Here are the steps to create a new chart:

P60-7 1 1-53-(1)-09162016.png

Procedures

1) Launch Microsoft Project and bring up the desired Microsoft Project source plan.

2) Set the Flags/Numbers field into the Microsoft Project source plan. This is the flag that OnePager uses to determine which rows to import. Determine which of the task/milestone rows are to be included and set the Flags/Numbers field cell to Yes for these while leaving the remainder of the task/milestone row’s flag field set to No, 0, or blank.

3) Click the OnePager button to bring up the OnePager Pro Start form.

P60-7 1 1-53-(2)-09162016.png
a) Alternatively, clicking the Template... button accesses a window with the Template which can be changed and saved.
P60-7 1 1-60-(3)-01302017.png
P60-7_1_1-60-(3)-01302017.png
b) The Template's format is very similar to the OnePager Chart Properties form which is described elsewhere. It is, in fact, the source of what appears in the Chart Properties form.
c) Once the desired changes to the current Template are made, save the Template and return to step 3) above.

4) At the completion of step 3) when you click the NEW button, OnePager displays a OnePager choices (OPC) form as shown below:

P60-7 1 1-60-(4)-01302017.png
P60-7_1_1-60-(4)-01302017.png
a) It is recommended that the chart name selected refer to both the project and, perhaps, the audience that viewing the completed chart.
b) Additionally, notice that the Select Tasks with ‘YES’ in field: is showing Flag20 as a default. Most users select Flag20 to tell OnePager which task/milestone rows to import but any of the 20 Flag fields or any of the 20 Number fields can be used. It is important that the flag field number represented in this window correspond to the flag field containing the Yes and No data placed in the Microsoft Project plan.
c) The Snapshot date represents the time now or as-of date for the project report you are about to create. If the date created by OnePager does not reflect the status date required, change the date by using the calendar dropdown window. As the plan changes later on, you can create additional snapshots to show changes consistently.
d) Finally, note that the Show field mappings checkbox is checked as shown above. Checking this checkbox and pressing the Next> button takes you to the form shown below:
P60-3 0 1-60-(16AA)-03072017.png
P60-3_0_1-60-(16AA)-03072017.png

5) This allows you to change which Microsoft Project source plan fields are used for various purposes such as task name and start date. The Edit current template button also gives you a second chance to change many more initial properties of the chart. Once these choices are confirmed or changed, click the Create new chart button and OnePager imports the flagged data and make the chart.

6) Once the chart is produced, you can edit it such as by clicking shapes and using the controls on the ribbon or right-clicking, double-clicking, or dragging the shapes.

7) When the desired editing is complete, click the Copy to Clipboard button on the ribbon and paste the graph into a Microsoft PowerPoint presentation, email message, or Microsoft Word document. If the chart contains more than one page, you can choose to copy the entire document, the last page (current page), or a selected numerical page to the clipboard.

8) OnePager can save all charts and snapshots after editing.

Related Links

Creating a NEW Chart via Pull Operation - OnePager Pro 7.13.1-70

Creating a NEW Chart via Pull Operation - OnePager Express 7.13.2-70

REPLACING a Snapshot via Pull Operation - OnePager Pro 7.14.1-70

REPLACING a Snapshot via Pull Operation - OnePager Express 7.14.2-70

ADDING a Snapshot via Pull Operation - OnePager Pro 7.15.1-70

ADDING a Snapshot via Pull Operation - OnePager Express 7.15.2-70

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro 7.16.1-70

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express 7.16.2-70

Using the OnePager "Data" Tab's "Selected file(s)" Button 7.17.1-70

(7.1.1-70)