Creating a NEW Project View - OnePager Pro Desktop for Version 7.0

From OnePager Documentation
Jump to: navigation, search

Overview

Here are the steps to create a new chart:

P60-7 1 2-53-(1)-09162016.png

Procedures

1) Set Flags/Numbers field into the Microsoft Project source plan. This is the flag that OnePager uses to determine which rows to import. Determine which of the task/milestone rows are to be included and set the Flags/Numbers cell to Yes for these while leaving the remainder of the task/milestone row’s flag field set to No, 0, or blank.

2) Launch OnePager from the desktop icon.

3) The OnePager splash page appears briefly followed by the OnePager Chart Editor form displaying the OnePager Pro Start form as shown below:

P60-7 1 2-53-(2)-09162016.png

4) At the completion of step 3) when you click the “NEW” button, OnePager displays an abbreviated OnePager choices (OPC) form as shown below:

P60-3 0 2-60-(4)-01272017.png
P60-3_0_2-60-(4)-01272017.png

5) Click the Select button. The OnePager application wthen provides a dropdown menu for you to either choose to use the BROWSE FILES... to select a source plan or click the RECENT MS Project Files... option to access Microsoft Project Server source files:

P60-3 0 2-60-(5)-01272017.png
P60-3_0_2-60-(5)-01272017.png

6) Clicking the BROWSE FILES… option as shown above accesses a Windows Open form where you can select a Microsoft Project source plan to load as shown here:

P60-3 0 2-60-(6)-01272017.png
P60-3_0_2-60-(6)-01272017.png

7) When you click the Open button on the Windows Open form above, OnePager loads the selected Microsoft Project source plan and provide you with the expanded OPC form so that you can confirm or change the settings before OnePager creates the new chart.

P60-7 1 2-60-(7)-01302017.png
P60-7_1_2-60-(7)-01302017.png
a) As shown above, OnePager displays the loaded Microsoft Project source plan in the Selected File(s) group of the OPC form. You can use the Add/Remove feature (described elsewhere) to modify the choice of Microsoft Project source plan, add additional files to the source packet, and remove files. Clicking the Add/Modify button brings up the Data source selection form as shown below:
P60-3 0 1-60-(16AA)-03072017.png
P60-3_0_1-60-(16AA)-03072017.png
b) It is recommended that the chart name selected refer to both the project and, perhaps, the audience that is viewing the completed chart.
c) Additionally, notice that the Select Tasks with ‘YES’ in field: is showing Flag20 as a default. Most users select Flag20 to tell OnePager which task/milestone rows to import but any of the 20 Flag fields or any of the 20 Number fields can be used. It is important that the flag field number represented in this window correspond to the flag field containing the Yes and No data placed in the Microsoft Project source plan.
d) The Snapshot date represents the time now or as-of date for the project report you are about to create. If the date created by OnePager does not reflect the status date required, change the date by using the calendar dropdown window. As the source plan changes later on, you can create additional snapshots to show changes consistently.
e) Finally, note that the Show file mappings checkbox is checked as shown above. Checking this checkbox and pressing the Next> button takes you to the form shown below:
P60-3 0 2-60-(7)-01272017.png
P60-3_0_2-60-(7)-01272017.png

8) This allows you to change which Microsoft Project source plan fields are used for various purposes such as task name and start date. The Edit current template button also gives you a second chance to change many more initial properties of the chart. Once these choices are confirmed or changed, click the Create new chart button and OnePager imports the flagged data and make the chart.

9) Once the chart is produced, you can edit it such as by clicking shapes and using the controls on the ribbon or right-clicking, double-clicking, or dragging the shapes.

10) When the desired editing is complete, click the Copy to Clipboard button on the ribbon and paste the graph into a Microsoft PowerPoint presentation, email message, or Microsoft Word document. If the chart contains more than one page, you can choose to copy the entire document, the last page (current page), or a selected numerical page to the clipboard.

11) OnePager can save all charts and snapshots after editing.

Related Links

Creating a NEW Chart via Pull Operation - OnePager Pro 7.13.1-70

Creating a NEW Chart via Pull Operation - OnePager Express 7.13.2-70

REPLACING a Snapshot via Pull Operation - OnePager Pro 7.14.1-70

REPLACING a Snapshot via Pull Operation - OnePager Express 7.14.2-70

ADDING a Snapshot via Pull Operation - OnePager Pro 7.15.1-70

ADDING a Snapshot via Pull Operation - OnePager Express 7.15.2-70

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Pro 7.16.1-70

Custom Update (Replacing) of a Snapshot via Pull Operation - OnePager Express 7.16.2-70

Using the OnePager "Data" Tab's "Selected file(s)" Button 7.17.1-70

(7.1.2-70)