' tab and then click the '''Import predecessors''' checkbox in the '''Data-Driven Task Links''' control group as shown below:
+
<center>[[File:X70-3_0_2_1-70-(38A-1)-09252020.png]]</center>
 +
<!--<center>X70-3_0_2_1-70-(38A-1)-09252020.png</center>-->
  
<center>[[File:X70-3_0_2_1-70-(38)-07122019.png]]</center>
+
With the '''Import predecessors''' checkbox checked '''ON''' and the '''dependency''' data field and '''dependency format''' selections made in the '''Template Properties''' form, the chart first created looks like this:
<center>X70-3_0_2_1-70-(38)-07122019.png</center>
+
 
+
:a) In the '''Template Task Link''' tab above there are two additional controls that need to be set to tell OnePager Express which data field you are using to express task '''dependencies''' in the form of '''predecessors''' and which '''dependency format''' you are using either (1) Microsoft Project or (2) Oracle Primavera. 
+
 
+
:b) These controls are in the form of dropdown menus as shown for the '''dependency format''' selector below:
+
 
+
<center>[[File:X70-3_0_2_1-70-(38A)-07122019.png]]</center>
+
<center>X70-3_0_2_1-70-(38A)-07122019.png</center>
+
 
+
:c) With the '''Import predecessors''' checkbox checked '''ON''' and the '''dependency''' data field and '''dependency format''' selections made in the '''Template''' form, the chart first created looks like this:
+
  
 
<center>[[File:X70-3_0_2_1-70-(39)-07122019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(39)-07122019.png]]</center>
<center>X70-3_0_2_1-70-(39)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(39)-07122019.png</center>-->
  
:d) To turn the '''Data-Driven Task Link''' feature '''ON''' after the chart is created, go to the '''Chart Properties''' form's '''Task Links''' tab and then click the '''Import predecessors''' checkbox in the '''Data-Driven Task Links''' control group as shown below:
+
To turn the '''Data-Driven Task Link''' feature '''ON''' after the chart is created, go to the '''Chart Properties''' form's '''Task Links''' tab and then click the '''Import predecessors''' checkbox '''ON''' in the '''Data-Driven Task Links''' control group as shown below:
  
<center>[[File:X70-3_0_2_1-70-(40-1)-07122019.png]]</center>
+
<center>[[File:X70-3_0_2_1-70-(40-2)-09252020.png]]</center>
<center>X70-3_0_2_1-70-(40-1)-07122019.png</center>
+
<!--<center>X70-3_0_2_1-70-(40-2)-09252020.png</center>-->
  
:e) Once imported, '''Data-Driven Task Links''' can be '''shown''' or '''hidden''' and can be edited globally using the '''Template/Chart Properties''' forms as shown above or individually using a selection right-click '''context menu'''.
+
Once imported, '''Data-Driven Task Links''' can be '''shown''' or '''hidden''' and can be edited globally using the '''Template Properties or Chart Properties''' forms as shown above or individually using a '''task link''' right-click '''context menu'''. OnePager Express 7.0 continues to support manual '''Task Links''' which in previous OnePager Express versions were called '''Event Links'''. The OnePager version 7.0 '''Data-Driven Task Links''' feature is flexible and powerful. 
  
:f) OnePager Express 7.0 continues to support manual '''Task Links''' which in previous OnePager Express versions were called '''Event Links'''.
+
More details are provided in the series of articles at:  [[Linking Task and Milestones Using Manual and Data-Driven Task Links for Version 7.0 | Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)]] <!--19.0.1-70-->
 
+
3) The OnePager version 7.0 '''Data-Driven Task Links''' feature is flexible and powerful. 
+
 
+
4) More details are provided in the series of articles at:  [[Linking Task and Milestones Using Manual and Data-Driven Task Links for Version 7.0 | Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)]]. 19.0.1-70
+
  
 
===Editing the Time Axis===
 
===Editing the Time Axis===
  
5) OnePager Express is also enhanced with new capabilities and feature so you can '''edit''' the '''time axis''' and configure it to focus on specific time periods of interest in your project schedule presentation.
+
OnePager Express is also enhanced with new capabilities and feature so you can '''edit''' the '''time axis''' and configure it to focus on specific time periods of interest in your project schedule presentation. As an example of the enhancements made to the '''time axis''' is the addition of the '''time axis cell stretch''' feature where you can lengthen the horizontal extend of any '''time axis cell''' so as to provide more space to focus on details within that time period.  An example of a stretched '''lower level time axis cell''' is shown below:
 
+
6) As an example of the enhancements made to the '''time axis''' is the addition of the '''time axis cell stretch''' feature where you can lengthen the horizontal extend of any '''time axis cell''' so as to provide more space to focus on details within that time period.  An example of a stretched '''lower level time axis cell''' is shown below:
+
  
 
<center>[[File:X70-3_0_2_1-70-(41)-07122019.png]]</center>
 
<center>[[File:X70-3_0_2_1-70-(41)-07122019.png]]</center>
<center>PX0-3_0_2_1-70-(41)-07122019.png</center>
+
<!--<center>PX0-3_0_2_1-70-(41)-07122019.png</center>-->
  
7) For additional detailed information on the '''editing''' of '''time axis cells''' and other related capabilities please see this article:  [[Modifying the Time Axis for Version 7.0 (Portal) | Modifying the Time Axis (Portal)]] 22.0.1-70.
+
For additional detailed information on the '''editing''' of '''time axis cells''' and other related capabilities please see this article:  [[Modifying the Time Axis for Version 7.0 (Portal) | Modifying the Time Axis (Portal)]] <!--22.0.1-70 -->
  
 
==Related Links==
 
==Related Links==
  
[[What's New with OnePager Release 7.0?]] 0.4-70
+
[[What's New with OnePager Release 7.0?]] <!--0.4-70-->
 
+
[[Getting Started with OnePager Express Version 7.0 Desktop | Getting Started with OnePager Express Desktop]] 3.0.2.2-70
+
  
[[Conditional Import for Version 7.0 (Portal) | Conditional Import Filters (Portal)]] 7.18.1-70
+
[[Getting Started with OnePager Express Version 7.0 Desktop | Getting Started with OnePager Express Desktop]] <!--3.0.2.2-70-->
  
[[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] 7.0.1-70
+
[[Conditional Import for Version 7.0 (Portal) | Conditional Import Filters (Portal)]] <!--7.18.1-70-->
  
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] 9.0.1-70
+
[[Basic Workflows for Version 7.0 (Portal) | Basic Workflows (Portal)]] <!--7.0.1-70-->
  
[[Linking Task and Milestones Using Manual and Data-Driven Task Links for Version 7.0 | Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)]] 19.0.1-70
+
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7.0 (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] <!--9.0.1-70-->
  
[[Modifying the Time Axis for Version 7.0 (Portal) | Modifying the Time Axis (Portal)]] 22.0.1-70
+
[[Linking Task and Milestones Using Manual and Data-Driven Task Links for Version 7.0 | Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)]] <!--19.0.1-70-->
  
[[Managing Chart Data for Version 7.0 | Managing Chart Data (Portal)]] 23.0.1-70
+
[[Modifying the Time Axis for Version 7.0 (Portal) | Modifying the Time Axis (Portal)]] <!--22.0.1-70-->
  
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] 24.0.1-70
+
[[Managing Chart Data for Version 7.0 | Managing Chart Data (Portal)]] <!--23.0.1-70-->
  
 +
[[Managing Templates for Version 7.0 (Portal) | Managing Templates (Portal)]] <!--24.0.1-70-->
  
 
(3.0.2.1-70)
 
(3.0.2.1-70)
Line 590: Line 403:
 
[[Category:Task Links]]
 
[[Category:Task Links]]
 
[[Category:Time Axis]]
 
[[Category:Time Axis]]
 +
[[Category:Multiple Swimlane Levels]]
 
[[Category:OnePager - Tool Bar]]
 
[[Category:OnePager - Tool Bar]]
 
[[Category:Help]]
 
[[Category:Help]]
 
[[Category:OnePager Express]]
 
[[Category:OnePager Express]]

Latest revision as of 15:35, 25 January 2021

Overview

As with previous version of OnePager Express, version 7.0 of OPX can be launched from a Desktop icon as well as from within Microsoft Excel (Add-in). Please note that after selecting the Add-in launch option that you are not be able to launch the OnePager Desktop application. Only one of these applications (Add-in or Desktop) can be active at a time. If you attempt to launch both, a warning message appears as shown below:

X70-3 0 2 1-70-(1)-07102019.png

Further note that as mentioned in What's New with OnePager Release 7.0? , this new version has enhanced features such as the User Interface Upgrade and Smart Task/Milestone Text Label Collision Avoidance Feature to name a few. This article provides the basic information needed to Getting Started and use OnePager Express (OPX) after you launch OPX from Microsoft Excel.

The article providing Getting Started guidance when launching from the OPX Desktop icon is at: Getting Started with OnePager Express Desktop

Launching OnePager Express for the First Time

The OPX Add-in automatically displays the OnePager icon on the Microsoft Excel ribbon's Add-in tool tab once OnePager is installed. That tool bar looks like this:

X70-3 0 2 1-70-(2)-07102019.png

Clicking the OnePager Express… button takes you to the Chart Editor. Clicking the Templates… button lets you edit the Template Properties form for your graphs. For now, it is simplest to use the default Template Properties form.

You can learn how Template Properties forms let you customize and standardize graph features later at: Managing Templates (Portal)

Before you launch OPX, however, you must have certain scheduling fields in your Microsoft Excel source plan. There is a lot of flexibility in how these fields can be named. A typical example is shown below. The only mandatory fields are fields representing Start, Finish, and Name. In this example, however, we are also including three optional fields:

1) A category field (Category) used to assign colors to tasks.
2) A selection field (Show It) used to choose which tasks to graph.
3) A Task ID field that OnePager uses to keep track of tasks/milestones as your Microsoft Excel plan is change through additions or deletions over the course of the project.
X70-3 0 2 1-70-(2A-1)-07102019.png

To control which tasks get graphed, you must specify a Flag field (e.g. Show It) that you wish to use. Numeric fields can also be used the same as the text fields where a 1 in a Number field indicates Yes and a 0 in a Number field indicates No. See how this is done in the illustration above. When making your first chart, we strongly recommend that you select 50 or fewer tasks with Yes. Please note that OPX is shipped with a number of fully populated Template Properties forms that are based on the Microsoft Excel source plan used in the Tutorial also shipped with the product – BlueGrass Project Plan. The following table describes field-heading types that OPX uses and shows variations on the heading titles that OnePager Express recognizes. It is not mandatory that you used these field names, since OPX gives you a chance to choose the actual Microsoft Excel source plan fields that it employs. However, using these names speeds things up because it helps OPX make reasonable guesses on which fields to use as its default selections. Note that three field heading types must always be present: Name, Start, and Finish.

We recommend the inclusion of an ID field with sequential numbering from top to bottom. This assists OnePager maintain a correspondence with Microsoft Excel’s rows after the Microsoft Excel source plan is updated.

X70-3 0 3-70-(3)-12082020.png

To launch OPX and make a chart, click on the OnePager Express... button on the Microsoft Express tool bar’s Add-ins tab, which accesses the OnePager Express Start form:

X70-3 0 2 1-70-(4)-07102019.png

The OnePager Express Start form provides you with three options:

1) NEW Clicking the NEW button brings up the OnePager choices (OPC) form.
2) UPDATE Clicking the UPDATE button allows you to BROWSE FILES for an existing chart or select a recently-opened chart.
3) OPEN Clicking the OPEN button allows you to BROWSE FILES for an existing chart or select a recently-opened chart. Once selected and opened, the chart is available for editing.

Creating a New Chart

Clicking the NEW button accesses the OnePager choices (OPC) form as shown below:

X70-3 0 2 1-70-(5)-07102019.png

Options on the New OnePager Choices form

The OPC form gives you more options for selecting source plans. The illustration above shows that OPX was initiated from Microsoft Excel with the source plan shown in the Selected File(s) group shown above. The Add/Remove button gives you the capability to add more source plans to the source packet or, for multiple file packets, to remove files. Clicking the Add/Remove button accesses the Data source selection form as shown below:

X70-3 0 2 1-70-(6)-07102019.png

The Data source selection form displays the current source plan that was loaded with Microsoft Excel when you clicked the OnePager Express... button. This form lets you Add more source Microsoft Excel source plans to create a multi-project chart or Remove a source plan from a multi-file source packet. These options are detailed below.

Adding a New Source Plan

When you click the Add button, OPX gives you the option to access a Windows Open form when you select the BROWSE FILES… option as shown here:

X70-3 0 2 1-70-(7)-07102019.png

Clicking the BROWSE FILES… option displays a Window’s Open from which you can select a Microsoft Excel source plan to add to the source packet. A sample Open form is shown below:

X70-3 0 2 1-70-(8)-07102019.png

When you select a desired Microsoft Excel source plan and click the Open button as shown above, OPX adds the source plan to the source packet and displays it in the Data source selection window as shown below:

X70-3 0 2 1-70-(9)-07102019.png

The selected source plan is added to the source packet as shown above. OPX shows the path name of the source plan in the window if you hover the mouse over the source plan name. If you select a recently used source plan from the dropdown menu displayed with the Add button is clicked in the Data source selection form, OPX adds that source plan to the source packet.

Removing a Source Plan

The Remove button allows you to remove a source plan from a source packet. if that source plan is not needed to create the new chart. To remove a file, first select the file in the Data source selection form’s window so that it is highlighted in blue then click the Remove button as shown in the sequence below:

X70-3 0 2 1-70-(10)-07102019.png
X70-3 0 2 1-70-(11)-07102019.png

Other Choices to Make

Moving on to the other groups of the OPC form, you are asked to confirm a few things before you build the chart. OPX makes good guesses for each of these choices, but you can change any of them:

X70-3 0 2 1-70-(15)-07112019.png

Starting Template

The current Template Properties form determines which fields get imported from Microsoft Excel and how the initial chart looks. OPX ships with many sample Template Properties forms, but you can also customize your own Template Properties form. To choose which Template Properties form to use in building your chart, click the Change… button in the top group of the OPC form.

X70-3 0 2 1-70-(15A)-07112019.png

For now, just stick with the default Template Properties form entitled Single Project Gantt View – Detailed, but you can always use a different Template Properties form to get a different type of chart.

Title of the New Chart

This is the Title of the graph and also the suggested save name in which it is saved. You can change the save name when you save it. We recommend that you enter a Title that helps you identify the chart later on as shown here:

X70-3 0 2 1-70-(15B)-07112019.png

For each chart you create, OnePager remembers colors, titles, legends, font sizes, and all other graph properties so that your work is saved. Later, you can update the chart with a snapshot of how the project looks on a different date. Then you can browse through the snapshots to see how the project is changing over time. OPX also saves the path name associated with the save name (.TAM). Path names are not available in .TAMs produced with version of OPX prior to version 6.0.

Task Selection

This is how you tell OPX which tasks to import from your Microsoft Excel source plan as indicated below:

X70-3 0 2 1-70-(15C)-07112019.png

Either click the Select all tasks radio button to graph everything or choose a Flag field. You can make several charts from a single Microsoft Excel source plan, each using a different Flag or Number field. In OPX if no Flags are set to Yes, OPX provides the user with a warning message shown below:

X70-3 0 2 1-70-(15D)-07112019.png

Clicking the Select tasks by custom filter button enables the Edit filters... button. Clicking the Edit filters... button takes you to a form that controls the Conditional Import Filters feature as shown here:

X70-3 0 2 1-70-(15E)-07112019.png

For more detailed information, please see the article at: Conditional Import Filters (Portal)

Snapshot Date

This is the date of the report and lets you keep track of how schedules change over time. The snapshot date is set by default as the current date taken from your computer. You can change the snapshot date by clicking on the dropdown button at the window shown in the illustration below:

X70-3 0 2 1-70-(15F)-07112019.png

Making a calendar date selection as shown above establishes the snapshot date for the chart and the snapshot being created. Each chart can have many snapshots. Snapshots and their management are important topics. Snapshots are the basis of how OnePager Express helps you track the progress of your project.

For more information, please see the articles at: Managing Chart Data (Portal)

Show Field Mappings

The Show field mappings checkbox near the bottom of the form. When this box is checked you have a chance to review and change the Microsoft Excel field mappings to OPX before you make your first chart. To do this, click the Next> button. You see the following screen:

X70-3 0 2 2-70-(15AA)-07162019.png

Notice in the graphic above that OPX has relied on the current Template Properties form to make some guesses on what Microsoft Excel fields should be used in making the graph. You can easily change any of these field mappings by making selections from the dropdown menus. For example, we show below how to change the Color:

X70-3 0 2 1-70-(15H)-07112019.png

Making the Graph

Once you are satisfied with the field mappings, click on Create new chart button to import your selected Microsoft Excel source plan data and create a chart. After a few second you see a screen that looks like this:

X70-3 0 2 1-70-(17)-07112019.png

Note that each task or milestone was color coded based on the value in the Category field. The Legend contains an optional diagram near the bottom, explaining that the bars inside the Gantt bars represent percent complete extracted from Microsoft Excel. Percent complete comes from a Microsoft Excel field that you specified in the field mapping form. Note that the current Template Properties form is the Template used by OnePager Express to create the first chart and determines how your data looks in the new chart. The Template Properties form’s Task Bars tab showing where the color control is located is shown below:

X70-3 0 2 1-70-(18-1)-09212020.png

Copying the Chart to Microsoft PowerPoint

OnePager provides access to the Windows clipboard so you can copy the chart and paste it into another application. To copy the current snapshot to the clipboard click the Copy button on the Home ribbon as shown below:

X70-3 0 2 1-70-(32A)-07112019.png

Then launch Microsoft PowerPoint and paste the clipboard copy of the chart into a Microsoft PowerPoint slide, as shown below:

X61-3 0 2 1-61-(32)-5032018.png

That’s it! You created a professional 1-page schedule summary from a complex Microsoft Excel schedule and copied it into a Microsoft PowerPoint presentation.

You can also print the chart by selecting the Print button on the File tab. OnePager has other features that let you move tasks vertically to different rows and swimlanes, change the number of swimlanes, add swimlane titles, show dependencies among tasks, change task colors, hide tasks, add floating comment boxes, and standardize on graph styles across organizations.

To learn more about these features, read about the specific workflows in this Wiki at Basic Workflows (Portal) and Manual versus Data-Driven Editing (Portal)

Opening a Chart

The right-most button on the OPC form is the OPEN button. Clicking the OPEN button displays a dropdown menu which happens to be the same for the UPDATE buttons. The options in the dropdown are discussed below:

X70-3 0 2 1-70-(18A)-07112019.png

Clicking the BROWSE FILES... option accesses a Windows Open form from which you can select a .TAM that you want to open. Selecting the desired .TAM causes OPX to display the selected chart in the Chart Editor. From this position, you can edit the chart, save it, or share it with others. Clicking any of the RECENT chart items the dropdown menu above causes OPX to load the associated .TAM into the Chart Editor where you can edit the chart, save it, or share it with others.

Replacing A Snapshot - Updating a Chart with Changes Made to the Microsoft Excel Source Plan's Data

Suppose after examining the chart you created and saved, you realize that it might be best to show more task bars. This, you think, would greatly improve the schedule presentation. Updating the chart at this point is a simple matter. Recall that OPX is active and the Chart Editor is displaying the current chart you want to update. Additionally, the Microsoft Excel source plan and the application are active. The original chart looked like this:

X61-3 0 2 1-61-(18B)-5022018.png

Since Microsoft Excel is still an active program and the Microsoft Excel source plan you are using is still being displayed, go back to the Microsoft Excel application and change the Show It field setting for the rows you want to now display from No to Yes for the rows you want to now display. As section of the Microsoft Excel source plan where this is done is shown below:

X61-3 0 2 1-61-(18C)-5022018.png

Once you’ve made the Show It field changes lines 7 through 15 in the Microsoft Excel the source plan looks like this:

X61-3 0 2 1-61-(18D)-5022018.png

With the Microsoft Excel source plan updated, go back to OPX and navigate to the Data tab on the ribbon where there are several buttons. To update your chart to now show the additional rows from your Microsoft Excel source plan click the Replace Snapshot button as shown below:

X70-3 0 2 1-70-(17C)-07112019.png

When you click the Replace Snapshot button, OPX goes back to the associated Microsoft Excel source plan that you just changed, imports all the rows that changed, and update your chart. At the conclusion of the operation, the updated chart looks like this:

X61-3 0 2 1-61-(18E)-5022018.png

The example above is just one of many uses of the Data tab’s Replace Snapshot button when you need to update a chart. You can do this as many times as necessary until the chart is the way you need it. In addition to adding and removing rows by changing the Show It field, you can change source plan task Start Dates, Finish Dates, or Resource Names' and display these data changes in the chart. Using the procedure above you can do this very efficiently. You can now save the chart by giving it a save name. When you save the chart in OPX, OnePager saves the .TAM and saves the Microsoft Excel source plan name and path information. This is useful when you want to further update the chart or when you want to add a snapshot later on. In the examples below it is assumes that the chart is saved as BlueGrass Project Report - Express.

Adding a Snapshot - Adding to the Chart with Changes Made to the Microsoft Excel Source Plan's Data

The power of OPX is illustrated when, after a period of progress on the project, it is time to produce another chart. OnePager produces your next snapshot with the same look and feel as the original. Assuming that the Microsoft Excel source plan was updated with actual start and finish, percent complete, and other relevant data during the reporting interval, OPX can easily generate a new snapshot. Suppose we have the following chart created on 11/1/2018 and we want to create another graph from the updated Microsoft Project source plan on 12/1/2018.

X61-3 0 2 1-61-(18F)-5022018.png

Before creating a new snapshot for 12/1/2018 as planned, we need to update the Microsoft Excel source plan say by updating the Percent Complete for the following tasks to the percentage indicated:

  • Eng. Team 1 Dev. - 100%
  • Internal Perf. Test - 10%
  • Create MERLIN System - 100%
  • Create ADONIS System - 25%

When the source plan is updated with this revised information we can proceed. Launch OPX either from Microsoft Excel or from the Desktop icon and click the UPDATE button on the OnePager Express Start form. Doing so accesses the following OnePager choices (OPC) form:

X61-3 0 2 1-61-(18G)-5022018.png

In the OPC form above we selected the NEW snapshot at date: as shown. You can also select a date for the snapshot so that this snapshot represents the project at the status date point in time. To see which snapshot dates already exist, just position your mouse over the NEW snapshot-date: window to see a list of the existing dates.

X61-3 0 2 1-61-(18H)-5022018.png

You can use the built in calendar dropdown or type in the new snapshot’s month, day, and year in the window provided as shown below:

X61-3 0 2 1-61-(18I)-5022018.png

Un-check the Show field mappings checkbox OFF if you want to use the same field mappings as you used before. The bottom of the screen now looks like this:

P60-3 0 1-60-(26)-01252017.png

Pressing the large New button creates a new snapshot for the chart. The chart opens at the new snapshot. The color, fonts, title, and swimlane assignments are consistent between the two snapshots:

X61-3 0 2 1-61-(22)-5022018.png

You can go back and forth between the two snapshots by using the snapshot forward/backward buttons on the View tab as shown below:

X70-3 0 2 1-70-(23)-07122019.png

Editing the Chart

Editing Text Label Font Sizes

You can edit the font sizes and text positions on task bars to optimize readability. To do this, hold down the left mouse button and drag a selection box (Lasso) that encloses many tasks/milestones at once:

X61-3 0 2 1-61-(24)-5022018.png

When you release the mouse, the enclosed tasks/milestones are all be selected:

X61-3 0 2 1-61-(25)-5022018.png

Click the Increase Font Size button on the tool bar shown below:

X70-3 0 2 1-70-(26)-07122019.png

The chart now looks something like this:

X61-3 0 2 1-61-(27)-5022018.png

Repeating this operation for the remaining tasks/milestones (we could have done Select All and done it all at once!), we obtain a chart with larger fonts on all the tasks/milestones:

X70-3 0 2 1-70-(28)-07122019.png

Editing Text Label Positions

Another common editing action is to move the task bar text label from their current positions to positions elsewhere around or on the task bar. To do this, click the text label to select it and then click the Label Position button on the tool bar. This action accesses the Label Position dropdown list where you can select one of the text-positioning buttons as shown here:

X70-3 0 2 1-70-(29-1)-09082020.png

At this point, as an example, click the Left option in the dropdown and the selected text label is moved to the left side of the task bar as shown here:

X70-3 0 2 1-70-(29A)-07122019.png

In case you change your mind about the last editing action you took, you can UNDO the last editing action by clicking the UNDO button above the OnePager tool bar. Successive clicking the UNDO button undoes editing actions in the reverse order that they were applied.

X70-3 0 2 1-70-(31)-07122019.png

Save the edited chart by pressing the Save button above the tool bar next to the UNDO button. All of the font size changes, text-position edits, and the new Legend position are now saved in case you need to update this chart with new data at a later time.

Editing Other Chart Contents

The examples above are just samples of Chart Editor capabilities provided for editing within the chart. Making other edits to task bars/milestone symbols and text labels are covered in more detail in this article: Manual Editing Task/Milestone Shapes and Text Labels (Portal)

Additionally, you can add task bar/milestone symbol information related to each task bar such as baseline data, percent complete information, and critical path information. You can add comment boxes to task bars, free floating comment boxes in the chart, vertical curtains, and background images. And you can change the chart's Start/End Dates, add or hide the Legend, and add time axes at the top, bottom, and within the graph. Further, you are able to edit task bar/milestone symbol shapes, you have at your disposal controls for editing rows/swimlanes, headers and footers in the chart, background colors, and other text information shown in the graph.

These capabilities and the articles that provide the detailed information on how to use them can be found in the set of article links at: Ways to Make Changes to Your Chart

Enhanced Editing Capabilities Provided in OnePager Express Version 7.0

Displaying Data-Driven Task Links

OnePager Express 7.0 is enhanced to assist you with displaying Task Link dependencies from the Microsoft Excel source plan data you provide. Typically, this feature is turned OFF in all Template Properties forms distributed with OnePager. However, the feature can be turned ON either before or after the creation of a chart. To turn the Data-Driven Task Link feature ON prior to creating a chart, go to the Template Properties form you plan to uses and click on the Task Links tab and then click the Import predecessors checkbox ON in the Data-Driven Task Links control group as shown below:

X70-3 0 2 1-70-(38-1)-09252020.png

In the Template Task Link tab above there are two additional controls that need to be set to tell OnePager Express which data field you are using to express task dependencies in the form of predecessors and which dependency format you are using either (1) Microsoft Project or (2) Oracle Primavera. These controls are in the form of dropdown menus as shown for the dependency format selector below:

X70-3 0 2 1-70-(38A-1)-09252020.png

With the Import predecessors checkbox checked ON and the dependency data field and dependency format selections made in the Template Properties form, the chart first created looks like this:

X70-3 0 2 1-70-(39)-07122019.png

To turn the Data-Driven Task Link feature ON after the chart is created, go to the Chart Properties form's Task Links tab and then click the Import predecessors checkbox ON in the Data-Driven Task Links control group as shown below:

X70-3 0 2 1-70-(40-2)-09252020.png

Once imported, Data-Driven Task Links can be shown or hidden and can be edited globally using the Template Properties or Chart Properties forms as shown above or individually using a task link right-click context menu. OnePager Express 7.0 continues to support manual Task Links which in previous OnePager Express versions were called Event Links. The OnePager version 7.0 Data-Driven Task Links feature is flexible and powerful.

More details are provided in the series of articles at: Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)

Editing the Time Axis

OnePager Express is also enhanced with new capabilities and feature so you can edit the time axis and configure it to focus on specific time periods of interest in your project schedule presentation. As an example of the enhancements made to the time axis is the addition of the time axis cell stretch feature where you can lengthen the horizontal extend of any time axis cell so as to provide more space to focus on details within that time period. An example of a stretched lower level time axis cell is shown below:

X70-3 0 2 1-70-(41)-07122019.png

For additional detailed information on the editing of time axis cells and other related capabilities please see this article: Modifying the Time Axis (Portal)

Related Links

What's New with OnePager Release 7.0?

Getting Started with OnePager Express Desktop

Conditional Import Filters (Portal)

Basic Workflows (Portal)

Manual Editing Task/Milestone Shapes and Text Labels (Portal)

Linking Task and Milestone Using Manual and Data-Driven Task Links (Portal)

Modifying the Time Axis (Portal)

Managing Chart Data (Portal)

Managing Templates (Portal)

(3.0.2.1-70)