==Introduction to the Percent Complete Feature in OnePager==
+
==Introduction to the Baselines Feature in OnePager==
  
This article describes OnePager’s '''Percent Complete''' feature.  The article covers the '''Add-in''' and '''Standalone''' editions of OnePager Pro, OnePager Express, and OnePager 360.  Illustrations used in this article are from OnePager Pro but the feature's function, controls, and manual edits apply equally to OnePager Express and OnePager 360.
+
This article describes OnePager’s '''Baselines''' feature.  The article covers the '''Add-in''' and '''Standalone''' editions of OnePager Pro, OnePager Express, and OnePager 360.  Illustrations used in this article are from OnePager Pro but the feature's function, controls, and manual edits apply equally to OnePager Express and OnePager 360.
  
==About Editing Percent Complete==
+
==About Editing Baselines==
  
'''Percent complete''' displays are driven by the '''Percent complete''' field data '''imported''' from the Microsoft Project '''source plan'''.  The Microsoft Project '''%Complete''' field is the defaultYou have the option to change the name of the Microsoft Project field used to display '''Percent complete''' in the chart. Not every task in a Microsoft Project '''source plan''' has '''Percent complete''' data associated with it.  '''Percent complete''' data for milestone symbols are usually either zero (0%) or totally (100%) complete.  When you want to display '''Percent complete''' information, it is essential that these data be properly represented in the associated '''source plan''' before the data are '''imported''' to OnePager.
+
'''Baseline property''' displays are driven by the '''baseline start and finish dates imported''' from the Microsoft Project '''source plan'''.  Not every task bar/milestone symbol in a Microsoft Project '''source plan''' has designated '''baseline start and finish dates'''.  A milestone symbols’ '''start and finish dates''' are usually the same.  When you need to display '''baseline property''' information, it is essential that the associated data be properly represented in your '''source plan''' before the data are '''imported''' to OnePager.
  
==Editing All Task Percent Complete Displays==  
+
==Editing All Task/Milestone Baseline Properties==
  
===Chart Properties Form - Task Bars Tab===
+
All task bars and milestone symbol '''baseline properties''' can be modified without changing the settings in the current '''Template Properties''' form by clicking the '''Chart Properties''' button on the OnePager '''Home''' ribbon tool bar tab in the '''Settings''' group. Next, navigate to either the '''Task Bars''' or '''Milestones''' tab as appropriate and ensure that the '''Baseline markers''' checkbox is checked '''ON''' as shown below:
  
All task bar '''Percent complete''' displays are '''edited''' without changing the settings in the current '''Template Properties''' form by using these steps. Click the '''Chart Properties''' button on the OnePager '''Home''' ribbon tool bar tab in the '''Settings''' group. Next, navigate to either the '''Task Bars''' tab on the '''Chart Properties''' form. Ensure that the '''Percent complete''' checkbox is checked '''ON''' as shown below:
+
<center>[[File:P70-10_5_1-(1-1)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(1-1)-06022020.png</center>-->
  
<center>[[File:P70-10_3_1-(1)-06012020.png]]</center>
+
Once the '''Baseline markers''' checkbox is checked '''ON''', '''baselines''' can be customized by clicking the '''Baseline Properties''' button which accesses the '''Set baseline properties''' form shown here:
<!--<center><P70-10_3_1-(1)-06012020.png></center>-->
+
  
===Set Percent-Complete Properties Form===
+
<center>[[File:P70-10_5_1-(2)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(2)-06022020.png</center>-->
  
Click the '''%Complete Properties''' button to access the '''Set percent-complete properties form''' shown here:
+
You can now '''edit''' '''baseline properties''' for task bars/milestone symbols using the '''Set Baseline Properties''' form.
  
<center>[[File:P70-10_3_1-(2)-06012020.png]]</center>
+
===Change Baseline Shape===
<!--<center><P70-10_3_1-(2)-06012020.png></center>-->
+
  
There are three (3) checkbox controls in the '''Set percent-complete properties''' form:  
+
The controls for changing the '''shape''' of the '''baseline''' are the same as for task bars/milestone symbols discussed in this article at: [[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] 9.2.1-70
  
:* The first is associated with the OnePager feature for '''Honoring non-working times''' when OnePager represents '''Percent complete''' when '''Non-Working Times''' are being considered in the chart.
+
The '''baseline shapes''' available are the same as for task bars/milestone symbols as shown in the '''Set baseline properties''' form below:
:* For changing the '''properties''' of the '''percent complete bar''' and
+
:* To change the '''properties''' of the '''percent complete label'''.
+
  
====Honoring Non-Working Times====
+
<center>[[File:P70-10_5_1-(3)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(3)-06022020.png</center>-->
  
Checking the '''Honoring non-working times''' checkbox '''ON''' tells OnePager to consider the inclusion of '''Non-Working Times''' in the representation of '''%Complete''' in the chart.
+
There are numerous '''baseline''' shapes that can be selected. Use the scroll bar on the right of the dropdown list to make your selection. When the selection is made, either continue to make additional properties changes or click the '''OK''' button to get back to the '''Chart Properties''' form where all '''edits''' are applied.
  
For more information on the '''Management of working hours and non-working hours''', please see the section in the article at:  [[Managing Working Hours and Non-Working Hours for OnePager Pro for Version 7.0#The Honor Non-Working Time Feature | Managing Working Hours and Non-Working Hours for OnePager Pro - The Honor Non-Working Time Feature]] 22.5.3-70
+
===Change Baseline Fill Pattern===
  
====Show Percent-Complete Bars====
+
In a fashion very similar to the way '''fill patterns''' are changed for task bars/milestone symbols, once again access the '''Set baseline properties''' form as before, navigate to the '''Use custom fills''' checkbox, check it '''ON''' to '''enable''' the dropdown, and use the associated dropdown list to make your selection as shown below:
  
Checking the '''Show percent-complete bars''' checkbox '''ON enables''' controls over the '''color''' of the '''percent complete bar''' displayed in the task bar and the '''height''' of the '''percent complete bar''' within the task bar as a percent of the total task bar's (Gantt bar) '''height'''. Clicking the '''%Complete color''' dropdown menu accesses the standard '''Color Chooser''' form where you can set the specific '''color''' for the '''percent complete bar'''. You can also use the '''%Complete height''' control to set the relative '''height''' of the '''Percent complete bar''' as a percentage of the total task bar '''height'''. When selecting a '''percentage''' for the '''percent complete bar height''', recall that task bars can vary in '''height''' through manual '''editing'''.  Therefore, applying this control to '''all''' task bars results in varying '''heights''' for the '''percent complete bar''' as well.
+
<center>[[File:P70-10_5_1-(4)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(4)-06022020.png</center>-->
  
====Show Percent-Complete Text====
+
When the selection is made, either continue to make additional properties changes or click the '''OK''' button to get back to the '''Chart Properties''' form where all changes can be applied.
  
Checking the '''Show percent-complete text''' checkbox '''ON enables''' control for the '''percent complete text''' (numerical) associated with the task bar.  You can choose to display the '''percent complete bar''' only, the '''percent complete text''' only, or both using these two checkboxes.  When '''enabled''', you have the following controls to '''edit''' the appearance of the '''percent complete''' information for '''all''' task bars:
+
===Change Baseline Height Percentage===
  
:* The '''%Complete font''' controls respond exactly as other '''label/text font''' controls found elsewhere in OnePager. 
+
The '''Height percentage''' control is located just below the '''Baseline custom shape''' dropdown. This control, shown above, allows you to change the '''height''' of the '''baseline''' as a percentage of the total '''height''' of the parent task bar/milestone symbol (task and baseline information included). The '''default setting''' is 30 percent (%) and a portion of the chart with '''baselines''' checked '''ON''' looks like this:
:* Clicking the '''%Complete font''' dropdown menu button accesses the standard '''Set font properties''' form.
+
:* Similarly, the '''Label position''' dropdown menu button gives you access to the '''twelve (12) available positions''' to place the '''percent complete text'''.
+
:* Finally, the '''Separator''' dropdown menu button provides you with '''eight (8) options''' for '''separating''' the '''percent complete text''' from the task bar '''label''' or '''start/finish dates'''.
+
  
When the '''%Complete''' checkbox is checked '''ON''' and both the '''Show percent-complete bars''' and '''Show percent-complete text''' checkboxes are checked '''ON''' in the '''Set percent-complete properties''' form, the '''percent complete''' information for task bars looks like this:
+
<center>'''Baseline Shapes with 30 Percent Height Setting'''</center>
 +
<center>[[File:P70-10_5_1-(5)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(5)-06022020.png</center>-->
  
<center>[[File:P70-10_3_1-(3)-06012020.png]]</center>
+
Increasing this value makes the '''baseline''' taller (higher) with respect to the task bar/milestone symbol. To change the value, navigate to the '''Height percentage''' control in the '''Specify how to display baseline properties''' control group of the '''Set baseline properties''' form.  Change the value with the controls provided. If you double the value to 60 percent, for example, the resulting baselines would look like this:
<!--<center><P70-10_3_1-(3)-06012020.png></center>-->
+
  
==Editing Individual Task Percent Complete Display==
+
<center>'''Baseline Shapes with 60 Percent Height Setting'''</center>
 +
<center>[[File:P70-10_5_1-(6)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(6)-06022020.png</center>-->
  
The default settings for displaying '''Percent complete''' information for individual task bar can be '''edited''' as follows:
+
===Change Baseline Transparency===
  
===Selecting Individual Task Bar or Bars===
+
The '''transparency''' control makes the '''baseline less transparent''' (opaque) when the value in the window of the form is '''decreased''' or as shown below where the value is set at its default of 0% (the '''baseline''' is highlighted in orange): 
  
You can select the task bar by right-clicking on it to access the '''task bar''' right-click '''context menu''' with the '''Format…''' command, the '''task bar name label''' right-click '''context menu''', or click the '''Format…''' button on the OnePager '''Home''' ribbon tool bar tab after selecting the desired tasks/milestones.  
+
<center>[[File:P70-10_5_1-(7)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(7)-06022020.png</center>-->
  
For examples on how access the '''Change Task/Milestone Properties''' from from the chart, please see the sub-section at:  [[Labeling Task/Milestone Dates for OnePager for Version 7.1#Right-Clicking a Task Bar/Milestone Symbol or Task Bar Name Label | Labeling Task/Milestone Dates for OnePager - Right-Clicking a Task Bar/Milestone Symbol or Task Bar Name Label]] 10.1.1-71
+
With this setting for '''transparency''' and '''baseline''' shape '''color''', the chart portion looks like this:
 +
 
 +
<center>[[File:P70-10_5_1-(8)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(8)-06022020.png</center>-->
 +
 
 +
When you need to make the '''baseline shape more transparent''' '''increase''' the percentage value as shown below where the value is '''increased''' to 60%:
 +
 
 +
<center>[[File:P70-10_5_1-(9)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(9)-06022020.png</center>-->
 +
 
 +
With the '''transparency''' for the '''baseline''' set at 60%, the chart portion looks like this:
 +
 
 +
<center>[[File:P70-10_5_1-(10)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(10)-06022020.png</center>-->
 +
 
 +
===Change Baseline Color===
 +
 
 +
You can also make the '''baseline''' any '''color''' different from the parent task bar/milestone symbol as we did above.  To '''edit''' the '''color properties''' of the '''baseline''' follow these steps. Go to the same '''Set baseline properties''' form as described above.  Check the '''Use custom color''' checkbox '''ON'''.  Then, click the dropdown to access to the '''Color Chooser''' form as shown below:
 +
 
 +
<center>[[File:P70-10_5_1-(11)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(11)-06022020.png</center>-->
 +
 
 +
Finally, select a desired '''color''', for example, orange as used above. When the '''color''' is selected, the '''Color Chooser''' form closes and after clicking '''OK''' in the '''Set baseline properties''' form, the chart looks like this:
 +
 
 +
<center>[[File:P70-10_5_1-(12)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(12)-06022020.png</center>-->
 +
 
 +
===Connect Baselines and Actual Task Bars/Milestone Symbols===
 +
 
 +
The '''Connecting Lines''' control group in the '''Set baseline properties''' form tells the OnePager whether you want to connect '''baseline shapes''' to their task bars with a '''line'''.  This control group is shown below with its controls highlighted:
 +
 
 +
<center>[[File:P70-10_5_1-70-(11)-09162019.png]]</center>
 +
<!--<center>P70-10_5_1-70-(11)-09162019.png</center>-->
 +
 
 +
Check the '''Connect baselines and actuals''' checkbox '''ON''' to '''enable''' the control group and apply the '''default baseline connection''' settings. To change the '''color''' of the '''connecting line''', check the '''Use custom color''' checkbox '''ON'''.  Then, click the '''color''' window dropdown button to access the standard '''Color Chooser''' form.  Making a selection changes the '''color''' of the '''connecting line'''.  If you do not check this checkbox '''ON''', OnePager uses the '''color''' of the task bar/milestone symbol as the '''color''' of the '''connecting line''' segments.
 +
 
 +
To change the '''type of line segment''' ('''solid, dotted, dashed, etc.'''), click the '''Line style''' dropdown button and make your selection. Finally, you can '''edit''' the '''width''' of the '''line''' by changing the value in the '''Line width''' control window.
 +
 
 +
Click '''OK'''  on the '''Set baseline properties form''' click the '''OK''' button on the '''Chart Properties''' form to see the '''baselines''' connected to their current schedule task bars/milestone symbols as shown in the sample below:
 +
 
 +
<center>[[File:P70-10_5_1-70-(12)-09162019.png]]</center>
 +
<!--<center>P70-10_5_1-70-(12)-09162019.png</center>-->
 +
 
 +
In the sample above, two of the three orange '''baselines''' are '''connected''' to their respective task bars with a '''red dash-dot line''' that was '''widened''' to '''2.0'''  to enhance visibility. The third '''baseline''' shown above does not display a '''connecting''' like because its '''finish date''' is within the '''start/finish dates''' boundaries of its task bar.
 +
 
 +
===Showing Baseline Dates===
 +
 
 +
'''Baseline start/finish dates''' are automatically '''imported''' by OnePager.  The '''Baseline dates''' control group on the '''Set baseline properties''' form provides the controls for '''showing, positioning, and editing''' '''baseline dates''' near the '''baselines''' for a more detailed information of target dates:
 +
 
 +
<center>[[File:P70-10_5_1-(14)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(14)-06022020.png</center>-->
 +
 
 +
By checking the '''Show start date''' and/or '''Show finish date''' '''ON''' you can select the '''date format''' that OnePager uses in annotating the '''baseline date''', including whether or not to use the '''fiscal year'''. If you choose to show both '''start and finish dates''' the same '''date format''' is applied both.
 +
 
 +
The controls in this control group are very similar to the '''date controls''' associated with task bar/milestone symbol '''date labels''' as described in the article at: [[Labeling Task/Milestone Dates for Version 7.0 (OnePager Pro) | Labeling Task/Milestone Dates for OnePager Pro]] <!--10.1.1-70-->
 +
 
 +
A sample of the '''date''' formats from the '''Date format''' dropdown menu is shown here:
 +
 
 +
<center>[[File:P70-10_5_1-(15)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(15)-06022020.png</center>-->
 +
 
 +
To specify the location of the '''baseline (date) label/text''', relative to the '''baseline''', use the dropdown menu shown below from the '''Baseline dates''' group:
 +
 
 +
<center>[[File:P70-10_5_1-(16)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(16)-06022020.png</center>-->
 +
 
 +
Some care needs to be taken when determining the positions of '''baseline start/finish dates''' as the settings discussed here are '''global''' setting and may result in the '''baseline start/finish date label/text colliding''' with other '''label information''' on the chart. When these '''baseline start/finish date label/text collisions''' do occur they can be corrected by individual '''editing''' of the '''baseline properties''' associated with the offending tasks.
 +
 
 +
For more information on '''Editing''' individual task bar '''baseline properties''', please see the section in the article at: [[Baselines for OnePager for Version 7.1#Editing Individual Task/Milestone Baseline Properties | Editing Individual Task/Milestone Baseline Properties]] 10.5.1-71
 +
 
 +
The '''Use fiscal year''' checkbox in the '''Baseline dates''' control group is an instruction, if checked '''ON''', tells OnePager to show the displayed '''baseline date''' in the '''fiscal year''' format in coordination with the chart’s '''time axis'''.  OnePager takes the action only if the '''time axis''' is, indeed, displaying the '''time axis''' in a '''fiscal year''' format.  To '''edit the '''font properties''' for '''baseline start/finish dates''', click the '''Date font''' dropdown button.  This accesses the '''Font properties''' form.  The controls in this form are the same as the controls for '''editing''' any '''label/text font''' in OnePager. 
 +
 
 +
The '''Font properties''' form is shown below:
 +
 
 +
<center>[[File:P70-10_5_1-(17)-06022020.png]]</center>
 +
<!--<center>P70-10_5_1-(17)-06022020.png</center>-->
 +
 
 +
The chart below is an example of positioning '''baseline start''' and '''finish dates''' below the '''baseline''':
 +
 
 +
<center>[[File:P70-10_5_1-70-(17)-09162019.png]]</center>
 +
<!--<center>P70-10_5_1-70-(17)-09162019.png</center>-->
 +
 
 +
==Editing Individual Task/Milestone Baseline Properties==
 +
 
 +
The default settings for displaying '''baseline information''' for individual task bars/milestone symbols can be '''edited''' by using the following steps:
 +
 
 +
===Selecting Individual Task Bar or Bars===
 +
 
 +
Before you can do so, you must confirm that the '''Baseline markers''' checkbox in either the '''Template Properties''' or '''Chart Properties''' form's '''Task Bars''' and/or '''Milestones''' tab is checked '''ON'''. You can select the task bar by right-clicking on it to access the task bar right-click '''context menu''' with the '''Format…''' command, right-clicking on the '''task bar name label''', or click the '''Format…''' button on the OnePager '''Home''' ribbon tool bar tab after selecting the desired task bars/milestone symbols.
  
 
===Accessing the Change Task/Milestone Properties Form===
 
===Accessing the Change Task/Milestone Properties Form===
  
Using any of the available method, click the '''Format...''' command to access the '''Change Task/Milestone Properties''' form.  Then, navigate to the '''Percent Complete''' tab in the '''Change Task/Milestone Properties''' form which looks like this:
+
Using any of the available method to select, click the '''Format...''' command to access the '''Change Task/Milestone Properties''' form.  Then, navigate to the '''Baselines''' tab in the '''Change Task/Milestone Properties''' form which looks like this:
  
<center>[[File:P70-10_3_1-(4)-06012020.png]]</center>
+
<center>[[File:P70-10_5_1-(18)-06022020.png]]</center>
<!--<center><P70-10_3_1-(4)-06012020.png></center>-->
+
<!--<center>P70-10_5_1-(18)-06022020.png</center>-->
  
====Percent Complete Tab Editing Controls====
+
====Baseline Tab Editing Controls====
  
Go to the '''Percent Complete''' tab as shown above controlling the display of the '''Percent complete''' (%) bar on the selected task bar and the placement of the numeric '''label/text''' for '''Percent complete''' information. The '''Show Percent Complete''' checkbox allows you to turn '''ON''' and '''OFF''' the display of '''Percent complete''' information for the selected task bar. When the '''Show Percent Complete''' checkbox is checked '''ON''', you have the option to display either the '''Percent Complete''' bar within the selected task bar or the '''Percent Complete numeric label/text''' or both by checking the appropriate checkboxes '''ON''' as illustrated above. Clicking the '''%Complete Font''' dropdown button at the '''Percent Complete''' tab of the '''Change Task/Milestone Properties''' form accesses the standard '''Font properties''' form so you can '''edit''' the '''Font properties''' of the '''%Complete label''' and numeric label/text.
+
The '''Baselines''' tab, shown above, controls the display of the '''baseline dates''' and '''connectors''' for the selected task bar/milestone symbol and the placement of the numeric label/text (dates) for '''baseline''' information. The '''Show Baseline''' checkbox allows you to turn '''ON''' and '''OFF''' the display of '''baseline''' information for the selected task bar/milestone symbol. When the '''Show Baseline''' checkbox is checked '''ON''', you have the option to specify the display of the '''connector''' and the display of '''baseline start and baseline finish dates''' or both for the selected task bar/milestone symbol. When the '''Show Baseline Start Date''' checkbox is checked '''ON''' or when the '''Show Baseline Finish Date''' checkbox is checked '''ON''' (or both) you have access to control over the '''date positions''' and '''font properties''' as discussed above related to modifying all task bar/milestone symbol '''baseline information'''.
  
====Use %Complete Defaults====
+
====Use Baseline Defaults====
  
Clicking the '''Use %Complete Defaults''' button in the '''Percent Complete''' tab of the '''Change Task/Milestone Properties''' form resets all '''format properties of the selected '''percent complete label/text''' back to the settings established in the '''Chart Properties''' form. The '''Use %Complete Defaults''' button looks like this:
+
Clicking the '''Use Baseline Defaults''' button in the '''Baselines''' tab of the '''Change Task/Milestone Properties''' form resets all '''format properties of the selected '''date label or labels''' back to the settings established in the '''Chart Properties''' form. The '''Use Baseline Defaults''' button looks like this:
  
<center>[[File:P70-10_3_1-(4A)-06012020.png]]</center>
+
<center>[[File:P70-10_5_1-(19)-06022020.png]]</center>
<!--<center><P70-10_3_1-(4A)-06012020.png></center>-->
+
<!--<center>P70-10_5_1-(19)-06022020.png</center>-->
  
 
===Example===
 
===Example===
  
As an example, if all task bars are globally set '''not''' to display '''percent-complete''', (1) we can select a particular task bar with a right-click, (2) navigate to the '''Percent-complete''' tab on the '''Change Task/Milestone Properties''' form, (3) set the appropriate checkbox '''ON''' to display '''percent-complete text''', and (4) position the '''percent-complete label/text''' into the boundaries of the task bar itself as shown below:
+
Below is an example of a single task bar’s '''baseline information''' modified:
  
<center>[[File:P70-10_3_1-(5)-06012020.png]]</center>
+
<center>[[File:P70-10_5_1-70-(19)-09172019.png]]</center>
<!--<center><P70-10_3_1-(5)-06012020.png></center>-->
+
<!--<center>P70-10_5_1-70-(19)-09172019.png</center>-->
  
With the '''Show %Complete Label''' checkbox '''ON''', OnePager displays the numeric value of the '''Percent complete''' in the position you determine by selecting an option from the dropdown menu to the right of the '''Show %Complete Label''' checkbox. When you click the '''OK''' button on the '''Change Task/Milestone Properties''' form, the '''edited''' task bar looks like this:
+
The controls at the '''Baselines''' tab of the '''Change Task/Milestone Properties''' form for '''Show Baseline Start Date''' and '''Show Baseline Finish Date''', that is, the '''Position''' and '''Font''' controls operate exactly as described for other '''start/finish date''' displays in OnePager. 
  
<center>[[File:P70-10_3_1-(6)-06012020.png]]</center>
+
For more information on '''Percent Complete tab of this form''', please see the section of this article at: [[Percent complete for OnePager for Version 7.1#Example | Percent complete for OnePager - Example]] 10.3.1-71
<!--<center><P70-10_3_1-(6)-06012020.png></center>-->
+
  
===Resetting Default Properties for Mavericked Task Shape===
+
There are no controls available in the '''Baseline''' tab of the '''Change Task/Milestone Properties''' form to '''edit''' the properties of the '''connector line''' for an '''individually''' selected task bar/milestone symbol.
  
The '''Use %Complete Defaults''' button bar, when clicked, changes the task’s '''%Complete properties''' to those currently specified as global in the current '''Template''' form.
+
==Related Link==
  
==Related Links==
+
[[Manual Editing Task/Milestone Shapes and Text Labels for Version 7. (Portal) | Manual Editing Task/Milestone Shapes and Text Labels (Portal)]] 9.0.1-71
 +
 
 +
[[Changing Individual Task/Milestone Properties (Color, Shape, Labels, etc.) for Version 7.0 | Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.)]] 9.2.1-70
  
 
[[Labeling Task/Milestone Dates for OnePager for Version 7.1 | Labeling Task/Milestone Dates for OnePager]] 10.1.1-71
 
[[Labeling Task/Milestone Dates for OnePager for Version 7.1 | Labeling Task/Milestone Dates for OnePager]] 10.1.1-71
  
[[Managing Working Hours and Non-Working Hours for OnePager Pro for Version 7.0 | Managing Working Hours and Non-Working Hours for OnePager Pro]] 22.5.3-70
+
[[Percent complete for OnePager for Version 7.1 | Percent complete for OnePager]] 10.3.1-71
 +
 
 +
[[Editing with the Chart Properties form for Version 7.1 (Portal) | Editing with the Chart Properties form (Portal)]] 21.0.1-71
 +
 
 +
[[Managing Templates for Version 7.1 (Portal) | Managing Templates (Portal)]] 24.0.1-71
  
(10.3.1-71)
+
(10.5.1-71)
  
 
[[Category:Version 7.1]]
 
[[Category:Version 7.1]]
Line 111: Line 205:
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Editing]]
 
[[Category:Task/Milestone Decorations]]
 
[[Category:Task/Milestone Decorations]]
[[Category:Percent Complete]]
+
[[Category:Baselines]]
[[Category:Working Times]]
+
[[Category:Non-Working Times]]
+
 
[[Category:Mavericks]]
 
[[Category:Mavericks]]
 
[[Category:OnePager Pro]]
 
[[Category:OnePager Pro]]
 
[[Category:OnePager Express]]
 
[[Category:OnePager Express]]
 
[[Category:OnePager 360]]
 
[[Category:OnePager 360]]

Revision as of 16:35, 19 February 2021

Introduction to the Baselines Feature in OnePager

This article describes OnePager’s Baselines feature. The article covers the Add-in and Standalone editions of OnePager Pro, OnePager Express, and OnePager 360. Illustrations used in this article are from OnePager Pro but the feature's function, controls, and manual edits apply equally to OnePager Express and OnePager 360.

About Editing Baselines

Baseline property displays are driven by the baseline start and finish dates imported from the Microsoft Project source plan. Not every task bar/milestone symbol in a Microsoft Project source plan has designated baseline start and finish dates. A milestone symbols’ start and finish dates are usually the same. When you need to display baseline property information, it is essential that the associated data be properly represented in your source plan before the data are imported to OnePager.

Editing All Task/Milestone Baseline Properties

All task bars and milestone symbol baseline properties can be modified without changing the settings in the current Template Properties form by clicking the Chart Properties button on the OnePager Home ribbon tool bar tab in the Settings group. Next, navigate to either the Task Bars or Milestones tab as appropriate and ensure that the Baseline markers checkbox is checked ON as shown below:

P70-10 5 1-(1-1)-06022020.png

Once the Baseline markers checkbox is checked ON, baselines can be customized by clicking the Baseline Properties button which accesses the Set baseline properties form shown here:

P70-10 5 1-(2)-06022020.png

You can now edit baseline properties for task bars/milestone symbols using the Set Baseline Properties form.

Change Baseline Shape

The controls for changing the shape of the baseline are the same as for task bars/milestone symbols discussed in this article at: Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.) 9.2.1-70

The baseline shapes available are the same as for task bars/milestone symbols as shown in the Set baseline properties form below:

P70-10 5 1-(3)-06022020.png

There are numerous baseline shapes that can be selected. Use the scroll bar on the right of the dropdown list to make your selection. When the selection is made, either continue to make additional properties changes or click the OK button to get back to the Chart Properties form where all edits are applied.

Change Baseline Fill Pattern

In a fashion very similar to the way fill patterns are changed for task bars/milestone symbols, once again access the Set baseline properties form as before, navigate to the Use custom fills checkbox, check it ON to enable the dropdown, and use the associated dropdown list to make your selection as shown below:

P70-10 5 1-(4)-06022020.png

When the selection is made, either continue to make additional properties changes or click the OK button to get back to the Chart Properties form where all changes can be applied.

Change Baseline Height Percentage

The Height percentage control is located just below the Baseline custom shape dropdown. This control, shown above, allows you to change the height of the baseline as a percentage of the total height of the parent task bar/milestone symbol (task and baseline information included). The default setting is 30 percent (%) and a portion of the chart with baselines checked ON looks like this:

Baseline Shapes with 30 Percent Height Setting
P70-10 5 1-(5)-06022020.png

Increasing this value makes the baseline taller (higher) with respect to the task bar/milestone symbol. To change the value, navigate to the Height percentage control in the Specify how to display baseline properties control group of the Set baseline properties form. Change the value with the controls provided. If you double the value to 60 percent, for example, the resulting baselines would look like this:

Baseline Shapes with 60 Percent Height Setting
P70-10 5 1-(6)-06022020.png

Change Baseline Transparency

The transparency control makes the baseline less transparent (opaque) when the value in the window of the form is decreased or as shown below where the value is set at its default of 0% (the baseline is highlighted in orange):

P70-10 5 1-(7)-06022020.png

With this setting for transparency and baseline shape color, the chart portion looks like this:

P70-10 5 1-(8)-06022020.png

When you need to make the baseline shape more transparent increase the percentage value as shown below where the value is increased to 60%:

P70-10 5 1-(9)-06022020.png

With the transparency for the baseline set at 60%, the chart portion looks like this:

P70-10 5 1-(10)-06022020.png

Change Baseline Color

You can also make the baseline any color different from the parent task bar/milestone symbol as we did above. To edit the color properties of the baseline follow these steps. Go to the same Set baseline properties form as described above. Check the Use custom color checkbox ON. Then, click the dropdown to access to the Color Chooser form as shown below:

P70-10 5 1-(11)-06022020.png

Finally, select a desired color, for example, orange as used above. When the color is selected, the Color Chooser form closes and after clicking OK in the Set baseline properties form, the chart looks like this:

P70-10 5 1-(12)-06022020.png

Connect Baselines and Actual Task Bars/Milestone Symbols

The Connecting Lines control group in the Set baseline properties form tells the OnePager whether you want to connect baseline shapes to their task bars with a line. This control group is shown below with its controls highlighted:

P70-10 5 1-70-(11)-09162019.png

Check the Connect baselines and actuals checkbox ON to enable the control group and apply the default baseline connection settings. To change the color of the connecting line, check the Use custom color checkbox ON. Then, click the color window dropdown button to access the standard Color Chooser form. Making a selection changes the color of the connecting line. If you do not check this checkbox ON, OnePager uses the color of the task bar/milestone symbol as the color of the connecting line segments.

To change the type of line segment (solid, dotted, dashed, etc.), click the Line style dropdown button and make your selection. Finally, you can edit the width of the line by changing the value in the Line width control window.

Click OK on the Set baseline properties form click the OK button on the Chart Properties form to see the baselines connected to their current schedule task bars/milestone symbols as shown in the sample below:

P70-10 5 1-70-(12)-09162019.png

In the sample above, two of the three orange baselines are connected to their respective task bars with a red dash-dot line that was widened to 2.0 to enhance visibility. The third baseline shown above does not display a connecting like because its finish date is within the start/finish dates boundaries of its task bar.

Showing Baseline Dates

Baseline start/finish dates are automatically imported by OnePager. The Baseline dates control group on the Set baseline properties form provides the controls for showing, positioning, and editing baseline dates near the baselines for a more detailed information of target dates:

P70-10 5 1-(14)-06022020.png

By checking the Show start date and/or Show finish date ON you can select the date format that OnePager uses in annotating the baseline date, including whether or not to use the fiscal year. If you choose to show both start and finish dates the same date format is applied both.

The controls in this control group are very similar to the date controls associated with task bar/milestone symbol date labels as described in the article at: Labeling Task/Milestone Dates for OnePager Pro

A sample of the date formats from the Date format dropdown menu is shown here:

P70-10 5 1-(15)-06022020.png

To specify the location of the baseline (date) label/text, relative to the baseline, use the dropdown menu shown below from the Baseline dates group:

P70-10 5 1-(16)-06022020.png

Some care needs to be taken when determining the positions of baseline start/finish dates as the settings discussed here are global setting and may result in the baseline start/finish date label/text colliding with other label information on the chart. When these baseline start/finish date label/text collisions do occur they can be corrected by individual editing of the baseline properties associated with the offending tasks.

For more information on Editing individual task bar baseline properties, please see the section in the article at: Editing Individual Task/Milestone Baseline Properties 10.5.1-71

The Use fiscal year checkbox in the Baseline dates control group is an instruction, if checked ON, tells OnePager to show the displayed baseline date in the fiscal year format in coordination with the chart’s time axis. OnePager takes the action only if the time axis is, indeed, displaying the time axis in a fiscal year format. To edit the font properties for baseline start/finish dates, click the Date font dropdown button. This accesses the Font properties form. The controls in this form are the same as the controls for editing any label/text font in OnePager.

The Font properties form is shown below:

P70-10 5 1-(17)-06022020.png

The chart below is an example of positioning baseline start and finish dates below the baseline:

P70-10 5 1-70-(17)-09162019.png

Editing Individual Task/Milestone Baseline Properties

The default settings for displaying baseline information for individual task bars/milestone symbols can be edited by using the following steps:

Selecting Individual Task Bar or Bars

Before you can do so, you must confirm that the Baseline markers checkbox in either the Template Properties or Chart Properties form's Task Bars and/or Milestones tab is checked ON. You can select the task bar by right-clicking on it to access the task bar right-click context menu with the Format… command, right-clicking on the task bar name label, or click the Format… button on the OnePager Home ribbon tool bar tab after selecting the desired task bars/milestone symbols.

Accessing the Change Task/Milestone Properties Form

Using any of the available method to select, click the Format... command to access the Change Task/Milestone Properties form. Then, navigate to the Baselines tab in the Change Task/Milestone Properties form which looks like this:

P70-10 5 1-(18)-06022020.png

Baseline Tab Editing Controls

The Baselines tab, shown above, controls the display of the baseline dates and connectors for the selected task bar/milestone symbol and the placement of the numeric label/text (dates) for baseline information. The Show Baseline checkbox allows you to turn ON and OFF the display of baseline information for the selected task bar/milestone symbol. When the Show Baseline checkbox is checked ON, you have the option to specify the display of the connector and the display of baseline start and baseline finish dates or both for the selected task bar/milestone symbol. When the Show Baseline Start Date checkbox is checked ON or when the Show Baseline Finish Date checkbox is checked ON (or both) you have access to control over the date positions and font properties as discussed above related to modifying all task bar/milestone symbol baseline information.

Use Baseline Defaults

Clicking the Use Baseline Defaults button in the Baselines tab of the Change Task/Milestone Properties form resets all format properties of the selected date label or labels back to the settings established in the Chart Properties form. The Use Baseline Defaults button looks like this:

P70-10 5 1-(19)-06022020.png

Example

Below is an example of a single task bar’s baseline information modified:

P70-10 5 1-70-(19)-09172019.png

The controls at the Baselines tab of the Change Task/Milestone Properties form for Show Baseline Start Date and Show Baseline Finish Date, that is, the Position and Font controls operate exactly as described for other start/finish date displays in OnePager.

For more information on Percent Complete tab of this form, please see the section of this article at: Percent complete for OnePager - Example 10.3.1-71

There are no controls available in the Baseline tab of the Change Task/Milestone Properties form to edit the properties of the connector line for an individually selected task bar/milestone symbol.

Related Link

Manual Editing Task/Milestone Shapes and Text Labels (Portal) 9.0.1-71

Changing Individual Task/Milestone Properties (Color, Shapes, Labels, etc.) 9.2.1-70

Labeling Task/Milestone Dates for OnePager 10.1.1-71

Percent complete for OnePager 10.3.1-71

Editing with the Chart Properties form (Portal) 21.0.1-71

Managing Templates (Portal) 24.0.1-71

(10.5.1-71)